BLD-Final | 6/17/2016 | 6/20/2016 | 6/20/2016 | P | PASS |
Phil Shearer
|
|
|
Chad Phone #: ###-####
|
DOC - Permit Finaled | 6/20/2016 | 6/20/2016 | 6/20/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 6/17/2016 | 6/17/2016 | 6/17/2016 | P | CANC |
Phil Shearer
|
|
|
|
BLD-Final | 6/16/2016 | 6/17/2016 | 6/17/2016 | A | FAIL |
Phil Shearer
|
|
|
Chad-call for access code Phone #: ###-####. Upstairs handrail
|
PubWorks Occupancy Approval | 6/16/2016 | 6/16/2016 | 6/16/2016 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
Plan Modification Accepted | | | 8/7/2015 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 8/7/2015 | | 8/7/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report again
|
BLD-Wall Bracing | 5/31/2015 | 6/1/2015 | 6/1/2015 | A | FAIL |
Phil Shearer
|
|
|
Re-Sheer wall Inspection Phone #: ###-#### Inspection requested via web by Michael Eisenbeiss
|
BLD-Energy code compliance | 6/1/2015 | 6/1/2015 | 6/1/2015 | P | PASS |
Phil Shearer
|
|
|
Re-Sheer wall Inspection Phone #: ###-#### Inspection requested via web by Michael Eisenbeiss
|
BLD-Energy code compliance | 5/27/2015 | 5/28/2015 | 5/28/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Michael Eisenbeiss
|
BLD-Framing/Rough-in | 5/21/2015 | 5/22/2015 | 5/22/2015 | P | PART |
Phil Shearer
|
|
|
Framing ; Air Seal Phone #: ###-#### Inspection requested via web by Michael Eisenbeiss. Need gerder nailing and engineered fix for cut foor joist
|
BLD-Wall Bracing | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | FAIL |
Phil Shearer
|
|
|
Framing ; Air Seal Phone #: ###-#### Inspection requested via web by Michael Eisenbeiss. Need to renail shear walls
|
Plan Modification Accepted | | | 5/21/2015 | | DONE |
|
|
|
another manual j report
|
Routing - MECHANICAL | 5/21/2015 | | 5/21/2015 | | PASS |
Troy James
|
|
|
resubmitted another manual j report
|
BLD-Foundation | 4/22/2015 | 4/23/2015 | 4/23/2015 | A | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 4/15/2015 | 4/16/2015 | 4/16/2015 | P | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-#### 1:00pm
|
BLD-Foundation | 4/14/2015 | 4/15/2015 | 4/15/2015 | P | CANC |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 4/13/2015 | 4/14/2015 | 4/14/2015 | P | CANC |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
PubWorks Subgrade Approval | 4/13/2015 | 4/13/2015 | 4/13/2015 | | DONE |
Jason C. Taylor
|
|
|
**RETAINING WALL SE SIDE OF GARAGE**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 4/7/2015 | 4/8/2015 | 4/8/2015 | P | NR |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
BLD-Foundation | 3/2/2015 | 3/2/2015 | 3/2/2015 | P | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 2/19/2015 | 2/19/2015 | 2/19/2015 | P | PASS |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
PubWorks Subgrade Approval | 2/19/2015 | 2/19/2015 | 2/19/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 2/5/2015 | | |
|
|
|
|
Plan assigned to (JG) | 1/22/2015 | 1/22/2015 | 2/5/2015 | | PASS |
Javier Guzman
|
|
|
Hillside Plan Mod
|
Routing - PLAN CHECK | 1/22/2015 | | 2/5/2015 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 2/5/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/5/2015 | | DONE |
|
|
|
do not re issue
|
Telephone call | | | 2/5/2015 | | DONE |
Candy A. Nichols
|
|
|
called Michael tof let know plan mod is ready and how much is owed-left message on his phone
|
CHANGE STATUS TO (ISS) | | | 2/5/2015 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 2/5/2015 | | DONE |
Christina Prado
|
|
|
|
Routing - FIRE | 1/27/2015 | | 2/2/2015 | | PASS |
Scott Arellano
|
|
|
No change in previous approval.
|
Routing - MECHANICAL | 1/28/2015 | | 1/28/2015 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 1/26/2015 | | 1/27/2015 | | FAIL |
Troy James
|
|
|
emailed corrections to idaho hvac
|
Routing - Erosion and Sediment | 1/27/2015 | | 1/27/2015 | | CANC |
Evan Jenkins
|
|
|
No Review Needed. Already approved initial permit
|
Routing PW Grading-Hillside | 1/22/2015 | | 1/26/2015 | | PASS |
Jason C. Taylor
|
|
|
No modifications to grading plan submitted or approved. Jason Taylor ###-####.
