BLD-Final | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | DONE |
Tony Young
|
|
|
Josh Phone #: ###-####
|
DOC - Permit Finaled | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 7/7/2015 | 7/7/2015 | 7/7/2015 | P | NR |
Tony Young
|
|
|
Call 30 mins before // Josh Phone #: ###-####, need hillside
|
BLD-Final | 7/2/2015 | 7/2/2015 | 7/2/2015 | P | NR |
Jim Sly
|
|
|
Josh Phone #: ###-#### No approval from Public Works for drainage.
|
CHANGE STATUS TO (ISS) | | | 7/2/2015 | | DONE |
|
|
|
plan mod fees paid
|
OVERRIDE | | | 7/1/2015 | | |
|
|
|
|
Plan assigned to (JG) | 6/30/2015 | 6/30/2015 | 7/1/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 6/30/2015 | | 7/1/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 7/1/2015 | | 7/1/2015 | | PASS |
David Moser
|
|
|
|
Case Summary (BLD) | | | 7/1/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/1/2015 | | DONE |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 7/1/2015 | | DONE |
|
|
|
plan mod please do not re-issue
|
Telephone call | | | 7/1/2015 | | DONE |
|
|
|
called tro let know the plan mod is ready and how much is owed. Left message at office-also called Josh and left a message
|
Plan Modification Accepted | | | 6/30/2015 | | DONE |
Christina Prado
|
|
|
Stair case modifications, David Moser did a short review but still requests a routing activity
|
BLD-Energy code compliance | 5/5/2015 | 5/6/2015 | 5/6/2015 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 5/5/2015 | 5/5/2015 | 5/5/2015 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####,, ok to cover
|
BLD-Energy code compliance | 4/29/2015 | 4/30/2015 | 4/30/2015 | P | FAIL |
Tony Young
|
|
|
Josh Phone #: ###-####,, correction not completed
|
BLD-Energy code compliance | 4/28/2015 | 4/29/2015 | 4/29/2015 | P | NR |
Tony Young
|
|
|
Insulation // Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 4/28/2015 | 4/29/2015 | 4/29/2015 | P | NR |
Tony Young
|
|
|
Josh Phone #: ###-####,, correction notice not complete
|
BLD-Framing/Rough-in | 4/24/2015 | 4/27/2015 | 4/27/2015 | A | FAIL |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Nail off all simpson hangars, Nail T22 girder trus on opposite face and provide the additional cluster nailing as per truss engineering, seal all penetrations in OSB on open web floor joist for draft stop, Install all MST 48 floor to floor straps on exterior as shown on sheet A4, install the simpson DTT2 with 1/2" diameter all thread in 2 places at deck to interior floor joist with blocking for lateral. Correction notice posted. ok to insulate.
|
BLD-Framing/Rough-in | 4/23/2015 | 4/24/2015 | 4/24/2015 | A | NR |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Needs to complete airseal prior to framing inspection.
|
Plan Modification Accepted | | | 4/21/2015 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 4/21/2015 | | 4/21/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 4/9/2015 | 4/10/2015 | 4/10/2015 | A | PASS |
Phil Shearer
|
|
|
Josh Phone #: ###-####
|
BLD-Wall Bracing | 4/9/2015 | 4/9/2015 | 4/9/2015 | P | FAIL |
Tony Young
|
|
|
Josh Phone #: ###-####,, not done per plan
|
BLD-Wall cover | 4/8/2015 | 4/9/2015 | 4/9/2015 | A | DEFR |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Wall Bracing | 4/8/2015 | 4/8/2015 | 4/8/2015 | P | FAIL |
Tony Young
|
|
|
Josh Phone #: ###-####,, not done
|
BLD-Foundation | 3/3/2015 | 3/3/2015 | 3/3/2015 | P | PART |
Tony Young
|
|
|
Adam Phone #: ###-####,, work in progress,, ok
|
BLD-Wall Bracing | 3/3/2015 | 3/3/2015 | 3/3/2015 | P | NR |
Tony Young
|
|
|
Adam Phone #: ###-####
|
BLD-Footing | 2/27/2015 | 2/27/2015 | 2/27/2015 | P | PART |
Tony Young
|
|
|
Pouring at 2 - Adam Phone #: ###-####
|
BLD-Foundation | 1/30/2015 | 1/30/2015 | 1/30/2015 | P | PART |
