Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD14-02837
StatusFinaled
Name INDUSTRIAL BUILDERS INC
Site Address 3201 W AIRPORT WAY
Project NameBoise Airport
Customer Number 
ePlanReviewYes
Description
(BOISE AIRPORT - CBRA ROOM - LOCATED ABOVE THE BAGGAGE MAKE-UP AREA) (7-18-16 PLAN MODIFICATION TO REMOVE AN EXISTING DOOR AND FRAME AND TO REPAIR THE WALL FINISH ASSOCIATED WITH THAT WORK.) (1-20-16 THE WORK UNDER THIS PERMIT WILL BE DONE PER THE PHASING SCHEDULE ON SHEET G0.3. A TOTAL OF 3 PHASES ARE DEFINED.) The fire sprinkler system is used for occupancy. To expand and remodel the existing CBRA Room located on the mezzanine above the baggage make-up area. The room will be expanded by about 1,147 square feet from about 1,090 square feet to about 2,237 square feet. The changes are needed to accommodate the new baggage conveyor system layout. Work is to include interior nonbearing walls, interior doors, new handrails to serve an existing stairways, anti-fatigue flooring, suspended acoustical ceiling, gypsum board soffits, spray applied fire proofing to create a 2-hr fire-resistance-rated floor assembly and 2-hr supporting elements, and finishes. An existing steel grate in the mezzanine floor will be removed and the floor opening will be infilled with a metal deck and concrete floor. A notch in the bottom of an existing beam will be enlarged to provide the required headroom at a walking surface. Steel box headers will be installed at alcoves and wall openings to support the walls above. Special Inspection is required for welding and the application of spray applied fire proofing. An existing roof top HVAC unit will be removed and a new unit, using a transition curb adapter, will be installed on the existing curb. The new HVAC unit is not allowed to weigh more than the removed HVAC unit. The work is required to comply with the approved drawings, with the plan review report, with the structural calculations, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 3/17/20184/10/2018 DONE
mailed 4-11-18
Permanent Occupancy  3/7/2018 DONE
FIRE-Final Inspection2/16/20182/16/20182/16/2018PPASS
DetailsTroy Cobbley
Life safety passed for project scope of work.


Lee Phone #: ###-####
BLD-Final2/15/20182/16/20182/16/2018APASS
DetailsJim Storey
Lee Phone #: ###-####
DOC - Permit Finaled2/16/20182/16/20182/16/2018PPASS
DetailsJim Storey
CHANGE STATUS TO (ISS)  2/16/2018 DONE
should not have been finaled. customer called in for fire life saftey
BLD-Final12/15/201712/18/201712/18/2017AFAIL
DetailsJim Storey
Please call ahead for access // Fireproofing & Final - Lee Phone #: ###-#### ele conduit blocking covrage of fire prooffing/ patches needed// si required need reports/ handrails required both exit stairs.
FIRE-Final Inspection12/15/201712/18/201712/18/2017ACANC
DetailsTroy Cobbley
Please call ahead for access - Lee Phone #: ###-####
BLD-Aging Inspection9/6/20179/6/20179/14/2017 CANC
DetailsJim Storey
BLD-Ceiling Grid Inspection9/6/20179/6/20179/6/2017PPART
DetailsBrandon Shaw
Lee Phone #: ###-####
FIRE-Final Inspection4/21/20174/24/20174/24/2017APART
DetailsTroy Cobbley
Life safety for Phase II passed.

Lee Phone #: ###-####
BLD-Conference11/16/201611/17/201611/17/2016APASS
DetailsJim Storey
Lee Phone #: ###-#### wip ok time line dec to march with equment instal/ stairs and fireprooffing to proceed aprox jan.
Telephone call  11/14/2016 DONE
Left a message for Martin informing him that this permit is going to expire in 23 days, showing that it had a plan mod done and there are fees due. Informed him I tried to call Industiral Builders, but the number given is not their number.
