DOC - Permit Finaled | | | 12/23/2015 | | DONE |
|
|
|
|
BLD-Final | 3/12/2015 | 3/13/2015 | 3/13/2015 | A | PASS |
Jim Storey
|
|
|
Please call Dutch 1/2 hr prior to arrival Thank You Phone #: ###-#### Inspection requested via web by Dennis Harmon built per reviewed plan.
|
FIRE-Final Inspection | 3/12/2015 | 3/13/2015 | 3/13/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. Provide the two exit signs per the approved plans prior to a building inspection
|
BLD-Ceiling Grid Inspection | 2/27/2015 | 2/27/2015 | 2/27/2015 | P | PASS |
Jim Storey
|
|
|
Please call Dutch 1/2 hour prior to arrival, Thank you Phone #: ###-#### Inspection requested via web by Dennis Harmon
|
FIRE-Conference | 2/10/2015 | 2/10/2015 | 2/10/2015 | P | DONE |
Forrest France
|
|
|
On site visit regarding exiting requirements, door hardware, fire sprinkler, fire alarm and hood suppression permit work. Need to revise plans to show accurate existing door swing at the kitchen area service exit.
|
BLD-Framing/Rough-in | 2/2/2015 | 2/2/2015 | 2/2/2015 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Dennis Harmon pending hvac aproval duct bath fans
|
BLD-Wall Bracing | 12/19/2014 | 12/22/2014 | 12/22/2014 | A | PASS |
Jim Storey
|
|
|
nail sheer// randey Phone #: ###-####
|
BLD-Framing/Rough-in | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Jim Storey
|
|
|
Randy Phone #: ###-####
|
Inspection Record Card- Bld | | | 12/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue PAID IN FULL permit | | | 12/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
1st review completed | | | 12/8/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/8/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (TLW) | 12/4/2014 | | 12/8/2014 | | PASS |
Tim L. Woodard
|
|
|
Dimising wall for pizza rest.
|
Routing - PLAN CHECK | 12/4/2014 | | 12/8/2014 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Sewer Rating | 12/4/2014 | | 12/8/2014 | | PASS |
Beverly Mountain
|
|
|
Pizza Pie permitted under other permit. This is just wall and grease abatement. bam
|
Routing PW Environmental | 12/4/2014 | | 12/4/2014 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 12/4/2014 | | 12/4/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 12/4/2014 | | 12/4/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLUMBING | 12/4/2014 | | 12/4/2014 | | PASS |
Bill VanDegrift
|
|
|
new grease interceptor with future waste stubbed into the building and capped.
|
Intake Approval | | | 12/4/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 11/10/2014 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see change marks on cover sheet.
|
Application received | | | 11/5/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 5 2014 3:15PM
|