Print Statement | | | 10/5/2015 | | DONE |
|
|
|
|
Second Notice | | 8/21/2015 | 9/15/2015 | | DONE |
|
|
|
Mailed 9/16/15
****Send to parcel owner per GC's request
|
First Notice | | 8/2/2015 | 8/11/2015 | | DONE |
Christina Prado
|
|
|
Mailed 8-12
Received request to send future notices to the Parcel Owners, Summit Development to get final figures
|
Permanent Occupancy | | | 7/23/2015 | | DONE |
|
|
|
|
BLD-Final | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Mike Jordan
|
|
|
Pool Inspection Phone #: ###-#### Inspection requested via web by Tyler Hildebrand. Will be ok for perm occ. once zoning signs perm.
|
FIRE-Final Inspection | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Troy Cobbley
|
|
|
Life Safety passed. The panic hardware has not been installed on the south facing gate yet.
|
BLD-Final | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | PASS |
Dave Hannah
|
|
|
building final Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
FIRE-Final Inspection | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or notes on site. I did note and verified with Carl Westfall that panic hardware is required on both exit gates and emergency lighting is required for the pool area.
|
BLD-Final | 7/1/2015 | 7/2/2015 | 7/2/2015 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tyler Hildebrand
|
FIRE-Final Inspection | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide approved panic hardware as per the approved plans. Will need to verify if emergency lighting is required.
|
Zoning Approval | 7/2/2015 | 7/2/2015 | 7/2/2015 | | PASS |
Josh Wilson
|
|
|
|
BLD-Energy code compliance | 4/28/2015 | 4/29/2015 | 4/29/2015 | A | PART |
Mike Jordan
|
|
|
insulation inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson. insulation ok. needs mech. permit for bathroom vent fans. Pending mech. rough in inspection.
|
BLD-Framing/Rough-in | 4/27/2015 | 4/27/2015 | 4/27/2015 | P | PASS |
Jim Sly
|
|
|
rough framing and shear inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
|
BLD-Energy code compliance | 2/26/2015 | 2/27/2015 | 2/27/2015 | A | PART |
Jim Sly
|
|
|
Vicki Phone #: ###-#### Foundation insulation only.......OK.
|
BLD-Foundation | 2/23/2015 | 2/24/2015 | 2/24/2015 | P | CANC |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Foundation | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | PASS |
Mike Jordan
|
|
|
wall //MANUAL Phone #: ###-####
|
BLD-Footing | 2/20/2015 | 2/23/2015 | 2/23/2015 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/18/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 2/18/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 1/23/2015 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/2015 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 1/23/2015 | | DONE |
|
|
|
Need a GC form and Revis. Cert. of Value
All requirements met
|
Plan assigned to (SRZ) | 12/8/2014 | | 1/23/2015 | | PASS |
Sam Zahorka
|
|
|
1sr review completed
|
Routing - PLAN CHECK | 1/21/2015 | | 1/21/2015 | | PASS |
Sam Zahorka
|
|
|
Pending ESC to PASS
|
Routing - PLANNING | 12/8/2014 | | 1/21/2015 | | PASS |
Susan Riggs
|
|
|
passed in ePlanReview
|
Route to Impact Fee Review | 12/17/2014 | 12/20/2014 | 12/19/2014 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 12/17/2014 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 12/8/2014 | | 12/17/2014 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - Design Review | 12/8/2014 | | 12/16/2014 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 12/8/2014 | | 12/15/2014 | | PASS |
Scott Arellano
|
|
|
No seperate comments attached to plans. At least one fire extinguisher is required for this building based on occupancy. Final approval will be subject to satisfactory field inspection by the PDS/Fire inspector.
|
Routing - PLUMBING | 12/8/2014 | | 12/8/2014 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Pending Assignment by JCM | 12/8/2014 | | 12/8/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 12/8/2014 | | 12/8/2014 | | PASS |
Todd Tucker
|
|
|
parcel was created with ROS14-00001 (9658)
|
Routing - Addressing | 12/8/2014 | | 12/8/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 12/8/2014 | | 12/8/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 12/8/2014 | | 12/8/2014 | | PASS |
Evan Jenkins
|
|
|
This work was described in previously submitted and approved SWPPP. ESC Submission Requirements Met for Issuance of ESC Permit
|
Application received | | | 11/5/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 5 2014 3:43PM
|