(F) Reprint permit | | | 9/2/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/1/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/24/2015 | | DONE |
|
|
|
|
BLD-Final | 7/24/2015 | 7/24/2015 | 7/24/2015 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 7/24/2015 | 7/24/2015 | 7/24/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | FAIL |
Mike Jordan
|
|
|
would like call ahead; Sydney Phone #: ###-####.. provide the required energy cert and post. Provide the blower door test result or the 3rd. party airseal inspection report and post. Also need to verify tempered glazing at front door. Correction notice posted.
|
BLD-Energy code compliance | 4/7/2015 | 4/8/2015 | 4/8/2015 | A | PASS |
Mike Jordan
|
|
|
Steven-please call prior Phone #: ###-####
|
BLD-Framing/Rough-in | 4/1/2015 | 4/1/2015 | 4/1/2015 | P | PASS |
Mike Jordan
|
|
|
All framing issues have been resolved.
|
BLD-Energy code compliance | 4/1/2015 | 4/1/2015 | 4/1/2015 | P | FAIL |
Mike Jordan
|
|
|
Insulation // Bob Phone #: ###-####. Provide R30 insulation at 2nd. story floor in garage.
|
BLD-Framing/Rough-in | 3/26/2015 | 3/27/2015 | 3/27/2015 | A | FAIL |
Mike Jordan
|
|
|
Please call ahead for access - Bob Phone #: ###-####. COmplete interior wal bracing, Provide additional truss hangars were missed, nail of all 2 and 3 ply girder trusses, this was completed while on site. Ok to insulate. Squash block at rough sawn lumber.
|
BLD-Wall Bracing | 3/27/2015 | 3/27/2015 | 3/27/2015 | A | PASS |
Mike Jordan
|
|
|
Please call ahead for access - Bob Phone #: ###-####
|
BLD-Foundation | 1/29/2015 | 1/29/2015 | 1/29/2015 | P | PART |
Mike Jordan
|
|
|
Ben Phone #: ###-####
|
BLD-Footing | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | PART |
Mike Jordan
|
|
|
Jay Phone #: ###-####. No approved plan on site. Told Jay ok to place, have approved plans for foundation inspection. Any descrencies will be repaired.
|
Issue PAID IN FULL permit | | | 1/20/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/20/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 10/28/2014 | | |
|
|
|
|
Plan assigned to (JG) | 9/12/2014 | 9/12/2014 | 10/28/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Pending Mech, 9/24 W L1 ePlan**
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/28/2014 | | DONE |
|
|
|
|
Routing - MECHANICAL | 10/22/2014 | | 10/27/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/22/2014 | | 10/22/2014 | | PASS |
Colleen T Carroll
|
|
|
signed off in ePlan by Colleen Carroll
|
Routing - MECHANICAL | 10/22/2014 | | 10/22/2014 | | FAIL |
Troy James
|
|
|
Comments dated 10-21-14 have not been addressed.
|
Routing - PLAN CHECK | 10/9/2014 | | 10/22/2014 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 10/21/2014 | | 10/21/2014 | | FAIL |
Troy James
|
|
|
eplan
Need to fix pressure losses design and need duct diameters shown.
|
Routing - MECHANICAL | 10/9/2014 | | 10/9/2014 | | FAIL |
Troy James
|
|
|
manual j does not match the resubmitted plans
|
Routing - PLAN CHECK | 9/24/2014 | | 10/9/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
Complete floor plan change
|
Routing Walk-In (Zoning) | 10/8/2014 | 10/8/2014 | 10/8/2014 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing - PLAN CHECK | 9/12/2014 | | 9/24/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 9/24/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 9/12/2014 | | 9/24/2014 | | FAIL |
Colleen T Carroll
|
|
|
Failed in ePlan planning review by Colleen Carroll
|
Routing - MECHANICAL | 9/12/2014 | | 9/15/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - Addressing | 9/12/2014 | | 9/12/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2014 | | 9/12/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 9/12/2014 | | PASS |
Candy A. Nichols
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/12/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 8/20/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 20 2014 10:36AM
|
Intake Approval | | | 8/20/2014 | | FAIL |
Christina Prado
|
|
|
Need engineering calcs for tall wall/bracing and Manual J
|