BLD-Final | 4/13/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Tony Young
|
|
|
call for access Phone #: ###-#### Inspection requested via web by David Wipper
|
DOC - Permit Finaled | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
PubWorks Occupancy Approval | 4/6/2015 | 4/6/2015 | 4/6/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Wall cover | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: 8507182 >> Inspection requested via mobile web by dave wipper. 5/8 type x rock on soffits ok.
|
BLD-Energy code compliance | 1/17/2015 | 1/21/2015 | 1/21/2015 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper
|
BLD-Framing/Rough-in | 1/20/2015 | 1/21/2015 | 1/21/2015 | A | PASS |
Tony Young
|
|
|
Phone #: 8507182 >> Inspection requested via mobile web by dave wipper
|
BLD-Framing/Rough-in | 1/17/2015 | 1/20/2015 | 1/20/2015 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper,, need mech pass 1st
|
BLD-Wall Bracing | 1/5/2015 | 1/6/2015 | 1/6/2015 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by David Wipper,, exterior shear ok
|
BLD-Foundation | 12/11/2014 | 12/11/2014 | 12/11/2014 | P | PASS |
Phil Shearer
|
|
|
Sean Phone #: ###-####-pour time 1:00
|
BLD-Footing | 12/9/2014 | 12/9/2014 | 12/9/2014 | P | PASS |
Phil Shearer
|
|
|
Shawn Phone #: ###-####-pour time 3:00
|
PubWorks Subgrade Approval | 12/9/2014 | 12/9/2014 | 12/9/2014 | | DONE |
Jason C. Taylor
|
|
|
*MAIN LEVEL ONLY--REMOVE ALL LOOSE /WET SOIL 6"-8" deep***A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 12/5/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/5/2014 | | DONE |
|
|
|
|
OVERRIDE | | | 12/4/2014 | | |
|
|
|
|
Plan assigned to (JG) | 11/12/2014 | 11/12/2014 | 12/4/2014 | | PASS |
Javier Guzman
|
|
|
1st review completed, 12/01 M L2 Hillside ePlan**
|
Routing - PLAN CHECK | 12/1/2014 | | 12/4/2014 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2014 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/4/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 12/1/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 11/12/2014 | | 12/1/2014 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - MECHANICAL | 11/12/2014 | | 11/17/2014 | | FAIL |
Troy James
|
|
|
emailed correction to idaho hvac
|
Routing - MECHANICAL | 11/17/2014 | | 11/17/2014 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 11/12/2014 | 11/12/2014 | 11/14/2014 | | PASS |
Scott Arellano
|
|
|
This structure has been evaluated for Fire Department Vehicle Access.
|
Routing PW Grading-Hillside | 11/12/2014 | | 11/13/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLANNING | 11/12/2014 | | 11/13/2014 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 11/12/2014 | | 11/13/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 11/12/2014 | | 11/13/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 11/12/2014 | | 11/13/2014 | | PASS |
Evan Jenkins
|
|
|
Permit for the construction of a new 3111 sq. ft., two story (first story 2668 sq. ft., second story 443 sq. ft.) single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately 75 sq. ft. of covered patio’s/porches and 1200 sq. ft. attached garage per the approved plans, plan review report and any notations. A-1 zoning and setbacks per planning.
|
Intake Approval | | | 11/12/2014 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/12/2014 | | DONE |
|
|
|
|
Application received | | | 11/6/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2014 9:16AM
|