Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD14-03565
StatusFinaled
Name WEATHERTIGHT ROOFING INC
Site Address 10955 W FAIRVIEW AVE
Project NameQuilt Crossing TI
Customer Number 
ePlanReviewYes
Description
(QUILT CROSSING) Permit is to combine an existing 2,155 square foot space and a 10,345 square foot space (BLD12-00127) to create a new tenant space that is 12,500 square feet. This permit is approved contingent upon adhering to the approved plans on file and attached structural calculations. Work includes: painting, carpeting, lighting and select demolition to a non-bearing partition wall. Previous demolition of interior partition walls and construction of new restrooms were done under BLD13-02393. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  5/24/2016 DONE
Left a message for David. Has no value for ELE, but there is a permit
Second Notice 4/22/20165/11/2016 DONE
Mailed 5-12-16
First Notice3/10/20163/10/20164/12/2016 DONE
DetailsMike Jordan
Mailed 4-13-16
Print Occupancy Form  3/18/2016 DONE
Permanent Occupancy  3/18/2016 DONE
DOC - Permit Finaled3/10/20163/10/20163/10/2016PPASS
DetailsMike Jordan
No electrical work was done.
BLD-Final3/9/20163/10/20163/10/2016PPASS
DetailsMike Jordan
Plans are at the desk Phone #: ###-#### Inspection requested via web by David Krings
BLD-Final3/9/20163/9/20163/9/2016PNR
DetailsMike Jordan
Verify no ELE needed, please - David Phone #: ###-####. no approved plans on site.
FIRE-Final Inspection12/17/201512/18/201512/18/2015APASS
DetailsTroy Cobbley
Life safety passed
BLD-Framing/Rough-in12/7/201512/8/201512/8/2015APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by David Krings. Interior steel studs and header for new opening ok.
Issue PAID IN FULL permit  11/20/2015 DONE
DetailsChristina Prado
Inspection Record Card- Bld  11/20/2015 DONE
DetailsChristina Prado
Expiration Notice11/12/201512/4/201511/12/2015 DONE
DetailsBrittany Hill
Plan assigned to (JG)12/18/201412/18/201411/3/2015 PASS
DetailsJavier Guzman
1st review completed, Quilt Crossing TI Expires 12/6
Routing - PLAN CHECK11/3/2015 11/3/2015 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  11/3/2015 DONE
Permit Ready to Issue  11/3/2015 DONE
***ALL REQUIRMENTS MET 11-19-15 //CEV NEED GC and certificate of value
Extend Review Timeline  7/1/2015 DONE
DetailsJason Blais
Extension request received and approved for another 180 days.
Routing - PUBLIC WORKS12/18/2014 12/19/2014 PASS
DetailsJennifer Bruner
1st review completed  12/19/2014 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK12/18/2014 12/19/2014 FAIL
DetailsJavier Guzman
ePlan
Routing - Addressing12/18/2014 12/18/2014 PASS
DetailsEmily Dixon
Intake Approval  12/18/2014 PASS
DetailsAdele J Schaffeld-Griffin
Application received  12/11/2014 DONE
Application submitted via PDS Online on Dec 11 2014 1:45PM