BLD-Final | 9/16/2015 | 9/16/2015 | 9/16/2015 | A | PASS |
Bob Archibald
|
|
|
Verified by 450. Ok for final
|
CHANGE STATUS TO (FNL) | | | 9/16/2015 | | DONE |
Christina Prado
|
|
|
Per passing inspection on 9-16 by inspector 325
|
Letter of compliance/Occupancy | | | 9/16/2015 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 9/16/2015 | | PASS |
Bob Archibald
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/16/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/22/2015 | | DONE |
|
|
|
Spoke with Sam Burrows informing him that his plan mod is ready and the fees that are due.
|
Inspection Record Card- Bld | | | 7/22/2015 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 6/23/2015 | | 7/21/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/23/2015 | | 7/21/2015 | | PASS |
Tim L. Woodard
|
|
|
Recieved structural calculations 7-20-15 TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/21/2015 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 6/23/2015 | | DONE |
|
|
|
received 3 copies of sheets A2.1 and A2.1A
|
BLD-Final | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | PART |
Mike Jordan
|
|
|
Cecil Phone #: ###-####. Ok to occupy cvor. plan mod for new screen wall.
|
FIRE-Final Inspection | 5/29/2015 | 5/29/2015 | 5/29/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled
|
BLD-Framing/Rough-in | 3/26/2015 | 3/27/2015 | 3/27/2015 | P | PASS |
Mike Jordan
|
|
|
Ceclie Phone #: ###-####
|
BLD-Conference | 2/18/2015 | 2/19/2015 | 2/19/2015 | A | DONE |
Mike Jordan
|
|
|
Ceicle Phone #: ###-####
|
BLD-Framing/Rough-in | 2/19/2015 | 2/19/2015 | 2/19/2015 | P | DONE |
Mike Jordan
|
|
|
Ceicle Phone #: ###-####. Single user restroom/shower. Frtaming is existing.
|
Issue PAID IN FULL permit | | | 1/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/22/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 1/22/2015 | | DONE |
|
|
|
|
Telephone call | | | 1/22/2015 | | DONE |
Candy A. Nichols
|
|
|
called Sam to let know permit is ready and that we need the Gc form and rev cert of val from the GC-Sam is out so talked to Scott Wendall
|
Telephone call | | | 1/22/2015 | | DONE |
|
|
|
Emailed Brandon remaining fees due
|
Routing - FIRE | 1/14/2015 | 1/14/2015 | 1/21/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - PLAN CHECK | 1/21/2015 | | 1/21/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/21/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/21/2015 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 10/30/2014 | | 1/21/2015 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed. Level 3 TI - Paper - St. Alphonsus 4th Floor Remodel
|
Plan resubmittals received | | | 1/14/2015 | | DONE |
Candy A. Nichols
|
|
|
resubmittals received 2 sets of each: response letter, A0.1, A2.0, E2.1L-took to TLW
|
Routing - PLAN CHECK | 1/14/2015 | | 1/14/2015 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 12/2/2014 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 12/1/2014 | | 12/2/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 12-02-14
|
Routing - PLAN CHECK | 11/10/2014 | | 12/1/2014 | | FAIL |
Tim L. Woodard
|
|
|
Refer to Plan Review Report attached. TLW
|
Routing - MECHANICAL | 11/6/2014 | | 11/10/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 11/3/2014 | | 11/6/2014 | | PASS |
Bill VanDegrift
|
|
|
Per plan ans ISPC.
|
Routing PW Sewer Rating | 11/3/2014 | | 11/3/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 10/31/2014 | | 11/3/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 10/30/2014 | | 10/31/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Pending Assignment by JCB | 10/27/2014 | | 10/30/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 10/27/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen on 10/24/14. Plan review fees paid on 10/27/14.
|
Plans ACCEPTED BY PLAN TECH | | | 10/27/2014 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/27/2014 | | DONE |
|
|
|
|
Application received | | 10/24/2014 | | | |
|
|
|
|