Third Notice | | 5/9/2015 | 6/8/2015 | | DONE |
|
|
|
This permit finaled on the web by Amy Wray
|
Second Notice | | 3/13/2015 | 5/4/2015 | | DONE |
|
|
|
|
First Notice | | 2/28/2015 | 3/3/2015 | | DONE |
|
|
|
mailed 3-3-15
|
Permanent Occupancy | | | 2/18/2015 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 2/10/2015 | 2/11/2015 | 2/11/2015 | A | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
FIRE-Final Inspection | 2/10/2015 | 2/10/2015 | 2/10/2015 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Final | 12/11/2014 | 12/12/2014 | 12/12/2014 | P | PART |
Dave Hannah
|
|
|
Doug Phone #: ###-#### ok for temp ok for perm occ after fire gos perm
|
FIRE-Final Inspection | 12/11/2014 | 12/12/2014 | 12/12/2014 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with scott's permission until the fire alrm is extended into this tenant space as per upgrade agreement. See FIR03-00803
|
BLD-Framing/Rough-in | 10/29/2014 | 10/29/2014 | 10/29/2014 | P | NR |
Dave Hannah
|
|
|
Doug Phone #: ###-#### needs elec rough in
|
Permit Ready to Issue | | | 10/29/2014 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 10/29/2014 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 10/29/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 10/21/2014 | | 10/22/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 10/21/2014 | | 10/22/2014 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 10/22/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2014 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/22/2014 | | DONE |
|
|
|
|
Intake Approval | | | 10/21/2014 | | PASS |
|
|
|
|
Application received | | | 10/17/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2014 2:18PM
|