CHANGE STATUS TO (ISS)  11/14/2016 DONE
(F) Reprint permit  11/14/2016 DONE
Plan assigned to (CJW)7/15/20167/15/20167/18/2016 PASS
DetailsCarl Westfall
Routing - PLAN CHECK7/15/2016 7/18/2016 PASS
DetailsCarl Westfall
Plan mod approved
PLANS/APPL TAKEN TO FRONT DESK  7/18/2016 DONE
Permit Ready to Issue  7/18/2016 DONE
DO NOT REISSUE PLAN MOD
Plan Modification Accepted  7/15/2016 DONE
DetailsChristina Prado
Plan Mod requested to change location of interior doorway
BLD-Framing/Rough-in6/9/20166/10/20166/10/2016APASS
DetailsJim Storey
Lee Phone #: ###-#### entry wall ok/
FIRE-Final Inspection5/20/20165/23/20165/23/2016APASS
DetailsTroy Cobbley
Phase 1 life safety passed.
FIRE-Final Inspection5/18/20165/19/20165/19/2016AFAIL
DetailsTroy Cobbley
The most up to date plans were not on site and neither were the small documents.
FIRE-Final Inspection5/12/20165/13/20165/13/2016AFAIL
DetailsTroy Cobbley
Project is not ready for a final inspection nor is the first phase of work. Need fire alarm and fire sprinkler work called in for inspection. I noted that the smoke detector and ceiling mounted horn/strobe is overspaced. Lee Phone #: ###-####
BLD-Ceiling Grid Inspection4/29/20165/2/20165/2/2016PPASS
DetailsJim Storey
Lee Phone #: ###-####
BLD-Framing/Rough-in3/30/20163/30/20163/30/2016PPASS
DetailsJim Storey
CBRA Rm, baggage handling area, call for access - Lee Phone #: ###-#### interior wall ok to cover
Print Occupancy Form  1/22/2016 DONE
Issue PAID IN FULL permit  1/22/2016 DONE
Plan assigned to (CJW)1/13/20161/13/20161/20/2016 PASS
DetailsCarl Westfall
plan mod
Routing - PLAN CHECK1/18/2016 1/20/2016 PASS
DetailsCarl Westfall
The proposed phasing schedule was approved. This was not really a plan mod since the permit had not been issued. No additional fees required.
PLANS/APPL TAKEN TO FRONT DESK  1/20/2016 DONE
Permit Ready to Issue  1/20/2016 DONE
DetailsChristina Prado
Need GC form & revised certificate of value for issuance
Plan Modification Accepted  1/18/2016 DONE
DetailsCarl Westfall
Work flow in ePlanReview received. This is not really a plan mod since the permit had not been issued yet.
Plan Modification Accepted  1/13/2016 DONE
DetailsChristina Prado
Resubmittal requested to add additional phasing plans and temporary locations
Extend Review Timeline  9/1/2015 DONE
Final extension. 180 days granted by JCB. See attached documents.
Expiration Notice8/27/20159/18/20158/27/2015 DONE
DetailsBrittany Hill
Extend Review Timeline  3/12/2015 DONE
DetailsChristina Prado
180 day extension granted per JCB
Expiration Notice3/2/20153/23/20153/2/2015 DONE
DetailsChristina Prado
Plan assigned to (CJW)12/19/201412/19/20141/23/2015 PASS
DetailsCarl Westfall
CBRA ROOM (BOISE AIRPORT) - Level 3 TI - ePlanReview - (15 days - Jan 6)
Plan resubmittals received  1/23/2015 DONE
Routing - PLAN CHECK1/23/2015 1/23/2015 PASS
DetailsCarl Westfall
Drawings approved with redlines
PLANS/APPL TAKEN TO FRONT DESK  1/23/2015 DONE
Permit Ready to Issue  1/23/2015 DONE
DetailsChristina Prado
Need revised cert of value & GC form
Routing - PLAN CHECK12/19/2014 1/12/2015 FAIL
DetailsCarl Westfall
Revised drawings required
Plan resubmittals requested  1/12/2015 DONE
DetailsCarl Westfall
1st review completed  1/12/2015 DONE
DetailsCarl Westfall
Failed building
Routing - FIRE12/19/201412/19/201412/23/2014 PASS
DetailsScott Arellano
Attached comments to plans.
Pending Assignment by JCB12/19/2014 12/19/2014 DONE
DetailsJason Blais
Intake Approval  12/17/2014 PASS
DetailsJason Blais
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
Intake Approval  9/26/2014 FAIL
DetailsAdele J Schaffeld-Griffin
1. Please upload your structural calculations into documents it appears they did not load.
2. Please submit your 310 form completed by the engineer and signed by the owner for the special inspections required for this project. See structural sheet and IBC chapter 17.
Application received  9/22/2014 DONE
Application submitted via PDS Online on Sep 22 2014 4:46PM