Third Notice | | 11/14/2015 | 12/10/2015 | | DONE |
|
|
|
|
Second Notice | | 10/22/2015 | 11/9/2015 | | DONE |
|
|
|
sent in mail
|
First Notice | 9/29/2015 | 9/29/2015 | 10/12/2015 | | DONE |
Candy A. Nichols
|
|
|
sent in mail
|
Permanent Occupancy | | | 10/1/2015 | | DONE |
|
|
|
|
BLD-Final | 9/28/2015 | 9/29/2015 | 9/29/2015 | P | PASS |
Jim Storey
|
|
|
Building E // Russ Phone #: ###-####
|
DOC - Permit Finaled | 9/29/2015 | 9/29/2015 | 9/29/2015 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PASS |
Jim Page
|
|
|
Life fire safetyy passed/complete
|
BLD-Footing | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | PASS |
Jim Storey
|
|
|
Russ Phone #: ###-####
|
BLD-Footing | 8/11/2015 | 8/11/2015 | 8/11/2015 | P | PASS |
Jim Storey
|
|
|
Russ Phone #: ###-####
|
BLD-Foundation | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PASS |
Mike Jordan
|
|
|
Russ Phone #: ###-####
|
OVERRIDE | | | 7/10/2015 | | |
|
|
|
|
Print Occupancy Form | | | 7/10/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/10/2015 | | DONE |
|
|
|
called Russ to let know resubmittals/plan mod are ready-we need RP, GC & rev cert of val
|
Issue PAID IN FULL permit | | | 7/10/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/10/2015 | | DONE |
|
|
|
resubmittal complete-need RP, GC & rev cert of val
|
Plan assigned to (TLW) | 6/10/2015 | | 7/9/2015 | | PASS |
Tim L. Woodard
|
|
|
Plan Mod
|
Routing - PLAN CHECK | 7/9/2015 | | 7/9/2015 | | PASS |
Tim L. Woodard
|
|
|
Recieved all new engineering for buildings and approved modification accordingly. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/8/2015 | | DONE |
|
|
|
resubmittals recieved 2 sets of ESC control plans-took to Evan
|
Routing - PLAN CHECK | 6/25/2015 | | 6/25/2015 | | PEND |
Tim L. Woodard
|
|
|
Cannot process modification. Appears a new metal building supplier was used; however, only engineering for the foundation was submitted. I contacted applicant and requested clarification. If a new metal building supplier is to be used than a new set of structural calculation is needed for the building. TLW
|
Plan resubmittals received | | | 6/10/2015 | | DONE |
|
|
|
resubmittals received 2 sets of sheet F-1 & F-2, 2 sets of foundation cals, & 2 sets of engineering-took to Tim W along with the permit that was in the drawer taht was ready
|
Telephone call | | | 6/1/2015 | | DONE |
|
|
|
Called Russ. Left a message letting him know if he would like an extension for this permit he would need to send a separate letter to Jason B
|
Extend Review Timeline | | | 6/1/2015 | | DONE |
|
|
|
180 days granted by JCB. See attached documents
|
Telephone call | | | 5/28/2015 | | DONE |
|
|
|
Left a message for Russ that the permit will expire in 11 days. Also spoke with Robert, but he didn't seem to know what I was talking about so he said he would look into it.
|
Expiration Notice | 5/19/2015 | 6/10/2015 | 5/19/2015 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 1/16/2015 | | |
|
|
|
|
Telephone call | | | 1/16/2015 | | DONE |
Christina Prado
|
|
|
Called Tom to advise permit is ready for pick up
|
Permit Ready to Issue | | | 1/16/2015 | | DONE |
Christina Prado
|
|
|
Pending GC, RP & revised cert of value
OWNER IS GC 5-1-15 blh
|
Plan assigned to (JCM) | 12/10/2014 | | 1/15/2015 | | PASS |
John Menard
|
|
|
1st Review Complete 12/20/2014
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2015 | | DONE |
John Menard
|
|
|
|
Plan resubmittals received | | | 1/14/2015 | | DONE |
Candy A. Nichols
|
|
|
runner brought in resubmittals-3 each sheet, S-1, S-2, S-3, S-4. 3 calcs from Lochsa & 2 response letters-took to John M.
|
Routing Off Site - STRUCTURAL | 1/7/2015 | | 1/12/2015 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 1/12/2015 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review comment. JCM
|
Plan resubmittals received | | | 1/6/2015 | | DONE |
Christina Prado
|
|
|
Received three sets of revised structural calcs; Docs taken to John Menard for further review
|
Plan resubmittals requested | | | 1/5/2015 | | DONE |
John Menard
|
|
|
E-mailed the arcitect a copy of the second structural review requesting additional calculations. JCM
|
Routing Off Site - STRUCTURAL | 12/24/2014 | | 1/5/2015 | | FAIL |
John Menard
|
|
|
|
Routing - Erosion and Sediment | 12/24/2014 | | 12/29/2014 | | PASS |
Evan Jenkins
|
|
|
(ALL PURPOSE STORAGE) - BUILDING E - To construct a new 13,800 square foot, one story, pre-engineered steel storage building and related site improvements. This will be an open structure used only for storage of recreational vehicles, trailers and boats.
|
Routing - PLAN CHECK | 12/24/2014 | | 12/24/2014 | | PASS |
John Menard
|
|
|
|
1st review completed | | | 12/24/2014 | | FAIL |
|
|
|
Failed Plan Check.
|
Plan resubmittals received | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
received resubmittals-3 each-struc calcs for both struc and foundations-SWPPP including sheets C-1, C-2, C-3, ESC-1-sheets LS1-0,A0.0,S0.01, S0.02, S0.03, S1.01, S5.01, & S5.02-had customer insert plans and took to John M to see if needs to be sent out to off site engineering
|
Plan resubmittals received | | | 12/24/2014 | | DONE |
Candy A. Nichols
|
|
|
as per John M. sent out for off site Eng plan review
|
Routing - FIRE | 12/20/2014 | | 12/24/2014 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Route to Impact Fee Review | 12/11/2014 | 12/16/2014 | 12/23/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLAN CHECK | 12/18/2014 | | 12/20/2014 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 12/20/2014 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Plan resubmittals requested | | | 12/18/2014 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesing revisions. JCM
|
Routing - PLUMBING | | | 12/18/2014 | | PASS |
Daryl Spivey
|
|
|
no plumbing no review
|
Routing Off Site - STRUCTURAL | 12/11/2014 | | 12/17/2014 | | FAIL |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 12/11/2014 | | 12/17/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING | 12/17/2014 | | 12/17/2014 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Design Review | | | 12/17/2014 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Erosion and Sediment | 12/17/2014 | | 12/17/2014 | | FAIL |
Evan Jenkins
|
|
|
|
Routing PW Street Lights | 12/16/2014 | | 12/17/2014 | | PASS |
Mike D Hedge
|
|
|
Street lighting to be placed on power pole.
|
Routing PW Drainage | 12/11/2014 | | 12/16/2014 | | PASS |
Brian Murphy
|
|
|
oked previous approvals
|
Routing - PLANNING Land Div | 12/11/2014 | | 12/11/2014 | | PASS |
Dave Abo
|
|
|
|
Routing - Addressing | 12/11/2014 | | 12/11/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/10/2014 | | DONE |
|
|
|
|
Intake Approval | | | 12/10/2014 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/10/2014 | | DONE |
|
|
|
|
Pending Assignment by JCM | 12/10/2014 | | 12/10/2014 | | DONE |
John Menard
|
|
|
|
Application received | | 12/10/2014 | | | |
|
|
|
|