BLD-Final | 3/23/2015 | 3/24/2015 | 3/24/2015 | P | PASS |
Jim Storey
|
|
|
Corrections have been completed, as requested by Forrest, and Fire-Final is scheduled for AM. Please call Todd. Phone #: ###-#### Inspection requested via web by Todd Weltner
|
FIRE-Final Inspection | 3/23/2015 | 3/24/2015 | 3/24/2015 | A | PASS |
Forrest France
|
|
|
Verified noted correction items for completion. Life safety passed.
|
BLD-Final | 3/20/2015 | 3/23/2015 | 3/23/2015 | P | NR |
Jim Storey
|
|
|
Please call Todd to coordinate. Phone #: ###-#### Inspection requested via web by Todd Weltner fire c/n
|
FIRE-Final Inspection | 3/20/2015 | 3/23/2015 | 3/23/2015 | A | FAIL |
Forrest France
|
|
|
Items noted include door hardware revisions at the new office and conference room, post fire extinguishers per plan.
|
BLD-Framing/Rough-in | 1/27/2015 | 1/28/2015 | 1/28/2015 | P | PASS |
Jim Storey
|
|
|
Please call Kent if any questions. Phone #: ###-#### Inspection requested via web by Todd Weltner
|
Issue PAID IN FULL permit | | | 1/23/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/23/2015 | | DONE |
|
|
|
|
Telephone call | | | 1/21/2015 | | DONE |
|
|
|
emailed Todd the remaining fees
|
Permit Ready to Issue | | | 1/21/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 11/19/2014 | 11/19/2014 | 12/9/2014 | | PASS |
Carl D Madsen
|
|
|
Create Common Good
|
Routing - PUBLIC WORKS | 12/9/2014 | | 12/9/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLAN CHECK | 12/9/2014 | | 12/9/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2014 | | DONE |
|
|
|
|
Routing Off Site - C.D.H | 11/19/2014 | | 12/1/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 11/20/2014 | | 12/1/2014 | | PASS |
Rick Christenson
|
|
|
|
1st review completed | | | 12/1/2014 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 11/19/2014 | | 11/25/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 11/19/2014 | | 11/25/2014 | | PASS |
Troy James
|
|
|
no mechanical to review
|
Routing - PUBLIC WORKS | 11/19/2014 | | 11/20/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 11/20/2014 | | 11/20/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 11/19/2014 | | 11/19/2014 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 11/19/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLUMBING | 11/19/2014 | | 11/19/2014 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - Design Review | 11/19/2014 | | 11/19/2014 | | PASS |
Andrea Tuning
|
|
|
|
Application received | | | 11/18/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 18 2014 4:17PM
|