Permit Information
Permit NumberBLD14-02741
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 1173 W UNIVERSITY DR
Project NameBSU Alumni and Friends Center
Customer NumberBLD14-02802
ePlanReviewYes
Description
(BSU Alumni and Friends Center) This building is designed as separated use. Plan Modificaiton to revise the exterior precast veneer elements on the facade of the building to brick in varous areas. See approved floor plan for A2 occupant load seating. To change upper roof structure from steel beams and deck to premanufactured metal trusses. Additional steel columns and beams added to exterior to support brick beneer. 3/30/15 **ajs**Project includes outdoor plaza, trash enclosure and parking lot. Permit for the construction of a new 4 story separateduse, fully fire sprinklered building. This permit includes the 4 story structure and all associated site work on the approved drawings. The car shelter is under BLD14-02802 and is a separate structure. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  1/6/2017 DONE
Second Notice 11/25/201612/14/2016 DONE
Mailed 12-15
First Notice 10/28/201611/15/2016 DONE
Mailed 11-16-16
BLD-Final10/18/201610/18/201610/18/2016PPASS
DetailsJim Storey
Jim Phone #: ###-####
Permanent Occupancy  10/18/2016 DONE
DetailsChristina Prado
BLD-Final10/3/201610/4/201610/4/2016APART
DetailsDave Hannah
Inspection requested via web by Jim Carriveau ok for temp occ c/n posted
Temporary Occupancy10/4/20161/2/201710/4/2016 DONE
DetailsChristina Prado
FIRE-Final Inspection9/28/20169/30/20169/30/2016APART
DetailsJim Page
Final for fire life safety cannot be completed until fire sprinkler and fire alarm permits are finaled, both FIR permits still have some work to be completed. Emergency lighting has been tested, fire extinguishers are in place with current inspection tags and door closers have been tested. After the FIR permits are finaled then life fire safety can be finaled.
Zoning Approval9/19/20169/19/20169/19/2016 DONE
DetailsDavid Moser
FIRE-Sprinkler Rough-in9/13/20169/14/20169/14/2016ADONE
DetailsJim Page
Request was for a life fire safety conference, fire conference complete.
BLD-Ceiling Grid Inspection9/6/20169/7/20169/7/2016APASS
DetailsJim Storey
first floor Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Conference8/1/20168/2/20168/2/2016APASS
DetailsJim Storey
Hi Jim, 4th floor ceiling grid, 2 hard lids 1st floor, after 10 if you can Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Conference7/22/20167/22/20167/22/2016PCANC
DetailsJim Storey
Hi Jim, looking at hard lid first floor and a couple hand rail questions Phone #: ###-#### Inspection requested via web by Jim Carriveau 1 st floor a3 ceilling ok
BLD-Ceiling Grid Inspection6/30/20167/1/20167/1/2016APASS
DetailsJim Storey
2nd ; 3rd floor ceiling grid Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Conference6/13/20166/14/20166/14/2016APASS
DetailsJim Storey
1st floor bathroom cover, i have a meeting from 9:30 to 10:30 for a heads up Phone #: ###-#### Inspection requested via web by Jim Carriveau4th ok 1st ok
BLD-Wall cover5/17/20165/18/20165/18/2016APASS
DetailsJim Storey
bathroom ceilings 2 ;3, north stair tower cover, 1st floor cover Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Wall cover4/14/20164/14/20164/14/2016APASS
DetailsJim Storey
3rd flr exterior insulation cover Phone #: ###-#### Inspection requested via web by Jim Carriveau ok to cover all
BLD-Wall cover4/4/20164/5/20164/5/2016APASS
DetailsJim Storey
edge of slab assembly 3rd ; 4th floors Inspection requested via web by Jim Carriveau engery code for exterior on 2nd ok to cover.
