Second Notice | | 2/12/2015 | 2/9/2015 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 1/8/2015 | 2/2/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 12/29/2014 | 12/29/2014 | 12/29/2014 | P | PASS |
Dave Hannah
|
|
|
Final inspection, glass sidelights complete. Ready for PM inspection, call Adam prior, ###-####. thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
Permanent Occupancy | | | 12/29/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 12/19/2014 | 12/23/2014 | 12/24/2014 | P | PART |
Dave Hannah
|
|
|
Building final inspection request/walk with Dave H. Call Adam prior to inspection visit. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson ok for temp occ needs to install glass.
|
FIRE-Final Inspection | 12/19/2014 | 12/23/2014 | 12/23/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory including trade related permit work. Project related fire sprinkler permit okayed for final- scheduled for 12/24 AM.
|
BLD-Ceiling Grid Inspection | 12/16/2014 | 12/17/2014 | 12/17/2014 | A | PASS |
Dave Hannah
|
|
|
Ceiling Grid reinspection, call Adam prior to inspection, ###-####. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/15/2014 | 12/16/2014 | 12/16/2014 | P | CANC |
Dave Hannah
|
|
|
Ceiling Grid reinspection, call Adam prior to inspection, ###-####. Thanks. Phone #: ###-#### >> Inspection requested via web by Adam Johnson Inspection cancelled from web by: Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/10/2014 | 12/11/2014 | 12/11/2014 | A | NR |
Dave Hannah
|
|
|
Ceiling grid inspection request, Stifel TI, 12th Floor at 8th and Main. Please call Adam prior to inspection. Thanks AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 11/10/2014 | 11/10/2014 | 11/10/2014 | P | PASS |
Jim Storey
|
|
|
Framing inspection request, Stifel TI, 12th Floor, call Adam prior to inspection ###-####. thanks akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
Issue PAID IN FULL permit | | | 10/14/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/14/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 10/10/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CJW) | 9/15/2014 | 9/15/2014 | 10/6/2014 | | PASS |
Carl Westfall
|
|
|
STIFEL - Level 3 TI - ePlanReview - (15 days - Oct 3)
|
Plan resubmittals received | | | 10/6/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/6/2014 | | 10/6/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with red lines after the 2nd review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2014 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/2/2014 | | DONE |
|
|
|
|
1st review completed | | | 10/2/2014 | | FAIL |
|
|
|
Did not pass plan review
|
Routing - PLAN CHECK | 9/15/2014 | | 10/2/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 9/15/2014 | | 9/24/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 9/15/2014 | 9/15/2014 | 9/22/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 09-22-14
|
Routing - Addressing | 9/15/2014 | | 9/22/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLUMBING | 9/15/2014 | | 9/16/2014 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 9/15/2014 | | 9/15/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 9/15/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved on 9/12/14 by Adele Schaffeld-Griffin. Plan review fees paid on 9/15/14.
|
Pending Assignment by JCB | 9/15/2014 | | 9/15/2014 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 9/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2014 10:51AM
|