BLD-Final | 7/16/2015 | 7/17/2015 | 7/17/2015 | P | PASS |
Jim Storey
|
|
|
Lockbox is on S side of 407 Warren and contains keys for both 407 and 411. Code is 1409 Phone #: ###-#### Inspection requested via web by Keath Bennett
|
DOC - Permit Finaled | 7/17/2015 | 7/17/2015 | 7/17/2015 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 2/10/2015 | 2/10/2015 | 2/10/2015 | P | PASS |
Jim Storey
|
|
|
Keith Phone #: ###-####
|
BLD-Wall Bracing | 2/4/2015 | 2/4/2015 | 2/4/2015 | P | PASS |
Jim Storey
|
|
|
Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 2/4/2015 | 2/4/2015 | 2/4/2015 | P | PART |
Jim Storey
|
|
|
Keith-frame and air infultration Phone #: ###-#### justafy 40 '' cantalever 2nd floor. ok to insulate
|
BLD-Framing/Rough-in | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | CANC |
Mike Jordan
|
|
|
Keith Phone #: ###-####
|
BLD-Wall Bracing | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | PART |
Mike Jordan
|
|
|
Keith Phone #: ###-####. Complete missed areas with LIB method.
|
BLD-Footing | 11/25/2014 | 11/26/2014 | 11/27/2014 | A | PASS |
Phil Shearer
|
|
|
tim Phone #: ###-####
|
OVERRIDE | | | 11/12/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/12/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/12/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 11/7/2014 | | |
|
|
|
|
Plan assigned to (JG) | 10/27/2014 | 10/27/2014 | 11/7/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/06 TH L1 ePlan** Pending Mech
|
Routing - MECHANICAL | 11/7/2014 | | 11/7/2014 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/4/2014 | | 11/6/2014 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 11/6/2014 | | 11/6/2014 | | FAIL |
Troy James
|
|
|
still need to show 3 ton condenser
|
Route to Impact Fee Review | 10/27/2014 | 10/30/2014 | 11/4/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 10/27/2014 | | 11/4/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 11/4/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 10/27/2014 | | 11/4/2014 | | PASS |
Sue Cummings
|
|
|
Signed off in ePlan
|
Routing - MECHANICAL | 10/27/2014 | | 11/3/2014 | | FAIL |
Troy James
|
|
|
emailed correction to western heating
|
Application received | | | 10/27/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 27 2014 12:44PM
|
Plans ACCEPTED BY PLAN TECH | | | 10/27/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 10/27/2014 | | PASS |
Candy A. Nichols
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/27/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - Addressing | 10/27/2014 | | 10/27/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 10/27/2014 | | 10/27/2014 | | PASS |
Jennifer Bruner
|
|
|
|