First Notice | | 1/22/2015 | 2/2/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed 2-2-15
|
Permanent Occupancy | | | 1/12/2015 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 1/8/2015 | 1/9/2015 | 1/9/2015 | A | PASS |
Mike Jordan
|
|
|
Please call 45 min before arriving Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
BLD-Final | 1/7/2015 | 1/8/2015 | 1/8/2015 | P | NR |
Mike Jordan
|
|
|
Mike Please call me Dennis Harmon to go over final concerns Phone #: ###-#### Inspection requested via web by Dennis Harmon. Needs electrical final.
|
BLD-Conference | 1/7/2015 | 1/8/2015 | 1/8/2015 | A | DONE |
Mike Jordan
|
|
|
I would like to talk to Mike concerning the plumbing permit attached to this permit. Phone #: ###-#### Inspection requested via web by Dennis Harmon. Had plumbing permit attached to the correct building permit.
|
BLD-Wall Bracing | 10/23/2014 | 10/24/2014 | 1/7/2015 | P | CANC |
Mike Jordan
|
|
|
David Phone #: ###-#### Inspection cancelled from web by: Dennis Harmon
|
BLD-Final | 12/8/2014 | 12/9/2014 | 12/9/2014 | A | NR |
Mike Jordan
|
|
|
Dennis Phone #: ###-####
|
FIRE-Final Inspection | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 10/22/2014 | 10/23/2014 | 10/23/2014 | P | DONE |
Mike Jordan
|
|
|
david - call 30 mins prior Phone #: ###-####
|
BLD-Framing/Rough-in | 10/13/2014 | 10/14/2014 | 10/14/2014 | A | PART |
Mike Jordan
|
|
|
Please call 1 hour before. I have a question on the fire separation wall. Will 2-3.5 in. walls work in place of a 6in. wall? This is a partial framing inspection due to fire sprinklers that need to be moved and the wall concerns. Phone #: ###-#### Inspection requested via web by Dennis Harmon. ok to one side 2hr. demissing wall.
|
Issue PAID IN FULL permit | | | 10/8/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/8/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 10/7/2014 | | DONE |
|
|
|
|
Telephone call | | | 10/7/2014 | | DONE |
|
|
|
emailed fees to Dennis Harmon
|
Routing - PLAN CHECK | 9/18/2014 | | 10/6/2014 | | PASS |
Carl D Madsen
|
|
|
Plans approved with conditions. Future tenant improvement to be submitted in the next 60 to 90 days for the DFS warehouse area for conversion to a manufacturing area. The warehouse area is not to be used for manufacturing under this permit. 10-6-14 CDM.
|
1st review completed | | | 10/6/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2014 | | DONE |
|
|
|
|
Routing - FIRE | 10/3/2014 | 10/3/2014 | 10/3/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 10-03-14
|
Routing - Addressing | 10/2/2014 | | 10/2/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - FIRE | 9/18/2014 | 9/18/2014 | 9/24/2014 | | FAIL |
|
|
|
See Fire Plan Review 09-24-14
|
Intake Approval | | | 9/15/2014 | | PASS |
|
|
|
|
Intake Approval | | | 9/9/2014 | | FAIL |
|
|
|
Please provide or indicate the following items on the plans.
1. Please provide a second application for the the remaining space including square footages and occupant loads.
2. Indicate the square footages and occupant loads for both spaces.
3. Revise the certificate of value to indicate any work being done in all areas including mechanical, electrical, plumbing and fire.
4.Provide a door and door hardware schedule.
5. indicate exit signs and emergency lighting.
6. indicate portable fire extinguishers.
7. Indicate accessibility upgrade work. (20% of the project value.
8. Indicate the existing restrooms and fixtures as each space is required to the minimum required fixtures.
9. Provide elevations and details for any point of service counters.
10. provide a list of commodities and method of storage.(contact Craig Hanson ###-####)
11. Indicate all required exit doors for both tenant spaces.
|
Application received | | | 9/5/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2014 2:53PM
|