BLD-Final | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | DONE |
Tony Young
|
|
|
Exterior soffits - Steve Phone #: ###-####
|
DOC - Permit Finaled | 10/5/2015 | 10/5/2015 | 10/5/2015 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Final | 4/2/2015 | 4/3/2015 | 4/3/2015 | P | PASS |
Tony Young
|
|
|
Garage access code is 0713 or 4444. Please call with any questions. Thanks, Kim Phone #: ###-#### Inspection requested via web by Kim Winkle,, bond in place,, final ok
|
PubWorks Occupancy Approval | 4/3/2015 | 4/3/2015 | 4/3/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Wall cover | 12/22/2014 | 12/23/2014 | 12/23/2014 | A | PASS |
Tony Young
|
|
|
soffits
|
BLD-Energy code compliance | 12/19/2014 | 12/22/2014 | 12/22/2014 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Lucas Christian
|
BLD-Energy code compliance | 12/18/2014 | 12/19/2014 | 12/19/2014 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Lucas Christian,, work in progress
|
BLD-Framing/Rough-in | 12/18/2014 | 12/18/2014 | 12/19/2014 | P | PASS |
Jim Sly
|
|
|
Lucas phone......###-####
|
BLD-Conference | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Lucas Christian Cans in soffits protected with 3/4" fire rated plywood box. Fire rated plywood installed prior to tongue and groove at soffits and patio ceilings.
|
Plan Modification Accepted | | | 12/8/2014 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 12/8/2014 | | 12/8/2014 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Lucas Christian,, exterior ok to cover now
|
BLD-Wall Bracing | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Lucas Christian,, exterior shear ok,, work in progress
|
BLD-Conference | 11/29/2014 | 12/1/2014 | 12/1/2014 | A | CANC |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Lucas Christian,, wanted shear inspection
|
BLD-Foundation | 10/29/2014 | 10/30/2014 | 10/30/2014 | P | PASS |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 10/29/2014 | 10/30/2014 | 10/30/2014 | A | PASS |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 10/28/2014 | 10/28/2014 | 10/28/2014 | A | NR |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Need to complete rebar in footings...... Got a verbal from Jim Wylee that subgrade was approved.
|
Routing PW Grading-Hillside | 10/28/2014 | | 10/28/2014 | | PASS |
Jim Wyllie
|
|
|
Received second geotec report approving foundation subgrade. Okay to schedule a footing inspection. (jim Wyllie / ###-####)
|
Issue PAID IN FULL permit | | | 10/16/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JG) | | 9/29/2014 | 10/15/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Pending Hillside, 10/15 W L2 Hillside**
|
Case Summary (BLD) | | | 10/15/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 10/15/2014 | | DONE |
Christina Prado
|
|
|
called Steve to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 10/15/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 10/13/2014 | | 10/15/2014 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Grading-Hillside | 10/14/2014 | | 10/14/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
1st review completed | | | 10/13/2014 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 10/2/2014 | | 10/13/2014 | | FAIL |
Javier Guzman
|
|
|
Pending Hillside review
|
Route to Impact Fee Review | 9/29/2014 | 10/2/2014 | 10/6/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Erosion and Sediment | 10/1/2014 | | 10/2/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection & Approval Required Prior to Earth Disturbance
|
Routing - MECHANICAL | | | 10/1/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/30/2014 | | 9/30/2014 | | PASS |
Sue Cummings
|
|
|
see notes on site planre: driveway width. In the Foothills WUI zone also.
|
Routing - FIRE | 9/30/2014 | | 9/30/2014 | | PASS |
Scott Arellano
|
|
|
This structure has been evaluated for Fire Department Vehicle Access.
|
Routing - PUBLIC WORKS | 9/29/2014 | | 9/30/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Grading-Hillside | 9/29/2014 | | 9/29/2014 | | FAIL |
Jason C. Taylor
|
|
|
Grading plan needs revised/signed by civil engineer prior to approval. Need engineering for retaining walls. JCT ###-####
|
Routing - Addressing | 9/29/2014 | | 9/29/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/29/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 9/29/2014 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | 9/29/2014 | | | |
|
|
|
|