Permit Information
Permit NumberBLD14-03123
StatusFinaled
Name URBAN MODZ
Site Address 3204 N 24TH WAY
Project NameBowen Residence
Customer Number 
ePlanReviewNo
Description
WUI Zone A, Class A Roof, Permit for the construction of a new 3,322 sq. ft., two story (first story 2,274 sq. ft., second story 1,048 sq. ft.) single family dwelling with 6 bedrooms, 4 bathrooms, approximately 616 sq. ft. of covered patio/porch and a 810 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1B zoning and setbacks per planning. JG A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  6/8/2016 DONE
PubWorks Occupancy Approval7/20/20157/20/20157/20/2015 DONE
DetailsJason C. Taylor
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
BLD-Final5/19/20155/20/20155/20/2015APASS
DetailsTony Young
Hans Phone #: ###-####
DOC - Permit Finaled5/20/20155/20/20155/20/2015PPASS
DetailsTony Young
c of o issued
PubWorks Occupancy Approval5/19/20155/19/20155/19/2015 DONE
DetailsJason C. Taylor
A bond for the sites concrete,final grading and revegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
BLD-Conference5/4/20155/6/20155/6/2015PDONE
DetailsTony Young
Hans Phone #: ###-####,, ?s on final
Telephone call  4/13/2015 DONE
telephone call from neighbor that there is avery bright reflection from this dwelling onto other neighbors also. 4-13-2015 10:33a.m. pep
BLD-Energy code compliance2/24/20152/25/20152/25/2015APASS
DetailsTony Young
Hans Phone #: ###-####
BLD-Other2/24/20152/25/20152/25/2015APASS
DetailsTony Young
Hans Phone #: ###-####,, soffit
BLD-Energy code compliance2/24/20152/24/20152/24/2015PNR
DetailsTony Young
Hans Phone #: ###-####
BLD-Framing/Rough-in2/18/20152/19/20152/19/2015APASS
DetailsJim Sly
Hanas Phone #: ###-####
BLD-Wall Bracing1/27/20151/28/20151/28/2015APART
DetailsJim Sly
Shear // Bob Phone #: ###-####
Exterior nailing only......OK
BLD-Foundation11/25/201411/26/201411/26/2014APART
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing11/24/201411/25/201411/25/2014PNR
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing11/24/201411/24/201411/24/2014PPART
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron,, work in progress,, ok
BLD-Footing11/21/201411/24/201411/24/2014APART
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron.. working on forms
BLD-Conference11/20/201411/21/201411/21/2014PDONE
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing11/20/201411/21/201411/21/2014PNR
DetailsTony Young
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
PubWorks Subgrade Approval11/21/201411/21/201411/21/2014 DONE
DetailsJason C. Taylor
*FOOTINGS ONLY - NO EXTERIOR COLUMNS*A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  11/12/2014 DONE
OVERRIDE  11/10/2014  
Plan assigned to (PEP)11/3/201411/3/201411/10/2014 PASS
DetailsPerry Paine
Telephone call  11/10/2014 DONE
called Hans and left vm permit is ready and fee due.
Routing - PLAN CHECK10/30/2014 11/10/2014 PASS
DetailsPerry Paine
1st review completed  11/10/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/10/2014 DONE
Inspection Record Card- Bld  11/10/2014 DONE
Permit Ready to Issue  11/10/2014 DONE
Plan resubmittals received  11/4/2014 DONE
DetailsCandy A. Nichols
received resubmitted plans-2 each of sheet 3,4,6,7 of 11-took to JG
Plan resubmittals received  11/4/2014 DONE
DetailsJavier Guzman
received resubmitted plans-2 each of sheet 3,4,6,7 of 11-took to Perry
Plan assigned to (JG)10/22/201410/22/201411/3/2014 DEFR
DetailsJavier Guzman
11/07 F L2 Hillside**
Routing - FIRE10/29/2014 10/30/2014 PASS
DetailsScott Arellano
This structure has been evaluated for Fire Department Vehicle Access.
Routing - Erosion and Sediment10/29/2014 10/29/2014 PASS
DetailsEvan Jenkins
SITE PREP INSPECTION REQUIRED
WUI Zone A, Class A Roof, Permit for the construction of a new 3,322 sq. ft., two story (first story 2,274 sq. ft., second story 1,048 sq. ft.) single family dwelling with 6 bedrooms, 4 bathrooms, approximately 616 sq. ft. of covered patio/porch and a 810 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1B zoning and setbacks per planning.
Routing - MECHANICAL10/27/2014 10/29/2014 PASS
DetailsTroy James
Routing - PLANNING10/27/2014 10/27/2014 PASS
DetailsColleen T Carroll
Routing - PUBLIC WORKS10/23/2014 10/27/2014 PASS
DetailsJennifer Bruner
Routing PW Grading-Hillside10/24/2014 10/27/2014 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing PW Sewer Rating10/24/2014 10/24/2014 PASS
DetailsJennifer Bruner
Application received 10/22/201410/23/2014 DONE
Routing - Addressing10/23/2014 10/23/2014 PASS
DetailsEmily Dixon
Plans ACCEPTED BY PLAN TECH  10/22/2014 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  10/22/2014 DONE
DetailsTisha Gallop
Intake Approval  10/22/2014 PASS
DetailsTisha Gallop