First Notice | | 1/3/2016 | 1/12/2016 | | DONE |
|
|
|
mailed 1-13-16
|
Permanent Occupancy | | | 12/24/2015 | | DONE |
|
|
|
|
BLD-Final | 3/10/2015 | 3/10/2015 | 3/11/2015 | A | PASS |
Dave Hannah
|
|
|
Katz Phone #: ###-####
|
BLD-Final | 3/6/2015 | 3/9/2015 | 3/10/2015 | A | NR |
Dave Hannah
|
|
|
Katz Phone #: ###-####
|
FIRE-Final Inspection | 3/6/2015 | 3/9/2015 | 3/10/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 3/5/2015 | 3/6/2015 | 3/6/2015 | A | FAIL |
Forrest France
|
|
|
Missing one exit sign per approved plans at the center hallway, provide approved style hardware at the second exit, post "door to remain...." signage at the main entry/exit, remove manual thumbturn and provide keyed lock as discussed at the main entry/exit, post fire extinguishers at locations per plan and discussion.
|
Permit Ready to Issue | | | 1/28/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/28/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/28/2015 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/23/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
spoke with contractor over question on RR wall finish. contaced architect as the permit has not been issued yet.
|
Plan assigned to (AJS) | 12/16/2014 | 12/16/2014 | 1/2/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
The Pain Center
|
Routing - PLAN CHECK | 12/16/2014 | | 1/2/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 1/2/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/2/2015 | | DONE |
|
|
|
|
Routing - FIRE | 12/16/2014 | 12/16/2014 | 12/24/2014 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Sewer Rating | 12/16/2014 | | 12/16/2014 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 12/16/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 12/16/2014 | | 12/16/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 12/16/2014 | | 12/16/2014 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 12/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 10 2014 8:10AM
|