Telephone call | | | 1/6/2016 | | DONE |
|
|
|
emailed Able that there are no final values required for grading permits.
|
Print Statement | | | 12/28/2015 | | DONE |
|
|
|
|
Third Notice | | 11/14/2015 | 12/10/2015 | | DONE |
|
|
|
|
Third Notice | | 10/17/2015 | 11/9/2015 | | DONE |
|
|
|
|
Second Notice | | 9/25/2015 | 10/12/2015 | | DONE |
|
|
|
Mailed 10-13-15
|
First Notice | 8/25/2015 | 8/25/2015 | 9/15/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed 9-15-15
|
BLD-Final | 8/25/2015 | 8/25/2015 | 8/25/2015 | A | DONE |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety inspection passed/complete
|
BLD-Final | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-####
|
FIRE-Final Inspection | 8/19/2015 | 8/19/2015 | 8/19/2015 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire dept access signage as per note #12. All other items appear ok.
|
FIRE-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | CANC |
Jim Page
|
|
|
Tom Phone #: ###-####
|
PubWorks Occupancy Approval | 8/12/2015 | 8/12/2015 | 8/12/2015 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 8/10/2015 | 8/11/2015 | 8/11/2015 | A | NR |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
BLD-Conference | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
Routing - FIRE | 11/17/2014 | 11/17/2014 | 11/18/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Mod Rev 1 11-18-14
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2014 | | DONE |
|
|
|
approved plan mod
|
CHANGE STATUS TO (ISS) | | | 11/18/2014 | | DONE |
|
|
|
batch stamped approved plan mod, no fees due.
|
Plan assigned to (LEG) Tisha | 10/28/2014 | | 11/18/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod; 11/4/14 failed fire
|
Plan resubmittals received | | | 11/17/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/17/2014 | | 11/17/2014 | | PASS |
Tisha Gallop
|
|
|
Tisha
|
Routing PW Solid Waste | 10/28/2014 | | 11/4/2014 | | PASS |
Peter J. McCullough
|
|
|
per ePlan
|
Routing - PUBLIC WORKS | 10/28/2014 | | 11/4/2014 | | PASS |
Tisha Gallop
|
|
|
Per ePlan
|
Routing - FIRE | 10/28/2014 | 10/28/2014 | 11/3/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review Mod 11-03-14
|
Routing PW Environmental | 10/28/2014 | | 11/3/2014 | | PASS |
Rick Christenson
|
|
|
per ePlan
|
Routing PW Sewer Design | 10/28/2014 | | 10/30/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - Design Review | 10/28/2014 | | 10/29/2014 | | PASS |
Cody Riddle
|
|
|
The project is not located in a DR overlay, so their approval is not required. CER
|
Routing - Erosion and Sediment | 10/28/2014 | | 10/29/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection Already Performed. A new aircraft maintenance hangar building with office space and warehouse space attached. Sitework includes utilities, parking, airplane apron and landscaping. 134,000 SF Maintanence Hanger
|
Routing PW Drainage | 10/28/2014 | | 10/29/2014 | | PASS |
Brian Murphy
|
|
|
|
Plan Modification Accepted | | | 10/28/2014 | | DONE |
|
|
|
plan mod workflow started.
|
Routing - PLAN CHECK | 10/28/2014 | | 10/28/2014 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLUMBING | 10/28/2014 | | 10/28/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Issue PAID IN FULL permit | | | 9/30/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 9/30/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 9/29/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 9/29/2014 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing PW Drainage | 9/17/2014 | | 9/26/2014 | | PASS |
Brian Murphy
|
|
|
|
Plan assigned to (LEG) Tisha | 9/2/2014 | | 9/26/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing PW Sewer Design | 9/25/2014 | | 9/25/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - FIRE | 9/17/2014 | 9/17/2014 | 9/18/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 09-18-14
|
Routing PW Sewer Design | 9/17/2014 | | 9/17/2014 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add pipe support to pressure line inside manhole (Stainless steel straps or equivalent).
Label existing manhole: MH 360N8.
Contact Boise public works 48 hours prior to instruction to obtain tap permit and schedule inspection.
|
Plan resubmittals received | | | 9/17/2014 | | DONE |
Tisha Gallop
|
|
|
ePlan
|
Routing - PLAN CHECK | 9/17/2014 | | 9/17/2014 | | PASS |
Tisha Gallop
|
|
|
|
1st review completed | | | 9/2/2014 | | DONE |
Tisha Gallop
|
|
|
failed Sewer Design, Drainage, Fire
|
Routing PW Solid Waste | 8/20/2014 | | 9/2/2014 | | PASS |
Peter J. McCullough
|
|
|
passed in e-plan
|
Routing PW Environmental | 8/20/2014 | | 9/2/2014 | | PASS |
Rick Christenson
|
|
|
passed in e-plan
|
Routing PW Street Lights | 8/20/2014 | | 9/2/2014 | | CANC |
Mike D Hedge
|
|
|
no reveiw per e-plan
|
Plan assigned to (CAN) Candy | 8/20/2014 | | 9/2/2014 | | DEFR |
Candy A. Nichols
|
|
|
defr to Tisha Gallop
|
Routing - FIRE | 8/20/2014 | 8/20/2014 | 8/29/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 08-29-14
|
Routing PW Drainage | 8/20/2014 | | 8/26/2014 | | FAIL |
Brian Murphy
|
|
|
need drainage report
|
Routing PW Sewer Design | 8/20/2014 | | 8/21/2014 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Discharge manhole must be coated with T-Lock, Sauereisen, or Spray Rock protective coatings. Show profile for force main. Place Air-Release Valves at high points per SD-513. Place Location Wire Boxes in 1000' intervals per SD-514. Install Pressure Sewer Cleanouts per SD-515 in the ISPWC. Install dry service line (size dictated by mechanical drawings) to the southern edge of site improvements for future gravity sewer service from Gowen Road. Use minimum slopes for service line. Cap and mark service line with finder wire per SD-512.
|
Routing PW Sewer Rating | 8/20/2014 | | 8/21/2014 | | PASS |
Beverly Mountain
|
|
|
Waiting for full plans to submit fees. bam
|
Routing - PLANNING | 8/20/2014 | | 8/21/2014 | | PASS |
Sarah Schafer
|
|
|
Approved for earthwork only. CER
Parking lot and utilities okay for construction. The 9/8/14 CUP hearing is only for the height of the proposed aircraft hangar. The other improvments are allowed
|
Routing - Erosion and Sediment | 8/20/2014 | | 8/21/2014 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLANNING Land Div | 8/20/2014 | | 8/20/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 8/20/2014 | | 8/20/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLAN CHECK | 8/20/2014 | | 8/20/2014 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLUMBING | 8/20/2014 | | 8/20/2014 | | PASS |
Daryl Spivey
|
|
|
|
Telephone call | | | 8/19/2014 | | DONE |
Candy A. Nichols
|
|
|
called Tracey twice-need to know the correct valuation for just this part of the project. Left message both times
|
Intake Approval | | | 8/19/2014 | | PASS |
Candy A. Nichols
|
|
|
|
Application received | | | 8/18/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 18 2014 2:44PM
|