Permit Information
Permit NumberBLD14-03486
StatusFinaled
Name MCALVAIN CONSTRUCTION INC
Site Address 1600 W GOWEN RD
Project NameSkyWest Maintenance Hangar TI
Customer Number 
ePlanReviewYes
Description
(SKYWEST MAINTENANCE HANGAR – Tenant Improvement) This permit is to build out a new 132,770 square feet Maintenance Hangar. Shell permit approved under BLD14-02926. Grading, drainage and Utilities approved under BLD14-02396. All work per approved plans. Scope of work includes: [construction of new interior non-bearing partition walls to create: a training room, a break-room, seven offices, a conference room, men’s / women’s locker rooms, nine storage rooms, a sheet metal shop, and a parts warehouse], installation of new accessible doors / hardware, installation of all new electrical, installation of all new mechanical, installation of new plumbing, and interior finishes in compliance with ch. 8 of the 2012 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. NOTE: racks installed over 8ft. in height will require a separate Building Permit prior to installation. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  1/6/2016 DONE
Telephone call  1/6/2016 DONE
emailed Able-he sent me revised final values so i emailed him back with the corrected fees that are due
Print Statement  12/28/2015 DONE
Third Notice 11/14/201512/10/2015 DONE
Third Notice 10/17/201511/9/2015 DONE
Second Notice 9/25/201510/12/2015 DONE
Mailed 10-13-15
First Notice 9/4/20159/15/2015 DONE
Mailed 9/16/15
BLD-Final8/25/20158/25/20158/25/2015APASS
DetailsJim Storey
DOC - Permit Finaled8/25/20158/25/20158/25/2015PPASS
DetailsJim Storey
Permanent Occupancy  8/25/2015 DONE
DetailsChristina Prado
FIRE-Final Inspection8/20/20158/21/20158/21/2015APASS
DetailsJim Page
Previously noted items repaired, Life fire safety inspection passed/complete
BLD-Conference8/20/20158/20/20158/20/2015PPASS
DetailsJim Storey
Phone #: ###-####
BLD-Final8/20/20158/20/20158/20/2015PPASS
DetailsJim Storey
Phone #: ###-#### temp ok pending others
FIRE-Final Inspection8/19/20158/19/20158/19/2015PFAIL
DetailsTroy Cobbley
1) Breakroom 108 exit has been moved from interior doors to exterior door. Need approval with the 118 person occupant load.
2) Provide emergnecy light in Fire Pump Rm
3)Repair Emergency Lights in Locker Rms.
4) Provide signage at Fire Pump Rm.
5) Provide exit discharge lighting without photo cells and timers per discussion.
FIRE-Final Inspection8/14/20158/14/20158/14/2015PCANC
DetailsJim Page
Tom Phone #: ###-####
Zoning Approval8/13/20158/13/20158/13/2015 DONE
DetailsCody Riddle
Isolated site, interior to airport campus, no planning inspection necessary.
BLD-Framing/Rough-in6/25/20156/25/20156/25/2015PPASS
DetailsJim Storey
Early afternoon - Lenard Phone #: ###-####
BLD-Ceiling Grid Inspection6/5/20156/8/20156/8/2015APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy
BLD-Framing/Rough-in5/8/20155/11/20155/11/2015APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy alcoves ok to cover hanger side rated wall.
BLD-Wall cover4/24/20154/27/20154/27/2015APART
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy progression gyp ok hanger side/raised floor ok
BLD-Framing/Rough-in4/14/20154/15/20154/15/2015APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy hard ceillings and raised floor ok
BLD-Wall cover3/27/20153/30/20153/30/2015APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy ok to cover office/ fire joint ok across hanger side.
BLD-Framing/Rough-in3/19/20153/20/20153/20/2015APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy
BLD-Framing/Rough-in3/10/20153/10/20153/10/2015PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Brian Murphy framing ok
BLD-Framing/Rough-in3/3/20153/4/20153/4/2015APASS
DetailsJim Storey
Framing / Firestopping Phone #: ###-#### Inspection requested via web by Brian Murphy end of 2hr and 1hr walls ok to cover.
BLD-Framing/Rough-in2/25/20152/26/20152/26/2015APART
DetailsJim Storey
Brian Phone #: ###-#### review top of wall detail/ rfi to arch for wide flange perpendiclur penatratio. menbrane.
Issue PAID IN FULL permit  2/2/2015 DONE
DetailsChristina Prado
Print Occupancy Form  2/2/2015 DONE
DetailsChristina Prado
Telephone call  1/28/2015 DONE
DetailsCandy A. Nichols
ws not a call but an email to Tracey @ McAlvain. Gave her the total fees due
OVERRIDE  1/27/2015  
Permit Ready to Issue  1/27/2015 DONE
NEEDS- GC form, Certificate of Value, ACHD, and RP (RP received CAN)
Routing - PLAN CHECK1/26/2015 1/26/2015 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  1/26/2015 DONE
Plan assigned to (TLW)12/5/2014 1/26/2015 PASS
DetailsTim L. Woodard
Plan Resubmittals Level 3 TI - ePlanReview - Skywest Maintenance Hangar
Routing - MECHANICAL1/20/2015 1/20/2015 PASS
DetailsTroy James
Plan resubmittals received  1/12/2015 DONE
DetailsTim L. Woodard
Routing - FIRE12/5/201412/5/201412/19/2014 PASS
DetailsScott Arellano
Attached comments to plans.
1st review completed  12/19/2014 DONE
DetailsTim L. Woodard
Routing - PUBLIC WORKS12/5/2014 12/17/2014 FAIL
DetailsTim L. Woodard
Refer to changemarks on drawings. TLW
Routing - PLAN CHECK12/5/2014 12/17/2014 FAIL
DetailsTim L. Woodard
Refer to Eplan Change marks. TLW
Routing - MECHANICAL12/5/2014 12/12/2014 FAIL
DetailsTroy James
Routing - Erosion and Sediment12/5/2014 12/8/2014 PASS
DetailsEvan Jenkins
(SKYWEST MAINTENANCE HANGAR) Tenant improvement for a new aircraft maintenance hangar with office space and warehouse space attached. Tenant improvements for office, parts, and shop areas. Work to include... Shell permit was done under BLD14-02926.
Routing - PLUMBING12/5/2014 12/8/2014 PASS
DetailsBill VanDegrift
Install a RPBP on water line to hose reel after eyewash station as required.
Routing - PLANNING12/5/2014 12/8/2014 PASS
DetailsCody Riddle
Cody Riddle - CUP14-00050
Routing - Addressing12/5/2014 12/5/2014 PASS
DetailsEmily Dixon
Pending Assignment by JCB12/5/2014 12/5/2014 DONE
DetailsJason Blais
Plan Reviewer's activity  12/4/2014 PASS
Plan intake approved
Intake Approval  12/4/2014 PASS
DetailsJason Blais
Prescreen approved by Carl Westfall and plan review fees paid.
Application received  12/3/2014 DONE
Application submitted via PDS Online on Dec 3 2014 9:14AM