Letter of compliance/Occupancy | | | 2/28/2017 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PASS |
Tony Young
|
|
|
Cris Phone #: ###-####
|
DOC - Permit Finaled | 1/13/2017 | 1/13/2017 | 1/13/2017 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Conference | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Tony Young
|
|
|
Cris Phone #: ###-####,, ?s on hand rail
|
BLD-Energy code compliance | 5/1/2015 | 5/4/2015 | 5/4/2015 | A | PASS |
Tony Young
|
|
|
Chris Phone #: ###-####
|
BLD-Energy code compliance | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, seal pack ok
|
BLD-Framing/Rough-in | 4/27/2015 | 4/28/2015 | 4/28/2015 | A | PART |
Tony Young
|
|
|
Chris Phone #: ###-####,, ok to insulate,, c/n on back side of truss engineering
|
BLD-Wall cover | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | PASS |
Jim Storey
|
|
|
Cris Phone #: ###-####
|
Plan Modification Accepted | | | 4/15/2015 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 4/15/2015 | | 4/15/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | DEFR |
Jim Storey
|
|
|
Cris Phone #: ###-#### out of time
|
BLD-Foundation | 4/1/2015 | 4/2/2015 | 4/2/2015 | A | PASS |
Jim Sly
|
|
|
Wall // Mana Phone #: ###-####
|
BLD-Foundation | 4/1/2015 | 4/2/2015 | 4/1/2015 | A | CANC |
Tony Young
|
|
|
Mana Phone #: ###-####,, late am
|
BLD-Footing | 3/31/2015 | 4/1/2015 | 4/1/2015 | P | PASS |
Tony Young
|
|
|
Mana Phone #: ###-####,, garage
|
BLD-Foundation | 2/5/2015 | 2/5/2015 | 2/5/2015 | P | PASS |
Phil Shearer
|
|
|
Wall // Mana Phone #: ###-####
|
BLD-Foundation | 2/4/2015 | 2/5/2015 | 2/5/2015 | A | NR |
Tony Young
|
|
|
Wall // Mana Phone #: ###-####,, wip
|
BLD-Footing | 2/2/2015 | 2/2/2015 | 2/2/2015 | P | PART |
Tony Young
|
|
|
Mana Phone #: ###-####,, basement ftgs,, wip,, ok
|
Issue PAID IN FULL permit | | | 1/29/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 1/9/2015 | | |
|
|
|
|
Plan assigned to (JG) | | 12/24/2014 | 1/9/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 1/07 W L1**
|
Telephone call | | | 1/9/2015 | | DONE |
|
|
|
called Chris- left message that permit is ready for pick up and remaining fees
|
Routing - PLAN CHECK | 1/7/2015 | | 1/9/2015 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 1/9/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/9/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 1/9/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/2/2015 | | 1/7/2015 | | FAIL |
Javier Guzman
|
|
|
emailed review report to applicant
|
1st review completed | | | 1/7/2015 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 12/30/2014 | | 1/6/2015 | | PASS |
Sue Cummings
|
|
|
signed off in planning review report by Sue Cummings 12/30/14
|
Routing - MECHANICAL | | | 1/2/2015 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 12/24/2014 | | 12/30/2014 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 12/30/2014 | | 12/30/2014 | | PASS |
Jennifer Bruner
|
|
|
|
Route to Impact Fee Review | 12/24/2014 | 12/27/2014 | 12/29/2014 | | PASS |
Cindy M. Gould
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/24/2014 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/24/2014 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/24/2014 | | DONE |
Christina Prado
|
|
|
|
Application received | | 12/24/2014 | | | |
|
|
|
|