VOIDED CHANGE STATUS | | | 5/6/2015 | | DONE |
|
|
|
Void per request, applicant will resubmit for new structure. This permit in place for retaining wall only
|
Meeting | | | 4/8/2015 | | DONE |
Rita DeYoung
|
|
|
customer sent email saying the only portion of the work that he is doing is the retaining wall only. The home will be demo and rebuilt per Matt Stevens.
|
PubWorks Occupancy Approval | 3/25/2015 | 3/25/2015 | 3/25/2015 | | DONE |
Jason C. Taylor
|
|
|
****RETAINING WALLS ONLY*****A letter from the applicant’s civil engineer indicating that the retaining wall construction is acceptable has been received by Public Works. Jason Taylor ###-####.
|
PubWorks Subgrade Approval | 3/5/2015 | 3/5/2015 | 3/5/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the rock retaining wall footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Meeting | | | 2/10/2015 | | DONE |
|
|
|
Homeowner came in to talk about getting a refund on this permit and possibly taking out a new permit for a new sfd.
|
Telephone call | | | 1/27/2015 | | DONE |
Candy A. Nichols
|
|
|
called Matt to let know the plan mod was ready and how much is owed. I asked him if he would sign the permit app when he came in. It was not signed at intake
|
CHANGE STATUS TO (ISS) | | | 1/27/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 1/26/2015 | | |
|
|
|
|
Routing Walk-In (Zoning) | 1/26/2015 | 1/26/2015 | 1/26/2015 | A | PASS |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 1/26/2015 | 1/26/2015 | 1/26/2015 | P | PASS |
Tisha Gallop
|
|
|
retaining rock wall
|
Routing Walk-In (PW Hillside) | 1/23/2015 | 1/23/2015 | 1/26/2015 | P | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the retaining wall subgrade is acceptable must be approved by Public Works prior to installation of rockery wall. Civil engineers approval letter must be submitted once the wall is completed and prior to final occupancy request. Call Jason Taylor at ###-####.
|
Inspection Record Card- Bld | | | 1/26/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/26/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Routing Walk-In (BLD) | 1/22/2015 | 1/22/2015 | 1/22/2015 | P | PASS |
Tisha Gallop
|
|
|
modification to permit to include reconstruction of 1st story walls to ceiling height of 9'
|
Inspection Record Card- Bld | | | 1/22/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/22/2015 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | PASS |
Tisha Gallop
|
|
|
questions on modification to heighten 1st story to 9ft. Option to lift 2nd story and build up fully engineered cripple wall above 1st story or lift 2nd story and completely rebuild 1st story walls at height desired.
|
BLD-Conference | 1/8/2015 | 1/12/2015 | 1/12/2015 | A | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, frame ?s
|
BLD-Foundation | 12/19/2014 | 12/22/2014 | 12/22/2014 | A | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | CANC |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/17/2014 | 12/18/2014 | 12/18/2014 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/18/2014 | 12/18/2014 | 12/18/2014 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/17/2014 | 12/17/2014 | 12/17/2014 | P | NR |
Jim Sly
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron No Humans or forms on site.
|
BLD-Footing | 12/14/2014 | 12/15/2014 | 12/15/2014 | A | NR |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/8/2014 | 12/9/2014 | 12/9/2014 | A | NR |
Tony Young
|
|
|
call 1st,, Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | NR |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
PubWorks Subgrade Approval | 12/8/2014 | 12/8/2014 | 12/8/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 11/24/2014 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 11/21/2014 | | |
|
|
|
|
Routing - MECHANICAL | 11/21/2014 | | 11/21/2014 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/21/2014 | | |
|
|
|
|
Plan Reviewer's activity | | | 11/21/2014 | | PASS |
|
|
|
|
Telephone call | | | 11/21/2014 | | DONE |
|
|
|
called mathew told permit was ready, fees due
|
Permit Ready to Issue | | | 11/21/2014 | | DONE |
|
|
|
|
Telephone call | | | 11/14/2014 | | DONE |
|
|
|
with Mr. Stevens to follow up on monday's e-mail reqest for an ACCA report. I had misspelled the address. All is in the process now. 11-14-2014 10;00 PEP
|
Routing Walk-In (BLD) | 11/10/2014 | 11/10/2014 | 11/13/2014 | P | FAIL |
Perry Paine
|
|
|
need Manual J report
|
Routing - Erosion and Sediment | 11/6/2014 | | 11/13/2014 | | PASS |
Perry Paine
|
|
|
waiver approved by evan
|
Routing PW Grading-Hillside | 11/6/2014 | | 11/10/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Routing Walk-In (Zoning) | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 11/6/2014 | 11/6/2014 | 11/6/2014 | P | FAIL |
Javier Guzman
|
|
|
Need Hillside review
|
1st review completed | | | 11/6/2014 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 11/6/2014 | | | |
|
|
|
|