PubWorks Occupancy Approval | 6/6/2016 | 6/6/2016 | 6/6/2016 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 3/4/2016 | 3/4/2016 | 3/4/2016 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
Issue PAID IN FULL permit | | | 1/16/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 1/16/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 12/17/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/17/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Case Summary (BLD) | | | 12/17/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Telephone call | | | 12/17/2014 | | DONE |
Christina Prado
|
|
|
Called David to advise permit is ready pending GC & RP and gave fees due
|
Permit Ready to Issue | | | 12/17/2014 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 11/21/2014 | | 12/17/2014 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - FIRE | 12/16/2014 | 12/16/2014 | 12/16/2014 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Plan resubmittals received | | | 12/12/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheet marked Sheet 9
|
Telephone call | | | 12/4/2014 | | DONE |
Candy A. Nichols
|
|
|
called Jeremy Amar to let know fire plan review failed. Left message on his machine
|
1st review completed | | | 11/24/2014 | | DONE |
|
|
|
Failed: Fire
|
Routing - FIRE | 11/24/2014 | | 11/24/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 11-24-14
|
Routing - PLANNING | 11/20/2014 | | 11/21/2014 | | PASS |
Joshua Johnson
|
|
|
|
Routing - Design Review | 11/21/2014 | | 11/21/2014 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLUMBING | 11/18/2014 | | 11/20/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 11/13/2014 | | 11/18/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 11/18/2014 | | 11/18/2014 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE)
3.75 Acre Env. Sensative Apartment Complex with Site Improvements. Site is bordered by both the Ridenbaugh Canal and South Slough. Installation of underground utilities, roads, curb and gutter, sidewalks, landscaping and other infrastructure necessary for dev. of apartment buildings.
|
Routing PW Drainage | 11/18/2014 | | 11/18/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Street Lights | 11/18/2014 | | 11/18/2014 | | PASS |
Mike D Hedge
|
|
|
No street lights required.
|
Routing PW Solid Waste | | | 11/17/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Plan resubmittals received | | | 11/17/2014 | | DONE |
|
|
|
received three copies of sheet 5 - given to Candy
|
Plan resubmittals received | | | 11/17/2014 | | DONE |
Candy A. Nichols
|
|
|
received 3 sheets of #5-took plans from Jennifer B, added sheets to plans and took back to Jennifer B
|
Routing PW Sewer Design | 11/14/2014 | | 11/14/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Drainage | 11/12/2014 | | 11/13/2014 | | FAIL |
Jason C. Taylor
|
|
|
Need 3 copies of Sheet 5 and new drainage calculations (slope or seepage bed?) Jason Taylor ###-####
|
Routing - Addressing | 11/6/2014 | | 11/12/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 11/6/2014 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 11/6/2014 | | 11/6/2014 | | PASS |
Dave Abo
|
|
|
ROS 9581
|
Recd Pcfee & Taken To Pln CK | | | 11/4/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | 11/4/2014 | | | |
|
|
|
|