Permit Information
Permit NumberBLD14-03157
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 1055 N CURTIS RD
Project NameSARMC 4TH FLOOR - OR Remodel
Customer Number 
ePlanReviewNo
Description
(SARMC – North Tower – 4th Floor – OR Remodel) Permit is to remodel existing cardiovascular operating rooms on the fourth floor of the existing hospital. PLAN MODIFICATION 7-21-15 – Modification submitted to add screening around new mechanical units.**TLW** This building is fully fire sprinklered. Approval contingent upon adhering to the approved plans on file. Work to include: installation of new smoke partition walls, installation of interior partition walls to create four operatory, installation of new accessible smoke tight doors, new light switching, and finishes in compliance with chapter 8 of the 2009 IBC. NOTE: This review recodifies the entire 4th floor to show compliance with the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/16/20159/16/20159/16/2015APASS
DetailsBob Archibald
Verified by 450. Ok for final
CHANGE STATUS TO (FNL)  9/16/2015 DONE
DetailsChristina Prado
Per passing inspection on 9-16 by inspector 325
Letter of compliance/Occupancy  9/16/2015 DONE
DOC - Permit Finaled  9/16/2015 PASS
DetailsBob Archibald
CHANGE STATUS TO (ISS)  9/16/2015 DONE
Telephone call  7/22/2015 DONE
Spoke with Sam Burrows informing him that his plan mod is ready and the fees that are due.
Inspection Record Card- Bld  7/22/2015 DONE
Plan assigned to (TLW)6/23/2015 7/21/2015 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK6/23/2015 7/21/2015 PASS
DetailsTim L. Woodard
Recieved structural calculations 7-20-15 TLW
PLANS/APPL TAKEN TO FRONT DESK  7/21/2015 DONE
Case Summary (BLD)  7/21/2015 DONE
Plan Modification Accepted  6/23/2015 DONE
received 3 copies of sheets A2.1 and A2.1A
BLD-Final5/29/20155/29/20155/29/2015PPART
DetailsMike Jordan
Cecil Phone #: ###-####. Ok to occupy cvor. plan mod for new screen wall.
FIRE-Final Inspection5/29/20155/29/20155/29/2015PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection5/26/20155/26/20155/26/2015PCANC
DetailsTroy Cobbley
To be rescheduled
BLD-Framing/Rough-in3/26/20153/27/20153/27/2015PPASS
DetailsMike Jordan
Ceclie Phone #: ###-####
BLD-Conference2/18/20152/19/20152/19/2015ADONE
DetailsMike Jordan
Ceicle Phone #: ###-####
BLD-Framing/Rough-in2/19/20152/19/20152/19/2015PDONE
DetailsMike Jordan
Ceicle Phone #: ###-####. Single user restroom/shower. Frtaming is existing.
Issue PAID IN FULL permit  1/30/2015 DONE
Inspection Record Card- Bld  1/30/2015 DONE
Inspection Record Card- Bld  1/22/2015 DONE
DetailsCandy A. Nichols
Permit Ready to Issue  1/22/2015 DONE
Telephone call  1/22/2015 DONE
DetailsCandy A. Nichols
called Sam to let know permit is ready and that we need the Gc form and rev cert of val from the GC-Sam is out so talked to Scott Wendall
Telephone call  1/22/2015 DONE
Emailed Brandon remaining fees due
Routing - FIRE1/14/20151/14/20151/21/2015 PASS
DetailsScott Arellano
Attached comments to plans.
Routing - PLAN CHECK1/21/2015 1/21/2015 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/21/2015 DONE
Case Summary (BLD)  1/21/2015 DONE
Plan assigned to (TLW)10/30/2014 1/21/2015 PASS
DetailsTim L. Woodard
1st Review Completed. Level 3 TI - Paper - St. Alphonsus 4th Floor Remodel
Plan resubmittals received  1/14/2015 DONE
DetailsCandy A. Nichols
resubmittals received 2 sets of each: response letter, A0.1, A2.0, E2.1L-took to TLW
Routing - PLAN CHECK1/14/2015 1/14/2015 PASS
DetailsTim L. Woodard
1st review completed  12/2/2014 DONE
DetailsTim L. Woodard
Routing - FIRE12/1/2014 12/2/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 12-02-14
Routing - PLAN CHECK11/10/2014 12/1/2014 FAIL
DetailsTim L. Woodard
Refer to Plan Review Report attached. TLW
Routing - MECHANICAL11/6/2014 11/10/2014 PASS
DetailsTroy James
Routing - PLUMBING11/3/2014 11/6/2014 PASS
DetailsBill VanDegrift
Per plan ans ISPC.
Routing PW Sewer Rating11/3/2014 11/3/2014 PASS
DetailsJennifer Bruner
Routing - PUBLIC WORKS10/31/2014 11/3/2014 PASS
DetailsJennifer Bruner
Routing - Addressing10/30/2014 10/31/2014 PASS
DetailsJason C. Taylor
Pending Assignment by JCB10/27/2014 10/30/2014 DONE
DetailsJason Blais
Intake Approval  10/27/2014 PASS
DetailsJason Blais
Prescreen approved by Carl Madsen on 10/24/14. Plan review fees paid on 10/27/14.
Plans ACCEPTED BY PLAN TECH  10/27/2014 DONE
Recd Pcfee & Taken To Pln CK  10/27/2014 DONE
Application received 10/24/2014