|
Routing - PLANNING | | | 1/26/2015 | | PASS |
|
|
|
|
Plan Modification Accepted | | | 1/22/2015 | | DONE |
|
|
|
received modification for complete home layout revision
|
BLD-Footing | 1/16/2015 | 1/16/2015 | 1/16/2015 | P | CANC |
Phil Shearer
|
|
|
Pat Phone #: ###-####
|
PubWorks Subgrade Approval | 1/15/2015 | 1/15/2015 | 1/15/2015 | | DONE |
Jason C. Taylor
|
|
|
**Column Pads & East Garage Footings***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
PubWorks Subgrade Approval | 12/23/2014 | 12/23/2014 | 12/23/2014 | | DONE |
Jason C. Taylor
|
|
|
*GARAGE FOOTINGS**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | NR |
Phil Shearer
|
|
|
Adam Phone #: ###-####
|
OVERRIDE | | | 12/18/2014 | | |
|
|
|
|
Plan assigned to (JG) | 12/18/2014 | 12/18/2014 | 12/18/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, Plan Mod garage footing
|
Routing PW Grading-Hillside | 12/18/2014 | | 12/18/2014 | | CANC |
Jason C. Taylor
|
|
|
No review for hillisde necessary on resubmitted plans.
|
Plan resubmittals received | | | 12/18/2014 | | DONE |
Candy A. Nichols
|
|
|
received resubmittals- 2 each sheet 2.0 & S1.0 also the truc calcs- took to JG
|
Case Summary (BLD) | | | 12/18/2014 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 12/18/2014 | | 12/18/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/18/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 12/18/2014 | | 12/18/2014 | | FAIL |
Javier Guzman
|
|
|
|
Inspection Record Card- Bld | | | 12/18/2014 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/18/2014 | | DONE |
Christina Prado
|
|
|
|
PubWorks Subgrade Approval | 12/15/2014 | 12/15/2014 | 12/15/2014 | | DONE |
Jason C. Taylor
|
|
|
* INTERIOR FOOTINGS & EXTERIOR COLUMNS**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Plan resubmittals received | | | 12/15/2014 | | DONE |
Christina Prado
|
|
|
received two sets of revised plan sheets marked 2.0, 3.0 & S1.0 as well as two sets revised structural calcs;Plans stamped and taken to JG for further review
|
BLD-Conference | 12/11/2014 | 12/12/2014 | 12/12/2014 | P | DONE |
Phil Shearer
|
|
|
call before to meet//dustin Phone #: ###-####
|
Plan resubmittals received | | | 12/12/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked 2.0, S1.0 & 3.0; Plans taken to Javier for further review
|
PubWorks Subgrade Approval | 12/3/2014 | 12/3/2014 | 12/3/2014 | | DONE |
Jason C. Taylor
|
|
|
* INTERIOR FOOTINGS ONLY - NO EXTERIOR COLUMNS**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/25/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 11/24/2014 | | |
|
|
|
|
Plan assigned to (JG) | | 10/30/2014 | 11/24/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, 11/17 M L2 Hillside**
|
Case Summary (BLD) | | | 11/24/2014 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 11/24/2014 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/24/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 11/24/2014 | | DONE |
Candy A. Nichols
|
|
|
called Michael to let know permit is ready and how much is owed. Left message on his phone
|
Routing - PLAN CHECK | 11/18/2014 | | 11/24/2014 | | PASS |
Javier Guzman
|
|
|
|
Plan resubmittals received | | | 11/20/2014 | | DONE |
|
|
|
received two sets of plans and one set of revised structural calculations
|
1st review completed | | | 11/18/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | | | 11/18/2014 | | FAIL |
Javier Guzman
|
|
|
emailed report to applicant
|
Routing - FIRE | 11/10/2014 | | 11/14/2014 | | PASS |
Scott Arellano
|
|
|
This structure has been evaluated for Fire Department Vehicle Access.
|
Routing - Erosion and Sediment | 11/7/2014 | | 11/10/2014 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE)
WUI Zone A, Class A Roof, Permit for the construction of a new 4437 sq. ft., two story (first story 2116 sq. ft., second story 853 sq. ft., and basement 1468 sq. ft.) single family dwelling with 4 bedrooms, 4 bathrooms, approximately 756 sq. ft. of covered patio’s/porches and 964 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1A/DA zoning and setbacks per planning. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection.
|
Routing - MECHANICAL | 11/3/2014 | | 11/7/2014 | | FAIL |
Troy James
|
|
|
emailed correction to idaho hvac
|
Routing - MECHANICAL | 11/7/2014 | | 11/7/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 11/3/2014 | | 11/3/2014 | | PASS |
Sue Cummings
|
|
|
|
Routing PW Grading-Hillside | 11/3/2014 | | 11/3/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - Addressing | 10/30/2014 | | 11/3/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 11/3/2014 | | 11/3/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/30/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 10/30/2014 | | PASS |
Candy A. Nichols
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/30/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | 10/30/2014 | | | |
|
|
|
|