First Notice | | 4/6/2015 | 7/2/2015 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Amar
|
BLD-Final | 3/27/2015 | 3/27/2015 | 3/27/2015 | P | PASS |
Mike Jordan
|
|
|
|
Zoning Approval | 3/27/2015 | 3/27/2015 | 3/27/2015 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 3/27/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 3/25/2015 | 3/26/2015 | 3/26/2015 | A | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Ok for temp occ. Will be ok for pwerm occ. once zoning signs perm.
|
BLD-Final | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | NR |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Needs mech. final. scheduled for tomorrow in the am.
|
FIRE-Final Inspection | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 3/24/2015 | 3/24/2015 | 3/24/2015 | P | FAIL |
Troy Cobbley
|
|
|
Will be ok to final when the project related fire alarm and fire sprinkler permits are finaled.
|
BLD-Other | 2/20/2015 | 2/20/2015 | 2/20/2015 | P | PASS |
Mike Jordan
|
|
|
sheet rock // Pat Phone #: ###-####
|
BLD-Energy code compliance | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Wall Bracing | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | PASS |
Mike Jordan
|
|
|
Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 2/12/2015 | 2/13/2015 | 2/13/2015 | A | FAIL |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Nail off all hangars, provide protection for microwave ducts. fireblock at reuturn air upstairs unit, provide adequate strapping on top plates at line sets. Provide truss engineering. Ok to insulate.
|
BLD-Wall Bracing | 2/13/2015 | 2/13/2015 | 2/13/2015 | A | FAIL |
Mike Jordan
|
|
|
Pat Phone #: ###-####. Install all missing floor to floor straps.
|
BLD-Foundation | 12/11/2014 | 12/12/2014 | 12/12/2014 | P | DONE |
Mike Jordan
|
|
|
John Phone #: ###-####
|
BLD-Footing | 12/10/2014 | 12/11/2014 | 12/11/2014 | A | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. Footing completed, need revised footing plan showing 16 inch wide footing.
|
Print Occupancy Form | | | 11/17/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/14/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/14/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 11/13/2014 | | |
|
|
|
|
Permit Ready to Issue | | | 11/13/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2014 | | DONE |
Sam Zahorka
|
|
|
|
Plan assigned to (SRZ) | 10/8/2014 | | 11/10/2014 | | PASS |
Sam Zahorka
|
|
|
Pending Plumbing to PASS
|
Routing - PLUMBING | 11/5/2014 | | 11/7/2014 | | PASS |
Daryl Spivey
|
|
|
ACCESS TO REMOVE WATER HEATER REQUIRED
|
Routing - PLAN CHECK | 10/8/2014 | | 11/5/2014 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PLANNING Land Div | 10/8/2014 | | 11/5/2014 | | PASS |
Todd Tucker
|
|
|
Passed in ePlanReview
|
Routing - FIRE | 10/8/2014 | | 10/20/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 10-20-14
|
Routing - MECHANICAL | 10/8/2014 | | 10/14/2014 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/8/2014 | 10/11/2014 | 10/10/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 10/8/2014 | | 10/10/2014 | | PASS |
Joshua Johnson
|
|
|
|
Application received | | | 10/8/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 8 2014 12:21AM
|
Pending Assignment by JCM | 10/8/2014 | | 10/8/2014 | | DONE |
John Menard
|
|
|
|
1st review completed | | | 10/8/2014 | | PASS |
John Menard
|
|
|
|
Routing - Design Review | 10/8/2014 | | 10/8/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 10/8/2014 | | 10/8/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/8/2014 | | 10/8/2014 | | PASS |
Beverly Mountain
|
|
|
per Bev Mountain
|
Routing - Erosion and Sediment | 10/8/2014 | | 10/8/2014 | | PASS |
Evan Jenkins
|
|
|
L2B3-6787 Irving. New Construction of 1 bdrm 4-Plex in Aberdeen
Site Prep Inspection and Approval Required Prior to Earth Disturbance
|
Routing - PLUMBING | 10/8/2014 | | 10/8/2014 | | FAIL |
Daryl Spivey
|
|
|
resubmit legible P-2 plan
|
Routing PW Sewer Rating | 10/8/2014 | | 10/8/2014 | | PASS |
Jennifer Bruner
|
|
|
|