Second Notice | | 5/14/2015 | 6/10/2015 | | DONE |
|
|
|
Mailed out 6-10-15
|
First Notice | 4/15/2015 | 4/15/2015 | 5/4/2015 | | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | PASS |
Mike Jordan
|
|
|
Call half hour before // Ben Phone #: ###-####
|
DOC - Permit Finaled | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 1/29/2015 | 1/29/2015 | 1/29/2015 | P | NR |
Mike Jordan
|
|
|
Tim// inspection for equipment building Phone #: ###-####
|
BLD-Foundation | 1/27/2015 | 1/28/2015 | 1/28/2015 | A | PASS |
Mike Jordan
|
|
|
Rebar // Tim Phone #: ###-####
|
BLD-Foundation | 1/26/2015 | 1/27/2015 | 1/27/2015 | P | NR |
Mike Jordan
|
|
|
Tim// Dan ###-#### Phone #: ###-####. rescheduled for tomorrow in the am.
|
Issue PAID IN FULL permit | | | 12/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 12/19/2014 | | |
|
|
|
|
Plan assigned to (CDM) | 11/21/2014 | 11/21/2014 | 12/19/2014 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/18/2014 | | 12/19/2014 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 12/19/2014 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2014 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/19/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 12/19/2014 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 12/19/2014 | | DONE |
Christina Prado
|
|
|
Called Mark to advise permit is ready pending GC & RP and gave fees due
|
Routing - FIRE | 12/12/2014 | 12/12/2014 | 12/18/2014 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown with no separate review comments attached. The equipment room and building shall be signed in accordance with IFC 608.7 indicating energized battery systems and electrical circuits.
|
Routing - Erosion and Sediment | 12/15/2014 | | 12/15/2014 | | PASS |
Evan Jenkins
|
|
|
ESC Waiver Submitted on 12-12-14 is Sufficient.
Approved.
Verizon Wireless Tower w/ Prefab building thats 11.5' x 25.5'ft
|
Routing - PLAN CHECK | | | 12/12/2014 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 12/12/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 12/3/2014 | 11/21/2014 | 12/3/2014 | | PASS |
Craig D. Hanson
|
|
|
No review required
|
Routing - Erosion and Sediment | 12/2/2014 | | 12/3/2014 | | FAIL |
Evan Jenkins
|
|
|
(ESC Waiver Letter Reqest Required due to new construction of small accessory building)
"VERIZON WIRELESS" For the construction of a new cellular antenna (100') and a associated equipment building (PA# MOD1###-####6) per the approved plans and the attached engineering.
|
Routing - Addressing | | | 12/2/2014 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 12/2/2014 | | 12/2/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING | | | 11/21/2014 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 11/21/2014 | | 11/21/2014 | | PASS |
Dave Abo
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/20/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 11/20/2014 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/20/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | 11/20/2014 | | | |
|
|
|
|