BLD-Wall cover3/31/20164/1/20164/1/2016APASS
DetailsJim Storey
edge of slab assembly for cover, 2nd floor Phone #: ###-#### Inspection requested via web by Jim Carriveau2nd ok 3rd southwest and east ok
BLD-Framing/Rough-in3/28/20163/29/20163/29/2016APART
DetailsJim Storey
Jim my insulator is gun shy with mineral wool install, he would like us to take a look to ensure proper install. I guess he had troubles at city center Inspection requested via web by Jim Carriveau ok to proceed
BLD-Framing/Rough-in3/21/20163/21/20163/21/2016APASS
DetailsJim Storey
exterior sofitt framing for cover Inspection requested via web by Jim Carriveau stair encloser ok/ soffits ok to cover
BLD-Wall cover3/17/20163/17/20163/17/2016APASS
DetailsJim Storey
Inspection requested via web by Jim Carriveau fire chalking at shafts ok
BLD-Wall cover2/9/20162/9/20162/9/2016PPART
DetailsJim Storey
Jim, any chance you can catch me right after lunch Inspection requested via web by Jim Carriveau 2nd and third core non rated walls ok to cover.
BLD-Wall cover2/2/20162/2/20162/2/2016APART
DetailsJim Storey
Jim, i have a meeting on site from 10 to 10:30 this morning so either side of that would be great if you can Phone #: ###-#### Inspection requested via web by Jim Carriveaushaft core board ok thru out building/ fire stopping pending
BLD-Energy code compliance1/18/20161/19/20161/19/2016APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Jim Carriveau sw mech. rm 1st and 2nd ok to cover.
BLD-Framing/Rough-in1/5/20161/6/20161/6/2016APASS
DetailsJim Storey
Jim Phone #: ###-#### top of shatfs ok to proceed/ ele boxes back to back two locations/ ele splice box 1 hr ele rm/fireriser rm remove or prorect.
BLD-Framing/Rough-in11/18/201511/19/201511/19/2015APASS
DetailsJim Storey
Jim Phone #: ###-#### col grout ok exteriot wall framing ok to cover exterior.
BLD-Framing/Rough-in10/21/201510/22/201510/22/2015APASS
DetailsJim Storey
Jim Phone #: ###-#### grout under col ok to cover.
BLD-Framing/Rough-in10/20/201510/20/201510/20/2015PPASS
DetailsJim Storey
Jim Phone #: ###-#### first floor exterior north ok
BLD-Conference9/28/20159/28/20159/28/2015PPASS
DetailsJim Storey
Jim Phone #: ###-#### reviewed fire assemblies curtin wall shaft and stair enclosers
BLD-Footing5/27/20155/27/20155/27/2015PPASS
DetailsJim Storey
Jim-pour time Phone #: ###-#### placed with si pending reports
CHANGE STATUS TO (ISS)  5/27/2015 DONE
BLD-Footing5/7/20155/8/20155/8/2015APASS
DetailsJim Storey
pour time 9:30AM; Jim Phone #: ###-#### si w/mti
OVERRIDE  4/3/2015  
Permit Ready to Issue  4/3/2015 DONE
DetailsChristina Prado
Plan mod ready
Need fees paid and status changed to ISS
Plan assigned to (AJS)3/10/20153/10/20153/30/2015 PASS
DetailsAdele J Schaffeld-Griffin
BSU
Routing - PLAN CHECK3/30/2015 3/30/2015 PASS
DetailsAdele J Schaffeld-Griffin
plan modification
Routing Off Site - STRUCTURAL3/30/2015 3/30/2015 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  3/30/2015 DONE
Plan Modification Accepted  3/10/2015 DONE
Permit Ready to Issue  2/27/2015 DONE
Issue PAID IN FULL permit  2/27/2015 DONE
Print Occupancy Form  2/27/2015 DONE
OVERRIDE  2/25/2015  
Telephone call  2/25/2015 DONE
emailed Margie Kennedy and told her permit is ready for pick up and remaing fees due
Permit Ready to Issue  2/25/2015 DONE
Requirements met- FEES DUE
Expiration Notice2/23/20153/16/20152/23/2015 DONE
DetailsChristina Prado
Routing - PLAN CHECK12/8/2014 12/20/2014 PASS
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL12/8/2014 12/20/2014 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  12/20/2014 DONE
Plan assigned to (AJS)9/19/2014 12/20/2014 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed New Building BSU Alumni and Friends Center
Routing PW Drainage11/19/2014 12/5/2014 PASS
DetailsBrian Murphy
Routing PW Sewer Design11/19/2014 12/3/2014 PASS
DetailsKyle S. Rosenmeyer
Routing Off Site - STRUCTURAL11/19/2014 11/26/2014 FAIL
DetailsAdele J Schaffeld-Griffin
see change marks in e plan
Route to Impact Fee Review10/24/201410/27/201411/18/2014 PASS
DetailsCindy M. Gould
1st review completed  10/24/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK9/19/2014 10/24/2014 FAIL
DetailsAdele J Schaffeld-Griffin
code review not complete spoke with Alexis at LCA. They would like to upload the revisions on the other failed reviews. They know the code review will continue but this will allow the project to advance as it was not separated into a structural submittal and a TI submital.
