Reopen Permit (ISS) | | | 3/23/2015 | | DONE |
|
|
|
reopen per bob to add mech permit
|
CHANGE STATUS TO (FNL) | | | 3/23/2015 | | DONE |
|
|
|
Mech. Permits have been added
|
Letter of compliance/Occupancy | | | 2/27/2015 | | DONE |
|
|
|
|
BLD-Final | 2/24/2015 | 2/24/2015 | 2/24/2015 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
FIRE-Final Inspection | 2/23/2015 | 2/23/2015 | 2/24/2015 | P | PASS |
Forrest France
|
|
|
|
DOC - Permit Finaled | | | 2/24/2015 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 12/9/2014 | 12/9/2014 | 12/9/2014 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Conference | 12/8/2014 | 12/9/2014 | 12/9/2014 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/8/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 12/8/2014 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 12/3/2014 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 11/13/2014 | 11/13/2014 | 11/20/2014 | | PASS |
Carl Westfall
|
|
|
Suite 360 (7 days - Nov 21)
|
Routing - PLAN CHECK | 11/13/2014 | | 11/20/2014 | | PASS |
Carl Westfall
|
|
|
Drawings approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2014 | | DONE |
|
|
|
|
1st review completed | | | 11/20/2014 | | DONE |
Carl Westfall
|
|
|
|
Intake Approval | | | 11/13/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 11/13/2014 | | 11/13/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 11/13/2014 | | 11/13/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 11/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 10 2014 3:11PM
|