Letter of compliance/Occupancy | | | 8/20/2015 | | DONE |
|
|
|
|
BLD-Final | 8/18/2015 | 8/18/2015 | 8/18/2015 | A | PASS |
Mike Jordan
|
|
|
Please inspect at approximately 10 am and call brian prior. Phone #: ###-#### Inspection requested via web by Brian Stark
|
DOC - Permit Finaled | 8/18/2015 | 8/18/2015 | 8/18/2015 | P | PASS |
Mike Jordan
|
|
|
|
Case Summary (BLD) | | | 8/17/2015 | | |
|
|
|
|
BLD-Wall Bracing | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Mike Jordan
|
|
|
Drywall fastening. Please call Brian prior to inspection. Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Energy code compliance | 4/29/2015 | 4/30/2015 | 4/30/2015 | A | PASS |
Mike Jordan
|
|
|
Please call brian prior Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Framing/Rough-in | 4/28/2015 | 4/29/2015 | 4/29/2015 | A | PASS |
Mike Jordan
|
|
|
Please call Brian 20 minutes prior Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 4/21/2015 | 4/22/2015 | 4/22/2015 | P | PASS |
Mike Jordan
|
|
|
Shear Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Wall Bracing | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | PASS |
Mike Jordan
|
|
|
Shear. Please call brian prior. Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Footing | 3/12/2015 | 3/12/2015 | 3/12/2015 | P | PASS |
Mike Jordan
|
|
|
Stair footings and rebar Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Energy code compliance | 3/9/2015 | 3/10/2015 | 3/10/2015 | A | PASS |
Mike Jordan
|
|
|
Foundation insulation Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD-Foundation | 2/27/2015 | 2/27/2015 | 2/27/2015 | A | PART |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | PASS |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
Issue PAID IN FULL permit | | | 1/2/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 12/24/2014 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Bld | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 12/24/2014 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/23/2014 | | 12/23/2014 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2014 | | DONE |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 12/23/2014 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 11/25/2014 | | 12/23/2014 | | PASS |
Tisha Gallop
|
|
|
plan check
|
1st review completed | | | 12/1/2014 | | FAIL |
Tisha Gallop
|
|
|
failed plan check, mechanical
|
Routing - MECHANICAL | 12/1/2014 | | 12/1/2014 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 11/25/2014 | | 12/1/2014 | | FAIL |
Tisha Gallop
|
|
|
need clarification lateral engineering
|
Plan assigned to (JG) | 11/17/2014 | 11/17/2014 | 11/25/2014 | | DEFR |
Javier Guzman
|
|
|
11/28 F L1**
|
Routing - MECHANICAL | 11/20/2014 | | 11/25/2014 | | FAIL |
Troy James
|
|
|
emailed correction to canfield
|
Routing - PLANNING | 11/19/2014 | | 11/20/2014 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 11/18/2014 | | 11/19/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 11/19/2014 | | 11/19/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Addressing | 11/17/2014 | | 11/18/2014 | | FAIL |
Jason C. Taylor
|
|
|
Application address does not match site plan addresses. Please revise plans to correct addresses/street names. Jason Taylor ###-####.
|
Plans ACCEPTED BY PLAN TECH | | | 11/17/2014 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/17/2014 | | DONE |
|
|
|
|
Intake Approval | | | 11/17/2014 | | PASS |
|
|
|
|
Application received | | 11/14/2014 | | | |
|
|
|
|