Telephone call | | | 5/21/2015 | | |
|
|
|
called Jim to let know that since Gordon Clark no longer works for him he will need a new RP
|
BLD-Framing/Rough-in | 12/9/2014 | 12/10/2014 | 12/10/2014 | A | PASS |
Tony Young
|
|
|
Gordon Phone #: ###-####,, frame work per plans, ok
|
BLD-Other | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PASS |
Jim Storey
|
|
|
REBAR//GORDON Phone #: ###-####
|
BLD-Footing | 11/12/2014 | 11/13/2014 | 11/13/2014 | P | NR |
Jim Storey
|
|
|
Gordon Phone #: ###-####
|
BLD-Conference | 11/10/2014 | 11/12/2014 | 11/12/2014 | A | PASS |
Jim Storey
|
|
|
Gordon Phone #: ###-####
|
BLD-Conference | 11/7/2014 | 11/7/2014 | 11/7/2014 | P | PASS |
Jim Storey
|
|
|
Gordon Phone #: ###-####
|
OVERRIDE | | | 11/6/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 11/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 11/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (CDM) | 9/9/2014 | 9/9/2014 | 10/28/2014 | | PASS |
Carl D Madsen
|
|
|
Addition - ePlanReview - Glaztech Industries
First review completed.
|
Routing PW Drainage | 10/24/2014 | | 10/28/2014 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2014 | | DONE |
|
|
|
|
Routing PW Drainage | 10/3/2014 | | 10/13/2014 | | FAIL |
Jason C. Taylor
|
|
|
NEEDS GEOTECH
|
Routing - MECHANICAL | 10/6/2014 | | 10/8/2014 | | PASS |
Troy James
|
|
|
Gas blower furnace is electric.
|
Routing - FIRE | 10/3/2014 | 10/3/2014 | 10/6/2014 | | PASS |
|
|
|
See Fire Plan Review Rev 1 10-06-14
|
Routing - PLAN CHECK | 10/3/2014 | | 10/6/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2014 | | 10/3/2014 | | PASS |
Beverly Mountain
|
|
|
|
Route to Impact Fee Review | 9/23/2014 | 9/26/2014 | 9/26/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 9/9/2014 | | 9/23/2014 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 9/23/2014 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 9/9/2014 | | 9/23/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 9/9/2014 | | 9/15/2014 | | FAIL |
Brian Murphy
|
|
|
See changemarks in ePlan. JCT
|
Routing - Design Review | 9/9/2014 | | 9/12/2014 | | PASS |
Josh Wilson
|
|
|
Ok per DRH14-00286
|
Routing - FIRE | 9/9/2014 | 9/9/2014 | 9/11/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-11-14
|
Routing PW Environmental | 9/9/2014 | | 9/10/2014 | | PASS |
Rick Christenson
|
|
|
|
Pending Assignment by JCB | 9/9/2014 | | 9/9/2014 | | DONE |
Jason Blais
|
|
|
|
Routing - PLANNING Land Div | 9/9/2014 | | 9/9/2014 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 9/9/2014 | | 9/9/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/9/2014 | | 9/9/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/9/2014 | | 9/9/2014 | | PASS |
Evan Jenkins
|
|
|
Approved with the submitted SWPPP: Not ESC Waiver
Site Prep Inspection Required Prior to any Earth Disturbance
|
Intake Approval | | | 9/5/2014 | | PASS |
Carl Westfall
|
|
|
Plan intake review approved
|
Intake Approval | | | 8/22/2014 | | FAIL |
|
|
|
Need the structural calculations for the engineered building.
|
Intake Approval | | | 8/13/2014 | | FAIL |
|
|
|
Please see the "red lines" on the plan intake checklist and provide the required drawings and/or documents.
|
Application received | | | 8/12/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 12 2014 4:32PM
|