Plan Reviewer's activity | | | 1/13/2020 | | DONE |
Javier Guzman
|
|
|
added a Men’s & Women’s restroom fixture ratio approval see attached document, any changes in workforce Men’s & Women’s percentages may require alterations to the restrooms.
|
Third Notice | | 5/9/2015 | 6/9/2015 | | DONE |
|
|
|
|
Second Notice | | 3/13/2015 | 5/4/2015 | | DONE |
|
|
|
|
First Notice | | 2/28/2015 | 3/3/2015 | | DONE |
|
|
|
mailed 3-3-15
|
BLD-Final | 2/17/2015 | 2/18/2015 | 2/18/2015 | A | PASS |
Mike Jordan
|
|
|
Dylan Phone #: ###-####. Ok for perm occ.
|
Permanent Occupancy | | | 2/18/2015 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 2/12/2015 | 2/13/2015 | 2/13/2015 | A | PART |
Mike Jordan
|
|
|
Dillion Phone #: ###-####. Ok for temp occ. Needs to provide ADA restroom sign provide flusher on toilet in mens restroom on turning side, Provide a high/low drinking fountain. A racking permit is also required.
|
Temporary Occupancy | 2/13/2015 | 5/14/2015 | 2/13/2015 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 2/12/2015 | 2/12/2015 | 2/12/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 2/10/2015 | 2/11/2015 | 2/11/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide the four exit discharge lights as per the approved plans.
|
FIRE-Sprinkler Rough-in | 2/9/2015 | 2/9/2015 | 2/9/2015 | P | CANC |
Troy Cobbley
|
|
|
wrong permit called in.
|
BLD-Ceiling Grid Inspection | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PASS |
Mike Jordan
|
|
|
Dillon Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/3/2015 | 2/4/2015 | 2/4/2015 | A | FAIL |
Mike Jordan
|
|
|
Dillon Phone #: ###-####. Needs to provide clips on permiter to prevent the runners from spreading.
|
BLD-Framing/Rough-in | 1/13/2015 | 1/14/2015 | 1/14/2015 | A | PASS |
Mike Jordan
|
|
|
Dillion Phone #: ###-####. INterior steel stud framed walls for restroom package. Hardlids are ok, but still needs fire sprinkler rough in inspection.
|
BLD-Framing/Rough-in | 1/7/2015 | 1/7/2015 | 1/7/2015 | P | PASS |
Mike Jordan
|
|
|
Dillon Phone #: ###-####. All interior steel stud framed walls except for restrooms ok. N o grid at this time.
|
BLD-Framing/Rough-in | 1/6/2015 | 1/7/2015 | 1/7/2015 | A | NR |
Mike Jordan
|
|
|
Dillon Phone #: ###-####. No city approved plans. Electrical rough in completed. Ok to start one side with shhretrock. Contractor will recall inspection for this afternoon or tomorrow morning.
|
Permit Ready to Issue | | | 1/5/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/5/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/5/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 12/12/2014 | 12/12/2014 | 12/30/2014 | | PASS |
Carl D Madsen
|
|
|
**Priority Review** Level 3 TI - ePlanReview - Diversified Fluid Solutions
|
Routing - PLAN CHECK | 12/30/2014 | | 12/30/2014 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2014 | | DONE |
|
|
|
|
1st review completed | | | 12/29/2014 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/12/2014 | | 12/29/2014 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 12/12/2014 | 12/12/2014 | 12/22/2014 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Solid Waste | 12/12/2014 | | 12/22/2014 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - MECHANICAL | 12/18/2014 | | 12/18/2014 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 12/12/2014 | | 12/16/2014 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 12/12/2014 | | 12/12/2014 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Environmental | 12/12/2014 | | 12/12/2014 | | PASS |
Rick Christenson
|
|
|
As long as manufacturing processes do not differ from current facility at 335 N Steelhead Way, no additional Pretreatment requirements exist. If new, wet processes are being added, please contact Boise City Pretreatment (###-####) for evaluation and regulatory guidance.
|
Routing PW Sewer Rating | 12/12/2014 | | 12/12/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 12/12/2014 | | 12/12/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 12/12/2014 | | 12/12/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 12/12/2014 | | PASS |
Jason Blais
|
|
|
Prescreen passed by Carl Westfall and plan review fees paid.
|
Pending Assignment by JCB | 12/12/2014 | | 12/12/2014 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 12/10/2014 | | FAIL |
|
|
|
(12-10-14) Please refer to the annotations on the plan intake checklist. The circled items require resolution. CJW
|
Application received | | | 12/8/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 8 2014 4:56PM
|