Print Statement | | | 1/6/2016 | | DONE |
|
|
|
|
Telephone call | | | 1/6/2016 | | DONE |
|
|
|
as per Able Viramontes-sent in revised final values
|
Telephone call | | | 1/6/2016 | | DONE |
|
|
|
emailed Able-he sent me revised final values so i emailed him back with the corrected fees that are due
|
Print Statement | | | 12/28/2015 | | DONE |
|
|
|
|
Third Notice | | 11/14/2015 | 12/10/2015 | | DONE |
|
|
|
|
Third Notice | | 10/17/2015 | 11/9/2015 | | DONE |
|
|
|
|
Second Notice | | 9/25/2015 | 10/12/2015 | | DONE |
|
|
|
Mailed 10-13-15
|
First Notice | 8/25/2015 | 8/25/2015 | 9/15/2015 | | DONE |
Jim Storey
|
|
|
Mailed 9/16/15
|
BLD-Final | 8/25/2015 | 8/25/2015 | 8/25/2015 | A | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety inspection passed/complete
|
BLD-Conference | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-####
|
BLD-Final | 8/20/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### temp ok pending others
|
FIRE-Final Inspection | 8/19/2015 | 8/19/2015 | 8/19/2015 | P | FAIL |
Troy Cobbley
|
|
|
Fire life safety will be ok to pass when the project related fire alarm and fire sprinkler permits are finaled
|
FIRE-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | CANC |
Jim Page
|
|
|
Tom Phone #: ###-####
|
Inspection Record Card- Bld | | | 8/10/2015 | | DONE |
|
|
|
|
BLD-Conference | 6/17/2015 | 6/18/2015 | 6/18/2015 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Brian Murphy ramps ok
|
Issue PAID IN FULL permit | | | 6/1/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2015 | | DONE |
|
|
|
|
Expiration Notice | 5/19/2015 | 6/10/2015 | 5/28/2015 | | DONE |
Brittany Hill
|
|
|
|
Telephone call | | | 5/28/2015 | | DONE |
|
|
|
Left message on Walters machine informing him that this permit expires in ten days and just wanted to touch bases to see if he would like to send a letter or email to Jason B for an extention or if he would like to just let the permit expire or go ahead and void it.
|
OVERRIDE | | | 5/12/2015 | | |
|
|
|
|
Routing PW Environmental | 5/1/2015 | | 5/11/2015 | | PASS |
Rick Christenson
|
|
|
Approved in E-Plan. TLW
|
Plan assigned to (TLW) | 4/30/2015 | | 5/11/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 4/30/2015 | | 5/11/2015 | | PASS |
Tim L. Woodard
|
|
|
Canopy Plan Modification approved. TLW
|
Routing - FIRE | 4/30/2015 | | 5/11/2015 | | PASS |
Scott Arellano
|
|
|
Attached revised plans to case.
|
Routing - PUBLIC WORKS | 4/30/2015 | | 5/1/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 5/1/2015 | | 5/1/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Rating | 5/1/2015 | | 5/1/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Modification Accepted | | | 4/30/2015 | | DONE |
|
|
|
Applicant called in to have a mod started to add a canopy to the existing shell and core. TLW
|
OVERRIDE | | | 4/13/2015 | | |
|
|
|
|
Plan assigned to (TLW) | 4/1/2015 | | 4/13/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/1/2015 | | 4/13/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/13/2015 | | DONE |
|
|
|
DO NOT REISSUE, PLAN MOD
|
Routing - FIRE | 4/1/2015 | | 4/10/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans. Fire Protection Water Storage Tank.
|
Routing - PLAN CHECK | 4/1/2015 | | 4/1/2015 | | PASS |
Tim L. Woodard
|
|
|
Approved contingent on outsource structural review. TLW
|
Plan Modification Accepted | | | 4/1/2015 | | DONE |
Tim L. Woodard
|
|
|
Modification for Water Tank.
