First Notice | | 2/8/2015 | 2/4/2015 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Print Occupancy Form | | | 1/29/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/29/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | PASS |
Dave Hannah
|
|
|
Derrick Phone #: ###-#### ok for perm occ
|
BLD-Final | 12/2/2014 | 12/2/2014 | 12/2/2014 | P | PART |
Dave Hannah
|
|
|
###-#### Derick ok for temp occ
|
FIRE-Final Inspection | 12/2/2014 | 12/2/2014 | 12/2/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | DONE |
Troy Cobbley
|
|
|
I spoke with Tom Gainer about the non-functional fire alarm panel and that the Liquor Store stocking shelves. I spoke with the Liquor Store manager about needing Boise Fire Dept permission to fire load the store prior to a inspection/sign off.
|
FIRE-Final Inspection | 11/28/2014 | 11/28/2014 | 11/28/2014 | P | FAIL |
Forrest France
|
|
|
Project is not in condition for final approval at this time. Noted several items including; missing panic hardware at the meeting room exit doors per plan, post max. occupant signage, provide second exit sign/EM light at the meeting room per plan, missing ceiling tile throughout, provide approved hardware at the restroom door, repair exit discharge light at the alley way, missing hardware at the second exit from meeting room, post fire extinguishers per plan, project related fire sprinkler permit is not yet finaled, remove non-applicable suite address numbers, blank or disable keyed deadbolt above panic hardware main entry/exit.
|
BLD-Framing/Rough-in | 11/13/2014 | 11/14/2014 | 11/14/2014 | A | PASS |
Dave Hannah
|
|
|
Derek Phone #: ###-####
|
Permit Ready to Issue | | | 11/13/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/13/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/13/2014 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 10/2/2014 | 10/2/2014 | 11/4/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Level 3 Liqour store, early start issued 10/8
|
Routing - PLAN CHECK | 11/4/2014 | | 11/4/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/16/2014 | | 10/23/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 10/16/2014 | 10/16/2014 | 10/20/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review Rev 1 10-20-14
|
1st review completed | | | 10/10/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - FIRE | 10/2/2014 | 10/2/2014 | 10/7/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-07-14
|
Routing PW Sewer Rating | 10/2/2014 | | 10/2/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2014 | | 10/2/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 10/2/2014 | | 10/2/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - Erosion and Sediment | 10/2/2014 | | 10/2/2014 | | CANC |
Evan Jenkins
|
|
|
No Review nor ESC Permit Required. No Earth Disturbance nor Saw Cutting
|
Intake Approval | | | 10/2/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 9/24/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 24 2014 2:31PM
|
Routing - PLAN CHECK | 10/2/2014 | | | | |
Adele J Schaffeld-Griffin
|
|
|
|