Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD14-03415
StatusFinaled
Name HARDWARE SOLUTIONS INC
Site Address 7881 W MOSSY CUP ST
Project NameDoor Service of Idaho
Customer Number 
ePlanReviewYes
Description
(DOOR SERVICE OF IDAHO) - To construct a new 6,915 square foot, one story, light industrial building and related site improvements. This building is constructed of of steel stud walls with a wood truss roof system. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  1/9/2017 DONE
Left a message for Jane to go over values
Second Notice 11/25/201612/14/2016 DONE
Mailed 12-15
First Notice 11/4/201611/15/2016 DONE
Mailed 11-16-16
Permanent Occupancy  10/25/2016 DONE
Zoning Approval10/20/201610/20/201610/20/2016 DONE
DetailsAndrea Tuning
Temporary Occupancy8/5/201611/3/20168/5/2016 DONE
DetailsCarlos Velazquez
BLD-Final7/27/20167/28/20167/28/2016APASS
DetailsMike Jordan
Paul Phone #: ###-####. Will be ok for perm occ. once zoning sings perm.
Zoning Approval Temp7/27/20167/27/20167/27/2016 DONE
DetailsAndrea Tuning
Bond has been placed for the awnings
BLD-Final7/25/20167/25/20167/25/2016PNR
DetailsMike Jordan
Needs zoning final.
BLD-Final7/25/20167/25/20167/25/2016PCANC
DetailsMike Jordan
Paul Phone #: ###-####.
FIRE-Final Inspection7/22/20167/25/20167/25/2016APASS
DetailsTroy Cobbley
Life safety passed. The south east exit sign was non-functional but being replaced when I left. To be tested with the building inspector.
CHANGE STATUS TO (ISS)  7/22/2016 DONE
(F) Reprint permit  7/22/2016 DONE
OVERRIDE  7/11/2016  
Expiration Notice7/11/20168/1/20167/11/2016 DONE
DetailsBrittany Hill
Permit Ready to Issue  7/11/2016 DONE
DO NOT RE ISSUE PLAN MOD
Plan Reviewer's activity  6/28/2016 DONE
After a conversation with Brian Murphy he indicated PW did not need to do a "Field Inspection". He has recieved a letter from the engineer and was never routed plans in the first review period. 6-28-16 TLW
PLANS/APPL TAKEN TO FRONT DESK  6/28/2016 DONE
Plan assigned to (TLW)3/29/2016 6/28/2016 PASS
DetailsTim L. Woodard
Plan Mod
Routing - PLAN CHECK3/29/2016 6/28/2016 PASS
DetailsTim L. Woodard
Routing - PUBLIC WORKS3/29/2016 6/28/2016 CANC
DetailsJennifer Bruner
PLAN MOD- as per Brian Murphy not needed
Routing PW Drainage3/29/2016 6/28/2016 CANC
DetailsBrian Murphy
PW DRAINAGE BLD APPROVED; as per Brian Murphy not needed
PubWorks Occupancy Approval4/29/20164/29/20164/29/2016 DONE
DetailsBrian Murphy
Route to Impact Fee Review3/29/20164/1/20163/31/2016 PASS
DetailsCindy M. Gould
Plan Modification Accepted  3/29/2016 DONE
received modifications to the grading plans
BLD-Framing/Rough-in2/5/20162/5/20162/5/2016PPART
DetailsMike Jordan
Paul Phone #: ###-####. interior steel stud walls and hardlids ok. Noted that transfer shower does not have the required 48 inch clearance from control wall.
BLD-Ceiling Grid Inspection10/26/201510/26/201510/26/2015PCANC
DetailsMike Jordan
Paul Phone #: ###-####
BLD-Framing/Rough-in10/26/201510/26/201510/26/2015PPASS
DetailsMike Jordan
Paul Phone #: ###-####. Ok to rock ceiling only.
Case Summary (BLD)  10/20/2015 DONE
BLD-Wall Bracing8/13/20158/14/20158/14/2015APASS
DetailsMike Jordan
Paul Phone #: ###-####
BLD-Foundation2/19/20152/20/20152/20/2015PPASS
DetailsMike Jordan
Jeff Phone #: ###-####
BLD-Footing2/17/20152/17/20152/17/2015PPASS
DetailsMike Jordan
Jeff-rebar Phone #: ###-####. Will have special inspection. perimeter footing ok.
OVERRIDE  2/2/2015  
Issue PAID IN FULL permit  2/2/2015 DONE
DetailsCandy A. Nichols
Print Occupancy Form  2/2/2015 DONE
DetailsCandy A. Nichols
Permit Ready to Issue  2/2/2015 DONE
DetailsCandy A. Nichols
Routing - PLAN CHECK1/23/2015 1/29/2015 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  1/29/2015 DONE
DetailsJohn Menard
Plan assigned to (JCM)11/25/2014 1/29/2015 PASS
DetailsJohn Menard
1st Review Complete 12/20/2014
Routing Off Site - STRUCTURAL1/23/2015 1/26/2015 PASS
DetailsJohn Menard
Routing - FIRE1/7/20151/15/20151/15/2015 PASS
DetailsScott Arellano
Attached comments to case.
Routing Off Site - STRUCTURAL1/7/2015 1/14/2015 FAIL
DetailsJohn Menard
Routing - PLAN CHECK1/7/2015 1/13/2015 PASS
DetailsJohn Menard
Routing - PUBLIC WORKS1/7/2015 1/8/2015 PASS
DetailsJennifer Bruner
Routing - PLANNING Land Div1/7/2015 1/7/2015 PASS
DetailsTodd Tucker
Routing - Addressing1/7/2015 1/7/2015 PASS
DetailsEmily Dixon
1st review completed  12/20/2014 FAIL
DetailsJohn Menard
Routing - PLAN CHECK11/25/2014 12/20/2014 FAIL
DetailsJohn Menard
Routing PW Drainage11/25/2014 12/5/2014 FAIL
DetailsBrian Murphy
NEEDS C-33 SAND
Routing PW Sewer Design11/25/2014 12/3/2014 PASS
DetailsKyle S. Rosenmeyer
Routing Off Site - STRUCTURAL11/25/2014 12/3/2014 FAIL
DetailsJohn Menard
Routing - FIRE11/25/2014 11/28/2014 FAIL
DetailsCraig D. Hanson
See Fire Plan Review 11-28-14
Routing - PLUMBING11/25/2014 11/28/2014 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing11/25/2014 11/26/2014 FAIL
DetailsEmily Dixon
Building is on two parcels.
Routing PW Solid Waste11/25/2014 11/26/2014 PASS
DetailsPeter J. McCullough
Routing PW Sewer Rating11/25/2014 11/25/2014 PASS
DetailsBeverly Mountain
Routing PW Street Lights11/25/2014 11/25/2014 PASS
DetailsMike D Hedge
Routing - PUBLIC WORKS11/25/2014 11/25/2014 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment11/25/2014 11/25/2014 PASS
DetailsEvan Jenkins
(SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE)
Door Services of Idaho - Construct a new building and site improvements
Routing - PLANNING Land Div11/25/2014 11/25/2014 FAIL
DetailsDave Abo
Do not issue Building Permit until ROS14-00066 has been finaled.
Routing - Design Review11/25/2014 11/25/2014 PASS
DetailsAndrea Tuning
Intake Approval  11/25/2014 PASS
DetailsJohn Menard
Pending Assignment by JCM11/25/2014 11/25/2014 DONE
DetailsJohn Menard
Application received  11/20/2014 DONE
Application submitted via PDS Online on Nov 20 2014 8:24AM