|
BLD-Footing | 12/9/2014 | 12/9/2014 | 12/9/2014 | A | PASS |
Jim Storey
|
|
|
Concrete placement on 11/25 has been supported with engineering stamped documents from the engineer of record and engineer/owner of special inspection firm.
|
BLD-Foundation | 12/1/2014 | 12/2/2014 | 12/2/2014 | P | NR |
Jim Storey
|
|
|
Brian Phone #: ###-#### si nr
|
BLD-Foundation | 11/24/2014 | 11/25/2014 | 11/25/2014 | A | FAIL |
Jim Storey
|
|
|
Bryan Phone #: ###-#### placment half done upon ariving for insp special insp. on site. Rebar clearance no achived/ stopped placment required engineer of record and special insp to resolve isue and provide field reports from both to meet code and engineered design.
|
BLD-Foundation | 10/29/2014 | 10/30/2014 | 10/30/2014 | A | CANC |
Jim Storey
|
|
|
Brian Phone #: ###-####
|
BLD-Footing | 10/30/2014 | 10/30/2014 | 10/30/2014 | P | PART |
Jim Storey
|
|
|
Brian Phone #: ###-#### rebar ok pending reports/ soil value aproved by engineers of record si verifacation ok.
|
OVERRIDE | | | 10/29/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/29/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 10/29/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 10/28/2014 | | 10/28/2014 | | PASS |
Tim L. Woodard
|
|
|
Approved with resubmittals. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2014 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/28/2014 | | 10/28/2014 | | PASS |
Tim L. Woodard
|
|
|
Resubmittals approved by outsource engineering firm. TLW
|
Plan assigned to (TLW) | 10/3/2014 | | 10/28/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Route to Impact Fee Review | 10/17/2014 | 10/20/2014 | 10/24/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 10/3/2014 | | 10/17/2014 | | FAIL |
Tim L. Woodard
|
|
|
Refer to changemarks in E-Plan Review. TLW
|
Routing Off Site - STRUCTURAL | 10/3/2014 | | 10/17/2014 | | FAIL |
Tim L. Woodard
|
|
|
Refer to e-plan. TLW
|
Routing PW Sewer Rating | 10/3/2014 | | 10/17/2014 | | PASS |
Beverly Mountain
|
|
|
Approved in e-plan. TLW
|
Routing PW Solid Waste | 10/3/2014 | | 10/17/2014 | | PASS |
Peter J. McCullough
|
|
|
Approved in e-plan. TLW
|
Routing PW Environmental | 10/3/2014 | | 10/17/2014 | | PASS |
Rick Christenson
|
|
|
Approved in e-plan. TLW
|
Routing PW Sewer Design | 10/3/2014 | | 10/17/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Approved in e-plan. TLW
|
1st review completed | | | 10/17/2014 | | DONE |
|
|
|
|
Routing - FIRE | 10/3/2014 | | 10/16/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-16-14
|
Routing - PLUMBING | 10/3/2014 | | 10/8/2014 | | PASS |
Cody Riddle
|
|
|
1) vent interceptor
2) cap interceptor inlet diptube
|
Routing PW Street Lights | 10/3/2014 | | 10/7/2014 | | PASS |
Mike D Hedge
|
|
|
No street lighting required.
|
Routing - Erosion and Sediment | 10/3/2014 | | 10/6/2014 | | PASS |
Evan Jenkins
|
|
|
Site Prep Inspection Required Prior to Earth Disturbance. Please Refer to the ESC Site Maps from permit number ESC14-00791 for BMP locations
|
Routing - PLANNING | 10/3/2014 | | 10/3/2014 | | PASS |
Cody Riddle
|
|
|
|
Routing PW Drainage | 10/3/2014 | | 10/3/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING Land Div | 10/3/2014 | | 10/3/2014 | | PASS |
Cody Riddle
|
|
|
|
Routing - Addressing | 10/3/2014 | | 10/3/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/3/2014 | | 10/3/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 10/3/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Plan Reviewer's activity | | | 10/2/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Pre screen accepted per Ron Hill. See Ron for any questions.
|
Application received | | | 10/1/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 1 2014 8:56AM
|