Telephone call | | | 1/9/2017 | | DONE |
|
|
|
Left a message for Jane to go over values
|
Second Notice | | 11/25/2016 | 12/14/2016 | | DONE |
|
|
|
Mailed 12-15
|
First Notice | | 11/4/2016 | 11/15/2016 | | DONE |
|
|
|
Mailed 11-16-16
|
Permanent Occupancy | | | 10/25/2016 | | DONE |
|
|
|
|
Zoning Approval | 10/20/2016 | 10/20/2016 | 10/20/2016 | | DONE |
Andrea Tuning
|
|
|
|
Temporary Occupancy | 8/5/2016 | 11/3/2016 | 8/5/2016 | | DONE |
Carlos Velazquez
|
|
|
|
BLD-Final | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | PASS |
Mike Jordan
|
|
|
Paul Phone #: ###-####. Will be ok for perm occ. once zoning sings perm.
|
Zoning Approval Temp | 7/27/2016 | 7/27/2016 | 7/27/2016 | | DONE |
Andrea Tuning
|
|
|
Bond has been placed for the awnings
|
BLD-Final | 7/25/2016 | 7/25/2016 | 7/25/2016 | P | NR |
Mike Jordan
|
|
|
Needs zoning final.
|
BLD-Final | 7/25/2016 | 7/25/2016 | 7/25/2016 | P | CANC |
Mike Jordan
|
|
|
Paul Phone #: ###-####.
|
FIRE-Final Inspection | 7/22/2016 | 7/25/2016 | 7/25/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The south east exit sign was non-functional but being replaced when I left. To be tested with the building inspector.
|
CHANGE STATUS TO (ISS) | | | 7/22/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/22/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/11/2016 | | |
|
|
|
|
Expiration Notice | 7/11/2016 | 8/1/2016 | 7/11/2016 | | DONE |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 7/11/2016 | | DONE |
|
|
|
DO NOT RE ISSUE PLAN MOD
|
Plan Reviewer's activity | | | 6/28/2016 | | DONE |
|
|
|
After a conversation with Brian Murphy he indicated PW did not need to do a "Field Inspection". He has recieved a letter from the engineer and was never routed plans in the first review period. 6-28-16 TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2016 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 3/29/2016 | | 6/28/2016 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod
|
Routing - PLAN CHECK | 3/29/2016 | | 6/28/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 3/29/2016 | | 6/28/2016 | | CANC |
Jennifer Bruner
|
|
|
PLAN MOD- as per Brian Murphy not needed
|
Routing PW Drainage | 3/29/2016 | | 6/28/2016 | | CANC |
Brian Murphy
|
|
|
PW DRAINAGE BLD APPROVED; as per Brian Murphy not needed
|
PubWorks Occupancy Approval | 4/29/2016 | 4/29/2016 | 4/29/2016 | | DONE |
Brian Murphy
|
|
|
|
Route to Impact Fee Review | 3/29/2016 | 4/1/2016 | 3/31/2016 | | PASS |
Cindy M. Gould
|
|
|
|
Plan Modification Accepted | | | 3/29/2016 | | DONE |
|
|
|
received modifications to the grading plans
|
BLD-Framing/Rough-in | 2/5/2016 | 2/5/2016 | 2/5/2016 | P | PART |
Mike Jordan
|
|
|
Paul Phone #: ###-####. interior steel stud walls and hardlids ok. Noted that transfer shower does not have the required 48 inch clearance from control wall.
|
BLD-Ceiling Grid Inspection | 10/26/2015 | 10/26/2015 | 10/26/2015 | P | CANC |
Mike Jordan
|
|
|
Paul Phone #: ###-####
|
BLD-Framing/Rough-in | 10/26/2015 | 10/26/2015 | 10/26/2015 | P | PASS |
Mike Jordan
|
|
|
Paul Phone #: ###-####. Ok to rock ceiling only.
|
Case Summary (BLD) | | | 10/20/2015 | | DONE |
|
|
|
|
BLD-Wall Bracing | 8/13/2015 | 8/14/2015 | 8/14/2015 | A | PASS |
Mike Jordan
|
|
|
Paul Phone #: ###-####
|
BLD-Foundation | 2/19/2015 | 2/20/2015 | 2/20/2015 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Footing | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | PASS |
Mike Jordan
|
|
|
Jeff-rebar Phone #: ###-####. Will have special inspection. perimeter footing ok.
|
OVERRIDE | | | 2/2/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/2/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Print Occupancy Form | | | 2/2/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 2/2/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Routing - PLAN CHECK | 1/23/2015 | | 1/29/2015 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/2015 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 11/25/2014 | | 1/29/2015 | | PASS |
John Menard
|
|
|
1st Review Complete 12/20/2014
|
Routing Off Site - STRUCTURAL | 1/23/2015 | | 1/26/2015 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 1/7/2015 | 1/15/2015 | 1/15/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to case.
|
Routing Off Site - STRUCTURAL | 1/7/2015 | | 1/14/2015 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 1/7/2015 | | 1/13/2015 | | PASS |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 1/7/2015 | | 1/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING Land Div | 1/7/2015 | | 1/7/2015 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 1/7/2015 | | 1/7/2015 | | PASS |
Emily Dixon
|
|
|
|
1st review completed | | | 12/20/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PLAN CHECK | 11/25/2014 | | 12/20/2014 | | FAIL |
John Menard
|
|
|
|
Routing PW Drainage | 11/25/2014 | | 12/5/2014 | | FAIL |
Brian Murphy
|
|
|
NEEDS C-33 SAND
|
Routing PW Sewer Design | 11/25/2014 | | 12/3/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing Off Site - STRUCTURAL | 11/25/2014 | | 12/3/2014 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 11/25/2014 | | 11/28/2014 | | FAIL |
Craig D. Hanson
|
|
|
See Fire Plan Review 11-28-14
|
Routing - PLUMBING | 11/25/2014 | | 11/28/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 11/25/2014 | | 11/26/2014 | | FAIL |
Emily Dixon
|
|
|
Building is on two parcels.
|
Routing PW Solid Waste | 11/25/2014 | | 11/26/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Sewer Rating | 11/25/2014 | | 11/25/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Street Lights | 11/25/2014 | | 11/25/2014 | | PASS |
Mike D Hedge
|
|
|
|
Routing - PUBLIC WORKS | 11/25/2014 | | 11/25/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 11/25/2014 | | 11/25/2014 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE)
Door Services of Idaho - Construct a new building and site improvements
|
Routing - PLANNING Land Div | 11/25/2014 | | 11/25/2014 | | FAIL |
Dave Abo
|
|
|
Do not issue Building Permit until ROS14-00066 has been finaled.
|
Routing - Design Review | 11/25/2014 | | 11/25/2014 | | PASS |
Andrea Tuning
|
|
|
|
Intake Approval | | | 11/25/2014 | | PASS |
John Menard
|
|
|
|
Pending Assignment by JCM | 11/25/2014 | | 11/25/2014 | | DONE |
John Menard
|
|
|
|
Application received | | | 11/20/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 20 2014 8:24AM
|