BLD-Final | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | PASS |
Phil Shearer
|
|
|
Monica Phone #: ###-####
|
DOC - Permit Finaled | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 4/6/2015 | 4/7/2015 | 4/7/2015 | A | FAIL |
Phil Shearer
|
|
|
Monica-call for access code Phone #: ###-####. Fire caulking in the garage.
|
BLD-Wall Bracing | 2/13/2015 | 2/13/2015 | 2/13/2015 | P | PASS |
Phil Shearer
|
|
|
Shear // Monica Phone #: ###-####
|
BLD-Energy code compliance | 2/10/2015 | 2/11/2015 | 2/11/2015 | P | PASS |
Phil Shearer
|
|
|
Insulation // Monica Phone #: ###-####
|
BLD-Framing/Rough-in | 2/10/2015 | 2/10/2015 | 2/10/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Framing/Rough-in | 2/6/2015 | 2/9/2015 | 2/9/2015 | P | FAIL |
Phil Shearer
|
|
|
Change time and day per Monica blh 2-9-15 Phone #: ###-#### Need to provide updated plans.
|
BLD-Wall Bracing | 2/6/2015 | 2/9/2015 | 2/9/2015 | A | PASS |
Phil Shearer
|
|
|
Monica Phone #: ###-####
|
BLD-Footing | 12/10/2014 | 12/11/2014 | 12/11/2014 | A | PASS |
Phil Shearer
|
|
|
Derik Phone #: ###-####
|
PubWorks Subgrade Approval | 12/11/2014 | 12/11/2014 | 12/11/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 12/10/2014 | 12/10/2014 | 12/10/2014 | P | CANC |
Phil Shearer
|
|
|
about 4 if possible//Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/9/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/9/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 12/3/2014 | | |
|
|
|
|
Plan assigned to (JG) | 11/12/2014 | 11/12/2014 | 12/3/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/24 M L1 ePlan*
|
Routing - PLAN CHECK | 11/21/2014 | | 12/3/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/3/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 11/21/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 11/12/2014 | | 11/21/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - MECHANICAL | 11/12/2014 | | 11/14/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 11/12/2014 | | 11/12/2014 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Addressing | 11/12/2014 | | 11/12/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 11/12/2014 | | 11/12/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/12/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 11/12/2014 | | PASS |
Tisha Gallop
|
|
|
|
Intake Approval | | | 10/30/2014 | | FAIL |
|
|
|
still need Acca Report
|
Intake Approval | | | 10/29/2014 | | FAIL |
|
|
|
Missing Manual J and RES Check
|
Application received | | | 10/28/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 28 2014 11:37AM
|