Plan Reviewer's activity | | | 3/21/2018 | | DONE |
|
|
|
Took drawings to records
|
First Notice | | 6/6/2015 | 6/10/2015 | | DONE |
|
|
|
Mailed out 6-10-15
|
Permanent Occupancy | | | 5/27/2015 | | DONE |
|
|
|
|
BLD-Final | 5/22/2015 | 5/26/2015 | 5/26/2015 | P | CANC |
Jim Sly
|
|
|
Ray Phone #: ###-####
|
BLD-Final | 5/22/2015 | 5/26/2015 | 5/26/2015 | A | PASS |
Jim Sly
|
|
|
Ray Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 4/29/2015 | 4/29/2015 | 4/29/2015 | P | PASS |
Jim Sly
|
|
|
Ray Phone #: ###-####
|
BLD-Framing/Rough-in | 3/27/2015 | 3/30/2015 | 3/30/2015 | P | PASS |
Jim Sly
|
|
|
Ray Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2015 | 3/26/2015 | 3/26/2015 | A | NR |
Phil Shearer
|
|
|
Ray Phone #: ###-####
|
Telephone call | | | 2/26/2015 | | DONE |
|
|
|
called Ray- told him his permit is ready for pick up and that we need GC form and Certificate of Value- I went ahead and added the final building permit fees because he said he was the GC and the value will be the same as the initial
|
Issue PAID IN FULL permit | | | 2/26/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 2/25/2015 | | |
|
|
|
|
Plan assigned to (CJW) | 1/30/2015 | | 2/25/2015 | | PASS |
Carl Westfall
|
|
|
COMMUNITY PARTNERS (15 days - Feb 18)
|
Routing - FIRE | 2/20/2015 | | 2/25/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
1st review completed | | | 2/25/2015 | | FAIL |
|
|
|
Failed plan check.
|
Routing - PLAN CHECK | 2/25/2015 | | 2/25/2015 | | PASS |
Carl Westfall
|
|
|
The drawings were approved with redlines
|
Routing - PUBLIC WORKS | 2/25/2015 | | 2/25/2015 | | PASS |
Beverly Mountain
|
|
|
Toilet removed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2015 | | |
|
|
|
|
Print Occupancy Form | | | 2/25/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Permit Ready to Issue | | | 2/25/2015 | | DONE |
Candy A. Nichols
|
|
|
need GC and rev cert of val
|
Plan resubmittals received | | | 2/23/2015 | | |
|
|
|
received 2 copies of main floor plan, detail & schedules, and slab plan & utility- gave to CJW
|
Routing - PLAN CHECK | 2/12/2015 | | 2/20/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - PLUMBING | 2/9/2015 | | 2/12/2015 | | |
|
|
|
No review required
|
Routing - Erosion and Sediment | 2/8/2015 | | 2/9/2015 | | PASS |
Evan Jenkins
|
|
|
(COMMUNITY PARTNERSHIPS OF IDAHO, INC - CARE PLUS) 1st time occupancy for existing approx. 4,688 square foot space. Used as a billing center for a company that serves disabled children and adults (i.e. office). Building constructed under permit BLD99-02305. Two new toilet rooms, new toilet/shower room, drinking fountains, break room sink, interior walls, interior doors, suspended acoustical ceilings, interior concrete slab on grade, interior finishes
|
Routing - PLANNING | 2/5/2015 | | 2/8/2015 | | PASS |
Sarah Schafer
|
|
|
Approved. Use is allowed in the L-OD zone. Building design and landscape was approved under DRH97-00178.
|
Routing - Addressing | 1/30/2015 | | 2/2/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 2/2/2015 | | 2/2/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | | | 2/2/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Pending Assignment by JCB | 1/29/2015 | | 1/30/2015 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/29/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/29/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/29/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/9/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | 1/9/2015 | | | |
|
|
|
|