Third Notice | | 1/11/2015 | 1/7/2015 | | DONE |
|
|
|
|
Second Notice | | 12/11/2014 | 1/6/2015 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 1/6/15
|
First Notice | | 11/14/2014 | 12/1/2014 | | DONE |
|
|
|
|
BLD-Final | 11/3/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Tony Young
|
|
|
Mike Phone #: ###-####,, ok for perm c of o no mech needed
|
Permanent Occupancy | | | 11/4/2014 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/3/2014 | 11/3/2014 | 11/3/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed acceptable. Items to be done prior to structural final include; remove manual thumbturn at the main entry/exit, post correct address numbers to match.
|
BLD-Final | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | NR |
Tony Young
|
|
|
mike Phone #: ###-####
|
BLD-Framing/Rough-in | 10/21/2014 | 10/22/2014 | 10/22/2014 | A | PEND |
Tony Young
|
|
|
Mike Phone #: ###-####,, walls ok pending electrical rough in pass
|
Permit Ready to Issue | | | 9/30/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 9/30/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/30/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 9/3/2014 | 9/3/2014 | 9/29/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
9/29Level 3 TI - ePlanReview - Shu's Running Co. Expansion
|
Routing - PLAN CHECK | 9/3/2014 | | 9/29/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 9/29/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/2014 | | DONE |
|
|
|
|
Routing - FIRE | 9/3/2014 | 9/3/2014 | 9/11/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-11-14
|
Routing PW Sewer Rating | 9/3/2014 | | 9/4/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 9/3/2014 | | 9/3/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/3/2014 | | 9/3/2014 | | PASS |
Beverly Mountain
|
|
|
|
Pending Assignment by JCB | 9/3/2014 | | 9/3/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 9/2/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Javier Guzman on 8/28/14 and plan review fees paid on 9/2/14.
|
Application received | | | 8/27/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 27 2014 5:10PM
|