BLD-Final | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
DOC - Permit Finaled | 7/22/2015 | 7/22/2015 | 7/22/2015 | P | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 7/21/2015 | 7/21/2015 | 7/21/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
Plan Modification Accepted | | | 7/17/2015 | | DONE |
|
|
|
new manual j report
|
Routing - MECHANICAL | 7/17/2015 | | 7/17/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Energy code compliance | 5/15/2015 | 5/18/2015 | 5/18/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-####5
|
BLD-Framing/Rough-in | 5/13/2015 | 5/14/2015 | 5/15/2015 | P | PASS |
Dave Hannah
|
|
|
Brian Phone #: ###-####
|
BLD-Framing/Rough-in | 5/12/2015 | 5/13/2015 | 5/13/2015 | A | FAIL |
Phil Shearer
|
|
|
Brian Phone #: ###-#### CN posted
|
BLD-Wall Bracing | 5/13/2015 | 5/13/2015 | 5/13/2015 | P | PASS |
Phil Shearer
|
|
|
Brian Phone #: ###-####
|
BLD-Foundation | 3/19/2015 | 3/20/2015 | 3/21/2015 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 3/12/2015 | 3/16/2015 | 3/16/2015 | P | PASS |
Phil Shearer
|
|
|
Eric Phone #: ###-####
|
PubWorks Subgrade Approval | 3/16/2015 | 3/16/2015 | 3/16/2015 | | PASS |
Jim Wyllie
|
|
|
|
Issue PAID IN FULL permit | | | 2/26/2015 | | DONE |
Candy A. Nichols
|
|
|
|
OVERRIDE | | | 1/28/2015 | | |
|
|
|
|
Plan assigned to (JG) | | 12/19/2014 | 1/28/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 1/08 TH L2 Hillside* Pending fire
|
Telephone call | | | 1/28/2015 | | DONE |
Candy A. Nichols
|
|
|
called Doug to let know permit is ready and how much is owed.
left message on phone # ###-####. It's not Doug's phone #
|
Routing - PLAN CHECK | 1/27/2015 | | 1/28/2015 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 1/28/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/28/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/28/2015 | | DONE |
|
|
|
|
Routing - FIRE | 1/20/2015 | 1/20/2015 | 1/27/2015 | | PASS |
Scott Arellano
|
|
|
Approved. Attached plan review report to case.
|
Telephone call | | | 1/26/2015 | | DONE |
Scott Arellano
|
|
|
Sent email to applicant requesting information for the remaining correction item.
|
Plan resubmittals received | | | 1/16/2015 | | DONE |
|
|
|
Two copies of A-101 taken to Javier blh
|
Routing - FIRE | 1/14/2015 | 1/14/2015 | 1/14/2015 | | FAIL |
Scott Arellano
|
|
|
Attached comments to case. Emailed and faxed plan review report with correction items to applicant.
|
Routing - PLAN CHECK | 1/7/2015 | | 1/14/2015 | | PASS |
Javier Guzman
|
|
|
Pending fire review
|
Plan resubmittals received | | | 1/12/2015 | | DONE |
Christina Prado
|
|
|
Received two sets revised plan sheets marked A-103, S-101, S-105, S-106 & S-107 as well as two sets revised structural calcs; Plans stamped and taken to Javier for further review
|
Routing - PLAN CHECK | 12/23/2014 | | 1/7/2015 | | FAIL |
Javier Guzman
|
|
|
emailed applicant review report
|
1st review completed | | | 1/7/2015 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 12/22/2014 | 12/19/2014 | 12/23/2014 | | FAIL |
Scott Arellano
|
|
|
Emailed and faxed plan review comments to applicant.
|
Routing - Erosion and Sediment | 12/22/2014 | | 12/22/2014 | | PASS |
Evan Jenkins
|
|
|
(SITE PREP INSPECTION REQUIRED):
WUI Zone A, Class A Roof, Permit for the construction of a new 3082 sq. ft., one story single family dwelling with 3 bedrooms, 3 bathrooms, approximately 289.5 sq. ft. of covered patio/porch, ft., and a 973 sq. ft. attached garage per the approved plans,
|
Routing - MECHANICAL | 12/19/2014 | | 12/22/2014 | | PASS |
Troy James
|
|
|
|
Application received | | 12/19/2014 | 12/19/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 12/19/2014 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - PLANNING | 12/19/2014 | | 12/19/2014 | | PASS |
Susan Riggs
|
|
|
|
Routing - Addressing | 12/19/2014 | | 12/19/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 12/19/2014 | | 12/19/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 12/19/2014 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Recd Pcfee & Taken To Pln CK | | | 12/18/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 12/18/2014 | | FAIL |
|
|
|
Foundation and structural sections of plans need engineering stamp
|
Application received | | 12/18/2014 | | | |
|
|
|
|