Permanent Occupancy | | | 10/7/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 10/2/2014 | 10/3/2014 | 10/3/2014 | P | PASS |
Jim Sly
|
|
|
Steve Phone #: ###-#### OK for perm occ.
|
FIRE-Final Inspection | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 10/2/2014 | 10/3/2014 | 10/3/2014 | A | CANC |
Jim Sly
|
|
|
Steve Phone #: ###-####// please call before
|
FIRE-Final Inspection | 10/2/2014 | 10/2/2014 | 10/2/2014 | P | CANC |
Troy Cobbley
|
|
|
Steve Phone #: ###-####// please call before
|
FIRE-Final Inspection | 9/30/2014 | 10/1/2014 | 10/1/2014 | A | PART |
Troy Cobbley
|
|
|
Temporary occupancy for fire is approved with scott's permission until the exit signs are repaired.
|
Telephone call | | | 10/1/2014 | | DONE |
|
|
|
Spoke with Steve Yates regarding a TCO for tenant. The occupant load requires 1 exit, however, 3 exits are provided within the space which include emergency light devices with intergrated batteries. The batteries are not funtioning therefore need to be replaced if the tenant selects to leave these devices installed. Informed Steve that a TCO will be approved while the batteries are ordered and installed. Additional item that needs to be corrected, per field inspectors comments, prior to occupancy is the required fire extinguisher.
|
FIRE-Final Inspection | 9/19/2014 | 9/23/2014 | 9/23/2014 | A | FAIL |
Troy Cobbley
|
|
|
Repair the exit signs and emergency lights or remove. Provide fire extinguisher as discussed
|
Issue PAID IN FULL permit | | | 9/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 9/15/2014 | 9/18/2014 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 9/18/2014 | | 9/18/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 9/18/2014 | | 9/18/2014 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 9/18/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/18/2014 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/18/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 9/18/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/18/2014 | | DONE |
Tisha Gallop
|
|
|
called Steve Yates and left vm permit is ready.
|
Plans ACCEPTED BY PLAN CHECK | | | 9/15/2014 | | |
Tim L. Woodard
|
|
|
|
First Notice | | 10/17/2014 | | | |
|
|
|
|