Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-00060
StatusFinaled
Name STETSON HOMES INC
Site Address 5848 E WOODCROSS DR
Project Name 
Customer Number 
ePlanReviewNo
Description
WUI Zone B, Class A Roof, Permit for the construction of a new 2531 sq. ft., two story (first story 1299 sq. ft., second story 1232 sq. ft.) single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately 630 sq. ft. of covered patio’s/porches/balconies and 957 sq. ft. attached garage per the approved plans, plan review report and any notations. A-1 zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/22/20162/23/20162/23/2016APASS
DetailsPhil Shearer
Rustin Phone #: ###-####
DOC - Permit Finaled2/23/20162/23/20162/23/2016PPASS
DetailsPhil Shearer
BLD-Final2/16/20162/17/20162/17/2016AFAIL
DetailsPhil Shearer
Justin Phone #: ###-####. Landing for stairs off deck, Fire caulking in garage.
BLD-Aging Inspection2/5/20162/5/20162/5/2016 PEND
DetailsPhil Shearer
BLD-Aging Inspection2/4/20162/4/20162/4/2016 PEND
DetailsPhil Shearer
BLD-Energy code compliance9/22/20159/23/20159/23/2015APASS
DetailsJim Storey
Insulation // Rustin Phone #: ###-####
BLD-Framing/Rough-in9/22/20159/23/20159/23/2015APASS
DetailsJim Storey
Rustin Phone #: ###-####
BLD-Wall Bracing9/8/20159/9/20159/9/2015PFAIL
DetailsPhil Shearer
Rustin Phone #: ###-####. Shear nailing
BLD-Framing/Rough-in9/8/20159/9/20159/9/2015PPART
DetailsPhil Shearer
Rustin Phone #: ###-####. Upstairs window headers not to plans. OK to insulate
BLD-Foundation6/22/20156/22/20156/22/2015PPASS
DetailsPhil Shearer
Wall // Jay Phone #: ###-####
BLD-Footing6/19/20156/19/20156/19/2015PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Ben Sears
BLD-Footing6/19/20156/19/20156/19/2015PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Ben Sears
PubWorks Subgrade Approval6/11/20156/11/20156/11/2015 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Issue PAID IN FULL permit  5/7/2015 DONE
OVERRIDE  5/4/2015  
Plan assigned to (JG) 1/14/20155/4/2015 PASS
DetailsJavier Guzman
1st review completed, 1/30 F L2 Hillside** Pending Hillside, PW and Mech
Inspection Record Card- Bld  5/4/2015 DONE
Meeting  5/4/2015 DONE
notified the customer about the amount due
Routing PW Grading-Hillside5/4/2015 5/4/2015 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.

Routing - PUBLIC WORKS5/4/2015 5/4/2015 PASS
DetailsConnie Baumgartner
Case Summary (BLD)  5/4/2015 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  5/4/2015 DONE
Permit Ready to Issue  5/4/2015 DONE
NEED RP
Plan resubmittals received  5/1/2015 DONE
Site grading & drainage plan
Routing - MECHANICAL4/30/2015 4/30/2015 PASS
DetailsTroy James
Routing - PLAN CHECK2/6/2015 3/4/2015 PASS
DetailsJavier Guzman
Plan resubmittals received  3/3/2015 DONE
DetailsCandy A. Nichols
resubmitttals-received 2 sheets #2 foundation-took to Javier G.
Routing - PLAN CHECK1/27/2015 2/6/2015 FAIL
DetailsJavier Guzman
emailed review report to applicant
Plan resubmittals received  2/3/2015 DONE
received 3 new sets of plans- put on Javier's desk
Routing - FIRE1/22/2015 1/27/2015 PASS
DetailsScott Arellano
No comments attached.
1st review completed  1/27/2015 FAIL
DetailsJavier Guzman
Routing - PLAN CHECK  1/27/2015 FAIL
DetailsJavier Guzman
emailed applicant review report
Routing - Erosion and Sediment1/21/2015 1/22/2015 PASS
DetailsEvan Jenkins
(SITE PREP REQUIRED PRIOR TO EARTH DISTURBANCE)
New Single Family Home on Woodcross. Need Valid RP prior to issuance of Permit
Routing - MECHANICAL1/20/2015 1/21/2015 FAIL
DetailsTroy James
Emailed corrections to Air Comfort zone.
Routing - PLANNING1/20/2015 1/20/2015 PASS
DetailsColleen T Carroll
Routing - Addressing1/14/2015 1/20/2015 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS1/20/2015 1/20/2015 FAIL
DetailsConnie Baumgartner
FAILED BY HILLSIDE
Routing PW Grading-Hillside  1/20/2015 FAIL
DetailsJason C. Taylor
Grading plans need signed by engineer. Set backs have been reduced to zero by retaining wall. Jason Taylor ###-####.
Intake Approval  1/14/2015 PASS
DetailsCandy A. Nichols
Recd Pcfee & Taken To Pln CK  1/9/2015 DONE
DetailsCandy A. Nichols
Plans ACCEPTED BY PLAN TECH  1/9/2015 DONE
DetailsCandy A. Nichols
Intake Approval  1/9/2015 FAIL
DetailsCandy A. Nichols
need 3rd set of grading & drainage, engineered stamp on foundation sheets
Application received 1/9/2015