Tony Young
|
|
|
Wall. Pouring at 1:30 // Adam Phone #: ###-####,, lower section (9-11 ft) of rear wall ok to pour
|
BLD-Footing | 1/28/2015 | 1/28/2015 | 1/29/2015 | P | PART |
Dave Hannah
|
|
|
Adam Phone #: ###-#### back wall ftg only
|
PubWorks Subgrade Approval | 1/28/2015 | 1/28/2015 | 1/28/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 1/23/2015 | 1/23/2015 | 1/23/2015 | P | CANC |
Dave Hannah
|
|
|
Adam Phone #: ###-#### no geo tect soils signoff
|
Issue PAID IN FULL permit | | | 1/9/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 1/6/2015 | | |
|
|
|
|
Plan assigned to (JG) | 12/3/2014 | 12/3/2014 | 1/6/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 12/19 F L2 Hillside**
|
Telephone call | | | 1/6/2015 | | DONE |
|
|
|
called George- let him know his permit is ready and remaining balance
|
Routing - PLAN CHECK | 1/6/2015 | | 1/6/2015 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 1/6/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/6/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/6/2015 | | DONE |
Christina Prado
|
|
|
|
Override - Parcel Holds | | | 1/6/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 1/6/2015 | | |
|
|
|
|
Plan resubmittals received | | | 12/30/2014 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked A0, A1, A2, A3, A4, A5, A6 & A7; Plans stamped and taken to Javier for further review
|
Routing PW Grading-Hillside | 12/22/2014 | | 12/22/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 12/22/2014 | | 12/22/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING | 12/22/2014 | | 12/22/2014 | | PASS |
David Moser
|
|
|
OK as per CFH14-00041
|
Plan resubmittals received | | | 12/19/2014 | | DONE |
|
|
|
received 3 copies of: sheet C1, Shallow Injection Well Inventory Form, Well Logs, and patio wall engineering. Put with Plans and Took to Jason Taylor's desk
|
Routing PW Grading-Hillside | 12/11/2014 | | 12/15/2014 | | FAIL |
Jason C. Taylor
|
|
|
Need revised grading plans . See email dated 12/15/14 Jason Taylor ###-####
|
Routing - PLAN CHECK | 12/10/2014 | | 12/11/2014 | | FAIL |
Javier Guzman
|
|
|
emailed review report to applicant
|
1st review completed | | | 12/11/2014 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 12/9/2014 | 12/3/2014 | 12/10/2014 | | PASS |
Scott Arellano
|
|
|
This project has been evaluated for Fire Department Vehicle Access.
|
Routing - Erosion and Sediment | 12/8/2014 | | 12/9/2014 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED PRIOR TO EARTH DISTURBANCE)
WUI Zone A, Class A roof, Permit for the construction of a new 2661 sq. ft., two story (first story 1884 sq. ft., basement is 777 sq. ft.) single family dwelling with 3 bedrooms, 3 bathrooms, approximately 731 sq. ft. of covered patio’s/porches and 1032 sq. ft. attached garage per the approved plans
|
Routing - MECHANICAL | 12/9/2014 | | 12/9/2014 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 12/8/2014 | | DONE |
Candy A. Nichols
|
|
|
resubmitted 3 sheets of C1-took to JG
|
Routing - MECHANICAL | 12/4/2014 | | 12/8/2014 | | FAIL |
Troy James
|
|
|
manual j report floor plan does not match submitted plans
|
Routing - PLANNING | 12/4/2014 | | 12/4/2014 | | FAIL |
David Moser
|
|
|
The appeal deadline ends at 5pm on 12-5-14.
|
Routing PW Sewer Rating | 12/4/2014 | | 12/4/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PUBLIC WORKS | 12/3/2014 | | 12/4/2014 | | FAIL |
Jennifer Bruner
|
|
|
see Hillside
|
Routing PW Grading-Hillside | 12/3/2014 | | 12/3/2014 | | FAIL |
Jason C. Taylor
|
|
|
Need revised grading plans showing the driveway removed from the front yard. Jason Taylor ###-####
|
Routing - Addressing | 12/3/2014 | | 12/3/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 12/2/2014 | | | |
|
|
|
|