Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD14-02772
StatusFinaled
Name CSDI CONSTRUCTION INC
Site Address 3201 W AIRPORT WAY
Project NameEinstein Bros. Bagels
Customer Number 
ePlanReviewYes
Description
(EINSTEIN BROS. BAGELS - CITY OF BOISE AIR TERMINAL - 2ND STORY - FOOD COURT - WITHIN SECURITY AREA) Fire sprinklers used for fire area. To remodel an existing 1,329 square foot food preparation and food service tenant space (301 square foot “front of house” area and 1,028 square foot “back of house” kitchen area) located on the 2nd story next to the food court within the security area of the City of Boise Air Terminal. The “front of house” area will be reduced by about 222 square feet and the “back of house” kitchen area will be increased by about 222 square feet. The public will not be allowed within this tenant space. After being served, sit down dining for the public will be available in the food court. Work is to include new interior nonbearing walls, a new door with double-acting hinges installed between the “back of house” area and the “front of house” area, suspended acoustical ceilings, a new customer service counter, a hand sink, new millwork, and new finishes. Work within the kitchen includes a new hand sink, a gas convection oven, a new 88 square foot walk-in freezer with the condensing unit installed on the roof, shelves, and equipment. A new condensing unit will be installed on the roof to serve an existing walk-in cooler. The two existing grease hoods will be maintained. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 2/7/20153/3/2015 DONE
Second Notice 1/12/20152/2/2015 DONE
First Notice 12/26/20141/2/2015 DONE
BLD-Final12/16/201412/16/201412/16/2014PPASS
DetailsJim Storey
Permanent Occupancy UNPAID FEE  12/16/2014 DONE
DetailsCandy A. Nichols
FIRE-Final Inspection12/12/201412/15/201412/15/2014APASS
DetailsForrest France
Fire life safety passed. Locking hardware at the galley door between the back and front of house removed.
BLD-Final12/15/201412/15/201412/15/2014PPART
DetailsJim Storey
temo ok to remove lock hardware beteen survery to kitchen
BLD-Ceiling Grid Inspection11/26/201411/26/201411/28/2014PPASS
DetailsJim Storey
Call ahead for escort - Mark Phone #: ###-####
BLD-Framing/Rough-in11/12/201411/13/201411/13/2014APASS
DetailsJim Storey
Mark Phone #: ###-####
Permit Ready to Issue  10/15/2014 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  10/15/2014 DONE
DetailsChristina Prado
Print Occupancy Form  10/15/2014 DONE
DetailsChristina Prado
Plan assigned to (CJW)9/19/20149/19/201410/8/2014 PASS
DetailsCarl Westfall
Level 3 TI - ePlanReview - Einstein Bros. Bagels in Boise Airport(15 days - Oct 9)
Routing - PLAN CHECK9/19/2014 10/8/2014 PASS
DetailsCarl Westfall
Drawings approved with red lines
1st review completed  10/8/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  10/8/2014 DONE
Routing - MECHANICAL9/19/2014 9/25/2014 PASS
DetailsTroy James
Routing - FIRE9/19/20149/19/20149/23/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review 09-23-14
Routing - PUBLIC WORKS9/19/2014 9/23/2014 PASS
DetailsBeverly Mountain
Routing - PLUMBING9/19/2014 9/22/2014 PASS
DetailsBill VanDegrift
May require a RPBP on steamer instead of DCVA.
Routing - Addressing9/19/2014 9/22/2014 PASS
DetailsEmily Dixon
Routing Off Site - C.D.H9/19/2014 9/22/2014 PASS
DetailsTidemark Corp
Intake Approval  9/19/2014 PASS
DetailsCarl Westfall
Plan intake approved
Pending Assignment by JCB9/19/2014 9/19/2014 DONE
DetailsJason Blais
Application received  9/16/2014 DONE
Application submitted via PDS Online on Sep 16 2014 1:16PM