Print Statement | | | 9/22/2015 | | DONE |
|
|
|
|
Third Notice | | 8/16/2015 | 9/15/2015 | | DONE |
|
|
|
|
Second Notice | | 7/19/2015 | 8/11/2015 | | DONE |
Candy A. Nichols
|
|
|
mailed notice
|
First Notice | | 6/25/2015 | 7/9/2015 | | DONE |
|
|
|
mailed in 7-10-15
|
Zoning Approval | 6/15/2015 | 6/15/2015 | 6/15/2015 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 6/15/2015 | | DONE |
|
|
|
|
BLD-Final | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PASS |
Phil Shearer
|
|
|
Call 20 mins before //Bill Phone #: ###-####
|
FIRE-Final Inspection | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | PASS |
Katie Marron
|
|
|
Life safety pass
|
BLD-Foundation | 4/9/2015 | 4/10/2015 | 4/10/2015 | A | PASS |
Phil Shearer
|
|
|
Rebar // Bruce Phone #: ###-####
|
BLD-Foundation | 4/3/2015 | 4/7/2015 | 4/7/2015 | A | PASS |
Phil Shearer
|
|
|
Rebar // Bruce Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/13/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/13/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 3/6/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 12/15/2014 | 12/15/2014 | 3/6/2015 | | PASS |
Carl Westfall
|
|
|
HARRIS RANCH COMMUNICATIONS - New Commercial - ePlanReview - (15 days - Jan 1)
|
Routing - PLAN CHECK | 3/5/2015 | | 3/6/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
need GC, RP & ACHD
|
Plan resubmittals received | | | 3/5/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 1/27/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/26/2015 | | 1/27/2015 | | FAIL |
Carl Westfall
|
|
|
Items not resolved
|
Plan resubmittals received | | | 1/26/2015 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/9/2015 | 1/12/2015 | 1/15/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 1/9/2015 | | FAIL |
Carl Westfall
|
|
|
Failed building
|
Plan resubmittals requested | | | 1/9/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/15/2014 | | 1/9/2015 | | FAIL |
Carl Westfall
|
|
|
|
Routing - FIRE | 12/15/2014 | 12/15/2014 | 12/22/2014 | | PASS |
Scott Arellano
|
|
|
If stationary storage battery systems are present with this facility, the provisions of IFC section 608 may apply. Provisions include, but are not limited to, exterior signage on building doors indicating the presence of energized electrical circuits and battery systems etc.
|
Routing - PLANNING Land Div | 12/15/2014 | | 12/16/2014 | | PASS |
Dave Abo
|
|
|
Lot 1, Block 15 of Dallas Harris Estates Subdivision No. 3
|
Routing - Design Review | 12/15/2014 | | 12/15/2014 | | PASS |
Josh Wilson
|
|
|
Ok per DRH14-00395.
|
Routing - Addressing | 12/15/2014 | | 12/15/2014 | | PASS |
Emily Dixon
|
|
|
Address corrected to 3680 E Warm Springs Ave.
|
Routing - PUBLIC WORKS | 12/15/2014 | | 12/15/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 12/15/2014 | | 12/15/2014 | | PASS |
Evan Jenkins
|
|
|
(HARRIS RANCH COMMUNICATIONS) New communications tower and shelter adjacent to the existing fire station building. Construction of 555sq ft' concrete pad, sidewalks for placement of 300 sq ft prefab building. Trenching approx 110'ft, not exceeding 4'ft deep for power
|
Pending Assignment by JCB | 12/15/2014 | | 12/15/2014 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 12/12/2014 | | PASS |
|
|
|
Plan intake completed. OK to sumit.
|
Intake Approval | | | 12/12/2014 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Westfall and plan review fees paid.
|
Intake Approval | | | 11/14/2014 | | FAIL |
|
|
|
Please resolve the items circled on the plan intake checklist.
|
Application received | | | 11/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 10 2014 2:42PM
|