BLD-Final | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | DONE |
Tony Young
|
|
|
Jeff Phone #: ###-####,, exemption met with cover
|
DOC - Permit Finaled | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Concrete | 1/22/2015 | 1/23/2015 | 1/23/2015 | P | PASS |
Tony Young
|
|
|
Rebar // Jeff Phone #: ###-####
|
PubWorks Subgrade Approval | 1/23/2015 | 1/23/2015 | 1/23/2015 | | DONE |
Jason C. Taylor
|
|
|
* SPA ONLY* A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 1/22/2015 | 1/22/2015 | 1/22/2015 | P | PEND |
Tony Young
|
|
|
Rebar // Jeff Phone #: ###-####,, ok pending hillside approval
|
BLD-Foundation | 1/21/2015 | 1/22/2015 | 1/22/2015 | A | PEND |
Tony Young
|
|
|
Rebar // Jeff Phone #: ###-####,, needs hillside approval
|
Routing Walk-In (PW Hillside) | 1/21/2015 | 1/21/2015 | 1/21/2015 | P | PASS |
Jason C. Taylor
|
|
|
**Subgrade inspection required**See BLD14-01311 for hillside requirements. Jason Taylor ###-####
|
CHANGE STATUS TO (ISS) | | | 1/21/2015 | | DONE |
Tisha Gallop
|
|
|
grading plan approved by Jason Taylor, taken to front desk for customer to pick up.
|
Telephone call | | | 1/21/2015 | | DONE |
|
|
|
called Clearwater Pools- spoke with Jeff- told him that revised Grading plans are ready for pick up, no fees due, and he needs them for inspection tomorrow
|
Plan resubmittals received | | | 1/21/2015 | | DONE |
Candy A. Nichols
|
|
|
received resubmittals 2 sets of sheet #'s C1-0, C2.0- took to Jason Tayler per Jason Taylors request
|
CHANGE STATUS TO (REV) | | | 10/22/2014 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2014 | | DONE |
Candy A. Nichols
|
|
|
talked to Don @ Shadow Built. Jason Taylor needs them to resubmit palns for the spa. Jason told them they need all new plans for review including 3 grading & drainage as well as the geotech
|
Routing Walk-In (Zoning) | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 10/21/2014 | 10/21/2014 | 10/21/2014 | P | DONE |
Perry Paine
|
|
|
|
Plan assigned to (PEP) | 10/21/2014 | 10/21/2014 | 10/21/2014 | | PASS |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 10/21/2014 | | |
|
|
|
|
1st review completed | | | 10/21/2014 | | FAIL |
|
|
|
mis representation from builder as to the documents required for the submittal of this plan.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/21/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/21/2014 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/21/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | 10/21/2014 | | | |
|
|
|
|