Permit Information
Permit NumberBLD14-02814
StatusFinaled
Name CSDI CONSTRUCTION INC
Site Address 3201 W AIRPORT WAY
Project NameCNBC SMARTSHOP
Customer Number 
ePlanReviewYes
Description
(CNBC SMARTSHOP - BOISE AIR TERMINAL ā€“ Concoarse ā€œCā€ ā€“ 1st Floor) This building is fully fire sprinklered. To convert an arcade area to a 340 square foot retail tenant space. Work is to include: installation of new retail cases, installation of new security grille, new accessible sales counter, new electrical and interior finishes. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 2/7/20153/3/2015 DONE
mailed 3-4-15
Permanent Occupancy  1/28/2015 DONE
DetailsCandy A. Nichols
BLD-Final1/26/20151/27/20151/27/2015PPASS
DetailsJim Storey
MIke Phone #: ###-####
BLD-Final12/16/201412/17/201412/17/2014PPART
DetailsJim Storey
Mike Phone #: ###-####-pending CDHD
FIRE-Final Inspection12/16/201412/17/201412/17/2014APASS
DetailsTroy Cobbley
life safety passed
Temporary Occupancy12/17/20143/17/201512/17/2014 DONE
DetailsCandy A. Nichols
BLD-Framing/Rough-in11/19/201411/19/201411/19/2014APART
DetailsJim Storey
patch fireproofing/ok pending others.
Print Occupancy Form  11/3/2014 DONE
Permit Ready to Issue  10/29/2014 DONE
Issue PAID IN FULL permit  10/29/2014 DONE
Print Occupancy Form  10/29/2014 DONE
Routing - PLAN CHECK10/28/2014 10/28/2014 PASS
DetailsTim L. Woodard
Approved with attached calculations on storefront. TLW
Routing Off Site - C.D.H10/28/2014 10/28/2014 PASS
DetailsTim L. Woodard
Approved by Tammie in E-Plan Review. TLW
PLANS/APPL TAKEN TO FRONT DESK  10/28/2014 DONE
Plan assigned to (TLW)9/30/2014 10/28/2014 PASS
DetailsTim L. Woodard
1st Review Completed. Waiting on CDH Approval. TLW
Routing - PLAN CHECK9/30/2014 10/9/2014 FAIL
DetailsTim L. Woodard
Routing Off Site - C.D.H9/30/2014 10/9/2014 FAIL
DetailsAdele J Schaffeld-Griffin
I do not have plans for this particular store front so I cannot approve until I know what is going in here. thanks tammie
1st review completed  10/9/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - Addressing9/30/2014 9/30/2014 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS9/30/2014 9/30/2014 PASS
DetailsBeverly Mountain
Intake Approval  9/30/2014 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  9/25/2014 FAIL
DetailsAdele J Schaffeld-Griffin
Please complete and upload the 518 check list.
Please complete the 304 form and upload into documents.
Application received  9/19/2014 DONE
Application submitted via PDS Online on Sep 19 2014 2:12PM