Permit Information
Permit NumberBLD14-02475
StatusFinaled
Name MCCARTER-MOORHOUSE LLC
Site Address 1508 S CLOVERDALE RD
Project NameBoise Tech Cafe
Customer Number 
ePlanReviewYes
Description
(BOISE TECH CAFE' - 2ND STORY) Fire sprinkler system used for story increase. To remodel the 2nd story of a new 3 story building for a 1,890 square foot restaurant and commercial kitchen. This permit is intended to establish a Certificate of Occupancy for the entire 3,902 square foot 2nd story which includes the restaurant, commercial kitchen, restrooms, and offices. The occupant load of the restaurant is limited to 58 based on the available ventilation. The restrooms were constructed under the shell permit (BLD14-00819) and are required to be accessible to the disabled. The floor between the 2nd and 3rd story, including the balconies and the supporting structure, will be upgraded to be of 1-hr fire-resistance-rated construction. The floor between the 1st and 2nd story will be structurally upgraded to have a live load capacity of 100 pounds per square foot. Other work is to include interior nonbearing walls, millwork, and kitchen equipment. The work is required to comply with the approved drawings, with the structural engineer’s calculations and design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 3/8/20153/11/2015 DONE
This permit finaled on the web by David Moorhouse
Third Notice 2/7/20153/3/2015 DONE
Second Notice 1/12/20152/2/2015 DONE
First Notice 12/25/20141/2/2015 DONE
BLD-Final12/12/201412/15/201412/15/2014APASS
DetailsMike Jordan
Final Inspection Please

Thanks David Moorhouse ###-#### Phone #: ###-#### Inspection requested via web by David Moorhouse. ok for perm occ.
Permanent Occupancy  12/15/2014 DONE
DetailsChristina Prado
FIRE-Final Inspection12/11/201412/12/201412/12/2014PPASS
DetailsTroy Cobbley
Fire life safety passed
BLD-Other10/28/201410/28/201410/28/2014APASS
DetailsMike Jordan
Please inspect 1st layer of ceiling sheetrock on 2nd floor. Please come as early as possible.

Thanks, Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Energy code compliance10/23/201410/23/201410/23/2014PPASS
DetailsDave Hannah
Please inspect Insulation

Thanks,
Dave Phone #: ###-#### Inspection requested via web by David Moorhouse
BLD-Framing/Rough-in10/20/201410/20/201410/20/2014PPASS
DetailsMike Jordan
Framing Inspection 2nd Floor location of Tech cafe

Thanks Dave Phone #: ###-#### Inspection requested via web by David Moorhouse. All framing issues on 3rd floor have been repaired, 2nd. floor framing ok to insulate. !st floor columns are now ok to cover.
Permit Ready to Issue  10/7/2014 DONE
DetailsCandy A. Nichols
Issue PAID IN FULL permit  10/7/2014 DONE
DetailsCandy A. Nichols
Print Occupancy Form  10/7/2014 DONE
DetailsCandy A. Nichols
Plan assigned to (CJW)9/3/20149/3/201410/3/2014 PASS
DetailsCarl Westfall
BOISE TECH CAFE - Level 3 TI - ePlanReview - (15 days - Sept 18) (1st review done)
Routing - PLAN CHECK9/26/2014 10/3/2014 DONE
DetailsCarl Westfall
Routing to other agencies completed
Routing PW Sewer Rating10/1/2014 10/3/2014 PASS
DetailsBeverly Mountain
(10-1-14) Use of kitchen changed so routed back for revision to sewer fees
PLANS/APPL TAKEN TO FRONT DESK  10/3/2014 DONE
Routing - MECHANICAL9/30/2014 9/30/2014 PASS
DetailsTroy James
Ventilation approved per occupant load as determined by building plan reviewer.
Routing PW Environmental9/26/2014 9/30/2014 PASS
DetailsRick Christenson
Routing - MECHANICAL9/26/2014 9/29/2014 FAIL
DetailsTroy James
emailed mechanical engineer to call me
Routing - FIRE9/26/2014 9/29/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 09-29-14
Routing - PLAN CHECK9/25/2014 9/26/2014 PASS
DetailsCarl Westfall
2nd review approved with red lines
Plan resubmittals received  9/25/2014 DONE
Routing - PLAN CHECK9/3/2014 9/19/2014 FAIL
DetailsCarl Westfall
Revised drawings required.
Plan resubmittals requested  9/19/2014 DONE
1st review completed  9/19/2014 FAIL
mech, plumb, building, fire did not approve
Routing - Design Review9/16/2014 9/18/2014 PASS
DetailsJosh Wilson
Routing - FIRE9/3/20149/3/20149/9/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 09-09-14
Routing - Addressing9/3/2014 9/8/2014 PASS
DetailsEmily Dixon
Routing PW Environmental9/4/2014 9/8/2014 FAIL
DetailsRick Christenson
No grease abatement shown. Facility needs properly sized grease trap.
Routing - MECHANICAL9/3/2014 9/8/2014 FAIL
DetailsTroy James
eplan
Routing - PUBLIC WORKS9/3/2014 9/4/2014 PASS
DetailsBeverly Mountain
Routing Off Site - C.D.H9/3/2014 9/4/2014 PASS
Details
Signed off by Jason in ePlan
Routing PW Sewer Rating9/4/2014 9/4/2014 PASS
DetailsBeverly Mountain
Routing - PLUMBING9/3/2014 9/3/2014 PASS
DetailsBill VanDegrift
Additional backflow protection on equipment may be required. Provide tempered water to hand wash sink.
Pending Assignment by JCB9/3/2014 9/3/2014 DONE
DetailsJason Blais
Intake Approval  8/29/2014 PASS
DetailsJason Blais
Prescreen approved by Carl Westfall and plan review fees paid.
Intake Approval  8/27/2014 FAIL
See "red lines" on Form #520 - Major Tenant Improvement Submittal Checklist.
Application received  8/25/2014 DONE
Application submitted via PDS Online on Aug 25 2014 3:05PM