Permit Information
Permit NumberBLD14-03660
StatusFinaled
Name TBL CONSTRUCTION
Site Address 1201 E FRANKLIN ST
Project NameNew Residence
Customer Number 
ePlanReviewYes
Description
***Plan modification to the engineered shear wall hold downs see attached engineering dated 5-31-2015***Plan Modification to garage area adding a door and moving window to the right. JG***Demo permit on file BLD13-03487*** Permit for the construction of a new 2951 sq. ft., two story (first story 1480 sq. ft., basement is 1471 sq. ft.) single family dwelling with 3 bedrooms, 2 bathrooms, approximately 328 sq. ft. of covered patio’s/porches and 647 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/9/20168/10/20168/10/2016APASS
DetailsPhil Shearer
Home will be open Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
DOC - Permit Finaled8/10/20168/10/20168/10/2016PPASS
DetailsPhil Shearer
BLD-Energy code compliance6/18/20156/18/20156/18/2015PPASS
DetailsDave Hannah
BLD-Wall cover6/17/20156/18/20156/18/2015APASS
DetailsDave Hannah
Corrections will be made today. Call Tim if any issues.

Thank you. Tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
BLD-Framing/Rough-in6/12/20156/12/20156/12/2015PPART
DetailsDave Hannah
Call tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin c/n on site ok to insulate
BLD-Wall Bracing6/3/20156/3/20156/4/2015PPART
DetailsDave Hannah
ok to cover ext but slill needs hold downs installed on inside
BLD-Conference6/3/20156/3/20156/3/2015PPASS
DetailsDave Hannah
Call Lucas if any problems. Lucas will be onsite.

Thank you much. Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
CHANGE STATUS TO (ISS)  6/2/2015 DONE
Plan assigned to (JG)6/1/20156/1/20156/1/2015 PASS
DetailsJavier Guzman
Routing - PLAN CHECK6/1/2015 6/1/2015 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  6/1/2015 DONE
Plan Modification Accepted  6/1/2015 DONE
DetailsTisha Gallop
modification for engineered placement of hold-downs. The original hold-downs were missed at foundation stage out on site and this is to correct that.
BLD-Wall Bracing5/22/20155/22/20155/22/2015PNR
DetailsJim Storey
Shear only. Framers are on site. Call if any problems

Thanks much. Tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin not built per aproved pan or engineering.
BLD-Wall Bracing5/20/20155/20/20155/21/2015PFAIL
DetailsDave Hannah
Re inspection for shear panels. Framing crew and siding crew are on site

Thank you much. Tim Phone #: ###-#### Inspection requested via web by Timothy Beaudoin
BLD-Wall Bracing5/18/20155/18/20155/18/2015PFAIL
DetailsPhil Shearer
plans are hanging inside the closet near the front door. Call Tim if any problems. Thank you much Phone #: ###-#### Inspection requested via web by Timothy Beaudoin. Missing hold downns, Shear nailing wrong CN posted
Plan Modification Accepted  5/12/2015 DONE
new manual j
Routing - MECHANICAL5/12/2015 5/12/2015 PASS
DetailsTroy James
resubmitted manual j
BLD-Wall Bracing5/8/20155/8/20155/8/2015AFAIL
DetailsDave Hannah
Shear inspection. gate code is 1201

Call Tim if any issues. Thank you. Phone #: ###-#### Inspection requested via web by Timothy Beaudoin no plans on site
BLD-Foundation4/8/20154/8/20154/9/2015PPASS
DetailsDave Hannah
Phone #: 6971241 >> Inspection requested via mobile web by Heron
BLD-Footing4/7/20154/7/20154/7/2015PPASS
DetailsDave Hannah
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing4/6/20154/6/20154/7/2015PNR
DetailsDave Hannah
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
Telephone call  3/31/2015 DONE
called Catherine to let her know that Javier made the corrections requested for modification and that I batched stamped them and the three drawings are in the approved folder in eplan// KRS
BLD-Foundation2/8/20152/9/20152/10/2015PPASS
DetailsDave Hannah
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing1/30/20151/30/20151/30/2015PPASS
DetailsDave Hannah
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
BLD-Footing1/28/20151/29/20151/30/2015ACANC
DetailsDave Hannah
Heron Phone #: ###-####
BLD-Footing1/30/20151/30/20151/30/2015APASS
DetailsDave Hannah
Heron Phone #: ###-#### basement ftgs
Issue PAID IN FULL permit  1/26/2015 DONE
DetailsCandy A. Nichols
Inspection Record Card- Bld  1/26/2015 DONE
DetailsCandy A. Nichols
OVERRIDE  1/13/2015  
Plan assigned to (JG)1/6/20151/6/20151/13/2015 PASS
DetailsJavier Guzman
1/16 F L1 ePlan**
Routing - PLAN CHECK1/6/2015 1/13/2015 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  1/13/2015 DONE
Permit Ready to Issue  1/13/2015 DONE
1st review completed  1/13/2015 DONE
DetailsJavier Guzman
Intake Approval  1/6/2015 PASS
Routing - MECHANICAL1/6/2015 1/6/2015 PASS
DetailsTroy James
Routing - PLANNING1/6/2015 1/6/2015 PASS
DetailsAndrea Tuning
Routing - Addressing1/6/2015 1/6/2015 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS1/6/2015 1/6/2015 PASS
DetailsJennifer Bruner
Application received  12/22/2014 DONE
Application submitted via PDS Online on Dec 22 2014 8:59AM
Intake Approval  12/22/2014 FAIL
DetailsCandy A. Nichols
need manual j's, res check, revised sheet needs to be stamped by engineer and can not be done in red (you can do in black or blue), also need set backs