Third Notice | | 6/15/2015 | 6/16/2015 | | DONE |
|
|
|
|
Print Statement | | | 6/16/2015 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 5/14/2015 | 6/10/2015 | | DONE |
|
|
|
Mailed out 6-10-15
|
First Notice | | 4/3/2015 | 5/4/2015 | | DONE |
|
|
|
|
BLD-Final | 3/23/2015 | 3/24/2015 | 3/24/2015 | A | PASS |
Jim Storey
|
|
|
Call half hour before // David Phone #: ###-####
|
Permanent Occupancy | | | 3/24/2015 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/16/2015 | 3/16/2015 | 3/16/2015 | P | PASS |
Forrest France
|
|
|
Verified previous correction items for completion.
|
BLD-Ceiling Grid Inspection | 3/11/2015 | 3/12/2015 | 3/12/2015 | P | PASS |
Jim Sly
|
|
|
David Phone #: ###-####
|
FIRE-Conference | 3/10/2015 | 3/10/2015 | 3/11/2015 | P | DONE |
Troy Cobbley
|
|
|
David and I went over life safety requirements. I noted that an address needs to be posted at the top of the hill/property entrance and door hardware provided. Plan review comments have been modified to show the fuel pump
|
BLD-Framing/Rough-in | 2/26/2015 | 2/27/2015 | 2/27/2015 | A | PASS |
Jim Storey
|
|
|
cover // david Phone #: ###-####
|
Permit Ready to Issue | | | 1/22/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/22/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/22/2015 | | DONE |
|
|
|
|
Routing - FIRE | 1/14/2015 | 1/14/2015 | 1/15/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to case.
|
Plan assigned to (CDM) | 12/29/2014 | 12/29/2014 | 1/15/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 1/15/2015 | | 1/15/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/15/2015 | | DONE |
Candy A. Nichols
|
|
|
we need GC form filled out as well as rev cert of val
|
Routing - Addressing | 1/14/2015 | | 1/14/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PLAN CHECK | 12/29/2014 | | 1/6/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 1/6/2015 | | FAIL |
|
|
|
|
Routing - FIRE | 12/29/2014 | 12/29/2014 | 1/5/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed comments to architect. Attached report to case.
|
Routing PW Sewer Rating | 12/29/2014 | | 12/30/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Environmental | 12/29/2014 | | 12/30/2014 | | PASS |
Rick Christenson
|
|
|
approved per RWC
|
Routing - PLANNING | 12/29/2014 | | 12/30/2014 | | PASS |
Sarah Schafer
|
|
|
Exterior paint approved through the building plans.
|
Routing - PUBLIC WORKS | 12/29/2014 | | 12/30/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 12/29/2014 | | PASS |
|
|
|
|
Routing - Addressing | 12/29/2014 | | 12/29/2014 | | FAIL |
Emily Dixon
|
|
|
Address changed to 2996 W Airport Way.
|
Intake Approval | | | 12/23/2014 | | FAIL |
|
|
|
Provide the form 518 checklist with all required items.
|
Application received | | | 12/18/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2014 4:47PM
|