Print Statement | | | 1/14/2015 | | DONE |
|
|
|
|
First Notice | | 12/29/2014 | 1/2/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/19/2014 | | DONE |
|
|
|
|
BLD-Final | 12/15/2014 | 12/16/2014 | 12/16/2014 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
Telephone call | | | 12/16/2014 | | DONE |
Candy A. Nichols
|
|
|
called-Leslie transferred me to Jason-called to let them know the temp c of o is going to expire in 2 days. Left message that they need to call in a final or request an extension before it expires
|
Temporary Occupancy | 11/20/2014 | 2/18/2015 | 11/20/2014 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 11/18/2014 | 11/19/2014 | 11/19/2014 | A | PART |
Dave Hannah
|
|
|
Dual Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 11/18/2014 | 11/19/2014 | 11/19/2014 | A | PASS |
Forrest France
|
|
|
Verified corrections. Fire life safety passed. Remainder of project finishes to be completed prior to structural final approval.
|
FIRE-Final Inspection | 11/17/2014 | 11/18/2014 | 11/18/2014 | P | NR |
Forrest France
|
|
|
Missing stamped plans and review notes, doors at several locations are not yet installed, relocation of exit sign needed, project finishes underway.
|
BLD-Ceiling Grid Inspection | 11/17/2014 | 11/17/2014 | 11/18/2014 | P | PASS |
Dave Hannah
|
|
|
Duel- Phone #: ###-####
|
BLD-Final | 11/17/2014 | 11/18/2014 | 11/18/2014 | P | CANC |
Dave Hannah
|
|
|
DUAL Phone #: ###-####
|
FIRE-Conference | 11/14/2014 | 11/14/2014 | 11/14/2014 | A | DONE |
Forrest France
|
|
|
Regarding project schedule, related trade work, unfinished work at the SW corridor.
|
BLD-Conference | 11/7/2014 | 11/7/2014 | 11/7/2014 | P | DONE |
Dave Hannah
|
|
|
Duel Phone #: ###-####
|
BLD-Framing/Rough-in | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PASS |
Dave Hannah
|
|
|
Trey Phone #: ###-####
|
BLD-Conference | 10/15/2014 | 10/16/2014 | 10/17/2014 | P | PEND |
Dave Hannah
|
|
|
Chris Phone #: ###-#### needs to pick up permit
|
BLD-Conference | 10/8/2014 | 10/8/2014 | 10/8/2014 | P | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### ok to one side walls
|
Permit Ready to Issue | | | 10/7/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/7/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/7/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 9/19/2014 | | 10/2/2014 | | PASS |
Carl Westfall
|
|
|
RED SKY - Level 2 - Eplan - (9 days - Oct. 1)
|
Plan resubmittals received | | | 10/2/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/2/2014 | | 10/2/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved with red lines.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2014 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/1/2014 | | DONE |
|
|
|
|
1st review completed | | | 10/1/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/19/2014 | | 10/1/2014 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - PUBLIC WORKS | 9/19/2014 | | 9/23/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 9/19/2014 | | 9/19/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 9/19/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 9/17/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 17 2014 2:11PM
|