Routing - Addressing10/23/2014 10/23/2014 PASS
DetailsEmily Dixon
Routing - PLANNING Land Div10/23/2014 10/23/2014 PASS
DetailsDave Abo
Parcel is consolidated into one parcel under ROS 9932.
Routing PW Solid Waste9/19/2014 10/7/2014 PASS
DetailsPeter J. McCullough
Routing PW Environmental9/19/2014 10/7/2014 PASS
DetailsRick Christenson
Routing Off Site - STRUCTURAL9/19/2014 10/3/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Please provide written responses, additional calculations and revised drawings where required.
Routing PW Drainage9/19/2014 9/30/2014 FAIL
DetailsBrian Murphy
NEEDS GROUND WATER LETTER AND C33 SAND FOR PAVERS
Routing - FIRE9/19/2014 9/30/2014 PASS
DetailsCraig D. Hanson
Approved with redlines See Fire Plan Review 09-30-14
Routing PW Sewer Design9/19/2014 9/25/2014 FAIL
DetailsKyle S. Rosenmeyer
Submit new sewer main alignment separately to public works for review. Include plan & profile, current standard notes, etc.
Remove abanoned pipe below building footprint or fill with a high slump concrete.
Avoid direct tapping large diamter sewer lines. Connect to existing manhole 91A with a cleanout/direction change @ the property line. Service must be perpendicular to the main line within Public R/W.
Contact Public Works 48 hours prior to tapping manhole to obtain a tap permit and schedule a sewer inspection.
Label Manhole - 91A
Routing - PLANNING9/19/2014 9/23/2014 PASS
DetailsDavid Moser
Routing - PLUMBING9/22/2014 9/22/2014 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing PW Sewer Rating9/19/2014 9/19/2014 PASS
DetailsBeverly Mountain
Routing PW Street Lights9/19/2014 9/19/2014 PASS
DetailsMike D Hedge
No street lighting required.
Routing - PLANNING Land Div9/19/2014 9/19/2014 FAIL
DetailsDave Abo
Must remove property lines where new structure is proposed.
Different property owners, Boise State Alumni and Boise State University. Also southern portion owned by State Board of Education.
Routing - Addressing9/19/2014 9/19/2014 FAIL
DetailsEmily Dixon
The proposed building would be on multiple parcels with different owners.
Routing - PUBLIC WORKS9/19/2014 9/19/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment9/19/2014 9/19/2014 PASS
DetailsEvan Jenkins
RP must be designated prior to issuence of permit.
Site Prep Inspection and Approval Required Prior to Earth Disturbance.
Intake Approval  9/18/2014 PASS
DetailsTim L. Woodard
Intake approved with separate application for "Cart Storage" building. TLW
Application received  9/15/2014 DONE
Application submitted via PDS Online on Sep 15 2014 8:35AM
Pending Assignment by JCM9/19/2014    
DetailsJohn Menard
Routing PW Geothermal10/24/2014   PASS
DetailsJon R. Gunnerson
Boise City to provide geothermal taps and pipe to right-of-way. Coordinate with City Public Works Department @ ###-####

signed off in e plan