Second Notice | | 12/13/2014 | 1/5/2015 | | DONE |
Candy A. Nichols
|
|
|
sent in mail 1/5/15
|
First Notice | | 11/28/2014 | 12/3/2014 | | DONE |
|
|
|
|
BLD-Final | 11/18/2014 | 11/18/2014 | 11/18/2014 | P | PASS |
Jim Sly
|
|
|
matt Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 11/18/2014 | | DONE |
Candy A. Nichols
|
|
|
|
FIRE-Final Inspection | 11/13/2014 | 11/13/2014 | 11/13/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Jim Sly
|
|
|
Thanks Matt, Phone #: ###-#### Inspection requested via web by Richard Schultz
|
BLD-Framing/Rough-in | 10/24/2014 | 10/24/2014 | 10/24/2014 | P | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/15/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/15/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 10/14/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 10/14/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 9/9/2014 | 9/9/2014 | 10/9/2014 | | PASS |
Carl Westfall
|
|
|
NOBLE ROMAN'S PIZZA - Level 3 TI - ePlanReview - (15 days - Sept 26) (1st review done)
|
Routing - PLAN CHECK | 10/8/2014 | | 10/9/2014 | | DONE |
Carl Westfall
|
|
|
Routing completed
|
Routing - MECHANICAL | 10/8/2014 | | 10/9/2014 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/2014 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/8/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/3/2014 | | 10/7/2014 | | PASS |
Carl Westfall
|
|
|
Started routing on 10-3-14. Structural calcualtions were received on 10-7-14. Drawings were approved.
|
Plan resubmittals requested | | | 10/7/2014 | | DONE |
|
|
|
Mechanical has not approved the drawings
|
Routing - MECHANICAL | 10/3/2014 | | 10/6/2014 | | FAIL |
Troy James
|
|
|
Previous review comments have not been addressed.
|
Routing - PLUMBING | 10/3/2014 | | 10/3/2014 | | PASS |
Bill VanDegrift
|
|
|
changed plumbing plans per plans and ISPC
|
Routing - PLAN CHECK | 10/2/2014 | | 10/3/2014 | | FAIL |
Carl Westfall
|
|
|
Compelted the 2nd review. One item is not resolved.
|
Plan resubmittals received | | | 10/2/2014 | | DONE |
|
|
|
|
1st review completed | | | 9/25/2014 | | FAIL |
|
|
|
Failed Plan check and Mechanical
|
Plan resubmittals requested | | | 9/25/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/9/2014 | | 9/25/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 9/9/2014 | | 9/16/2014 | | FAIL |
Troy James
|
|
|
eplan
|
Routing - PLUMBING | 9/9/2014 | | 9/16/2014 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - FIRE | 9/9/2014 | 9/9/2014 | 9/15/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-15-14
|
Routing PW Environmental | 9/9/2014 | | 9/10/2014 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 9/9/2014 | | 9/9/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - Addressing | 9/9/2014 | | 9/9/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/9/2014 | | 9/9/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/9/2014 | | 9/9/2014 | | PASS |
Evan Jenkins
|
|
|
Interior work with addition of Sand and Grease Trap: Some saw cutting to take place for removal of restroom fixtures and patch back work
|
Pending Assignment by JCB | 9/9/2014 | | 9/9/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 9/8/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen on 9/5/14. Plan review fees paid on 9/8/14.
|
Application received | | | 9/2/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 2 2014 11:23AM
|