BLD-Final | 6/26/2015 | 6/29/2015 | 6/29/2015 | A | PASS |
Phil Shearer
|
|
|
Brian Phone #: ###-####
|
DOC - Permit Finaled | 6/29/2015 | 6/29/2015 | 6/29/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 6/25/2015 | 6/26/2015 | 6/26/2015 | P | CANC |
Dave Hannah
|
|
|
Brian Phone #: ###-#### Inspection cancelled from web by: bryan murdoch
|
Routing PW Grading-Hillside | 6/26/2015 | | 6/26/2015 | | PASS |
Jim Wyllie
|
|
|
Hillside grading and landscaping are complete. Okay to issue building occupancy. Jim Wyllie / ###-####
|
BLD-Final | 6/24/2015 | 6/25/2015 | 6/25/2015 | P | NR |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
BLD-Energy code compliance | 3/30/2015 | 3/31/2015 | 3/31/2015 | A | PASS |
Phil Shearer
|
|
|
Brian Phone #: ###-####
|
BLD-Framing/Rough-in | 3/23/2015 | 3/24/2015 | 3/24/2015 | P | PASS |
Phil Shearer
|
|
|
Doug Phone #: ###-####
|
BLD-Wall Bracing | 3/18/2015 | 3/19/2015 | 3/19/2015 | A | PASS |
Phil Shearer
|
|
|
Shear // Brian Phone #: ###-####
|
BLD-Foundation | 12/5/2014 | 12/8/2014 | 12/8/2014 | A | PASS |
Phil Shearer
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 11/6/2014 | 11/7/2014 | 11/7/2014 | P | PASS |
Phil Shearer
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 11/5/2014 | 11/6/2014 | 11/6/2014 | P | NR |
Phil Shearer
|
|
|
Eric Phone #: ###-####
|
PubWorks Subgrade Approval | 11/3/2014 | 11/3/2014 | 11/3/2014 | | DONE |
Jason C. Taylor
|
|
|
*FOOTINGS ONLY - NO COLUMNS***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 10/16/2014 | | |
|
|
|
|
Application received | | 10/1/2014 | 10/16/2014 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 10/15/2014 | | 10/16/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2014 | | DONE |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 10/16/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 10/16/2014 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 10/16/2014 | | DONE |
Tisha Gallop
|
|
|
called Doug Lasher and left vm permit is ready and fee due.
|
Issue PAID IN FULL permit | | | 10/16/2014 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 10/14/2014 | 10/14/2014 | 10/15/2014 | | PASS |
Perry Paine
|
|
|
|
1st review completed | | | 10/15/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/15/2014 | | 10/15/2014 | | PASS |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (JG) | | 10/1/2014 | 10/14/2014 | | DEFR |
Javier Guzman
|
|
|
10/17 F L2 Hillside** Routed to Perry
|
Routing - FIRE | 10/10/2014 | | 10/13/2014 | | PASS |
Scott Arellano
|
|
|
This structure has been evaluated for Fire Department Vehicle Access. No comments attached to plans.
|
Routing - Erosion and Sediment | 10/9/2014 | | 10/10/2014 | | PASS |
Andy J. Long
|
|
|
ESC plan with site map and narrative approved. Valid RP and PD designated for project. Site prep inspection required.
|
Routing - MECHANICAL | 10/9/2014 | | 10/9/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/6/2014 | | 10/9/2014 | | PASS |
Joshua Johnson
|
|
|
|
Route to Impact Fee Review | 10/1/2014 | 10/6/2014 | 10/6/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 10/1/2014 | | 10/6/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 10/6/2014 | | 10/6/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/1/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 10/1/2014 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2014 | | DONE |
Christina Prado
|
|
|
|