Second Notice | | 12/13/2014 | 12/22/2014 | | DONE |
Kristal Soland
|
|
|
|
Print Statement | | | 12/22/2014 | | DONE |
|
|
|
|
First Notice | | 11/23/2014 | 12/3/2014 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/13/2014 | 11/13/2014 | 11/13/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Duct smoke detector relocated to return ducting
|
BLD-Final | 11/5/2014 | 11/6/2014 | 11/13/2014 | A | NR |
Jim Sly
|
|
|
MArk Phone #: ###-####
|
BLD-Final | 11/13/2014 | 11/13/2014 | 11/13/2014 | A | PASS |
Jim Sly
|
|
|
Mark ###-####-8573
|
Permanent Occupancy | | | 11/13/2014 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/5/2014 | 11/6/2014 | 11/6/2014 | A | FAIL |
Forrest France
|
|
|
AM inspection completed by T. Cobbley- items noted include; provide adequate location for the duct detector or verification min. airflow is met, missing signal transmission to offsite monitoring station, test switch is located at the roof deck.
|
BLD-Final | 11/4/2014 | 11/5/2014 | 11/6/2014 | A | NR |
Jim Sly
|
|
|
Mark Phone #: ###-#### Waiting for fire........
|
FIRE-Final Inspection | 11/4/2014 | 11/5/2014 | 11/5/2014 | A | FAIL |
Troy Cobbley
|
|
|
Contractor was not ready to test the duct smoke detector. Emergency lights have been repaired.
|
BLD-Final | 11/3/2014 | 11/4/2014 | 11/5/2014 | A | CANC |
Jim Sly
|
|
|
Mark Phone #: ###-####
|
FIRE-Final Inspection | 11/3/2014 | 11/4/2014 | 11/4/2014 | A | FAIL |
Troy Cobbley
|
|
|
Not ready due to missing ballasts. Mark is going to reschedule.
|
BLD-Final | 10/31/2014 | 11/3/2014 | 11/3/2014 | P | CANC |
Jim Sly
|
|
|
Mark Phone #: ###-####
|
FIRE-Final Inspection | 10/31/2014 | 11/3/2014 | 11/3/2014 | A | FAIL |
Troy Cobbley
|
|
|
Provide door hardware as discussed, provide fire sprinkler inspection for outstanding permit, provide fire alarm modifications for the duct smoke detectors (see mechanical drawings), repair the emergency lights and provide missing exit sign.
|
BLD-Ceiling Grid Inspection | 10/22/2014 | 10/23/2014 | 10/23/2014 | A | PART |
Jim Sly
|
|
|
Mark Phone #: ###-#### 90 percent complete
|
BLD-Framing/Rough-in | 10/21/2014 | 10/21/2014 | 10/22/2014 | P | PASS |
Jim Sly
|
|
|
mark Phone #: ###-####
|
BLD-Framing/Rough-in | 10/6/2014 | 10/7/2014 | 10/7/2014 | A | PART |
Jim Sly
|
|
|
partial framing // Mark Phone #: ###-#### Long East to West wall, Sm. room at N. E. corner and portions of exterior walls.......OK to cover.
|
Issue PAID IN FULL permit | | | 9/29/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (SRZ) | 8/22/2014 | 8/22/2014 | 9/15/2014 | | PASS |
Sam Zahorka
|
|
|
Level 3 TI - Paper - Dollar Tree
|
Routing - FIRE | 9/11/2014 | | 9/15/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-15-14
|
Routing - PLAN CHECK | 9/15/2014 | | 9/15/2014 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 9/15/2014 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2014 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 9/15/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 9/15/2014 | | DONE |
|
|
|
spoke with Devin-told him we need GC and ACHD approval letter
|
Permit Ready to Issue | | | 9/15/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 9/4/2014 | | 9/11/2014 | | PEND |
Sam Zahorka
|
|
|
|
Routing - Design Review | 9/11/2014 | | 9/11/2014 | | PASS |
Josh Wilson
|
|
|
Ok per CZC14-00265
|
Routing - PLAN CHECK | 9/11/2014 | | 9/11/2014 | | PASS |
Sam Zahorka
|
|
|
|
Case Summary (BLD) | | | 9/11/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - Design Review | 8/27/2014 | | 9/3/2014 | | FAIL |
Sarah Schafer
|
|
|
CZC needed for exterior storefront changes
|
Routing - PLUMBING | 8/26/2014 | | 8/27/2014 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Rating | 8/26/2014 | | 8/26/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 8/25/2014 | | 8/26/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 8/22/2014 | | 8/25/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Pending Assignment by JCB | 8/21/2014 | | 8/22/2014 | | DONE |
Jason Blais
|
|
|
|
Application received | | 8/15/2014 | 8/21/2014 | | DONE |
|
|
|
via mail
|
Intake Approval | | | 8/21/2014 | | PASS |
Sam Zahorka
|
|
|
Prescreen approved by Sam Zahorka 8/15/14 and plan review fees paid on 8/21/14.
|
Plans ACCEPTED BY PLAN TECH | | | 8/21/2014 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/21/2014 | | DONE |
Tisha Gallop
|
|
|
|